Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 1
Structured Solutions External Dependency Management Approach ........................................................................................... 2
Overview ................................................................................................................................................................................. 2
Manage External Dependencies ............................................................................................................................................... 3
Identify External Dependencies ............................................................................................................................................... 4
Definitions ........................................................................................................................................................................... 4
Enabling Microsoft Project Tools ........................................................................................................................................ 4
Tips & Tricks ....................................................................................................................................................................... 4
Code and Tag/Flag External Dependencies ............................................................................................................................. 4
Definitions ........................................................................................................................................................................... 4
Enabling Microsoft Project Tools ........................................................................................................................................ 6
Exercise – Code and Flag External Dependencies ............................................................................................................... 7
Tips & Tricks ....................................................................................................................................................................... 8
Exercise – Use SSI Tools to See External Dependency Codes and Flags ........................................................................... 8
Link External Dependencies from Predecessors in the Providing Project and to Successors in the Receiving Project ........... 9
Definitions ........................................................................................................................................................................... 9
Enabling Microsoft Project Tools ........................................................................................................................................ 9
Tips & Tricks ....................................................................................................................................................................... 9
Exercise – Adding Predecessors to External Outputs and Successors to External Inputs ................................................. 10
Synchronize Dates in Providing and Receiving Project......................................................................................................... 11
Definitions ......................................................................................................................................................................... 11
Enabling Microsoft Project Tools ...................................................................................................................................... 11
Tips & Tricks ..................................................................................................................................................................... 11
Exercise – Use Microsoft Project Tools to Combine Projects A & B ............................................................................... 13
Using SSI Link and Synchronize Tools ................................................................................................................................. 14
SSI Tools - Link Inputs/Outputs ........................................................................................................................................ 14
Exercise – Use SSI Tools to Link and Synchronize Projects A & B ................................................................................. 15
SSI Tools - Sync Remote Projects ..................................................................................................................................... 17
Exercise – Use SSI Tools Sync Remote Projects ............................................................................................................... 19
SSI Tools - Synchronization Options ................................................................................................................................ 20
Schedule Roles Explained ......................................................................................................................................................... 21
Schedule Integrator ................................................................................................................................................................ 21
Schedule Contributor (Subproject owner) ............................................................................................................................. 22
Supported Environments............................................................................................................................................................ 23
Separate Subprojects are Always Controlled by Their Respective Subproject Owner .......................................................... 23
Summary Master Project with Milestones from Subprojects ................................................................................................. 25
Split one Project into Two or More Subprojects .................................................................................................................... 26
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 2
Structured Solutions External Dependency Management Approach
Overview
A “Program” is often a collection of Projects and Subprojects. Often, these projects and subprojects are
owned and maintained by separate teams or organizations within a company or even by different
companies.
For the most part Projects and Subprojects have Internal Dependencies between their own tasks and
milestones. In many cases, however, an External Dependency exists where the predecessor or
successor is part of another project or subproject. Common names External Dependencies include
“Givers” and “Receivers”, “Inputs” and “Outputs” or just “Cross Project Dependencies”
Managing a Program having External Dependencies requires explicit identification of these
dependencies which may include a Unique Identification Code or number and Tags to show which
project Provides the external dependency (the “Giver” or “Provider”) and who Receives the external
dependency (the “Receiver” or “User”).
In the example below, Internal Dependencies are shown using Black arrows and External Dependencies
are show using Red arrows.
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 3
Manage External Dependencies
The process steps for managing External Dependencies is shown graphically using a “process wheel”.
A description of each step in the process, along with tips, tricks and tools used by the professional
scheduler and schedule analyst are described in the following sections of this document.
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 4
Identify External Dependencies
Definitions
External Dependencies exist in a Project or Subproject when the Predecessor or Successor of a
scheduled item is found in another project or subproject.
External Dependency Code is a Unique Code or number that is used by both the Provider and the
Receiver of the item. The Unique Code is usually determined and assigned by the Provider.
Enabling Microsoft Project Tools
Simple tables in a spreadsheet can be used to log each instance of a Dependency that will be produced
by one project (the “Giver” or “Provider”) and Received by another project (the “User” or “Receiver”)
Tips & Tricks
Have the Receiving Project or Subproject initiate the creation of External Dependencies. If done any
other way you may end up with items being Provided that no other Project or Subproject needs.
Code and Tag/Flag External Dependencies
Definitions
Giving a Unique Code to External Dependencies (#001 and #002 in the example below) is only a part of
its identity. Knowing the direction of the dependency (i.e., which project provides and which project
receives) is the other part. #001 is an Output from the perspective of Project A and it should be tagged
(or flagged) as such in Project A. From the perspective of Project B, however, the same item is an
Input.
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 5
Example of External Dependency Codes & Tags/Flags are shown in the table below: External Dependency Tag or Flag is used to show
the direction of the External Dependency. Since
there are two ends of an External Dependency, the
providing end will Tag or Flag the dependency as
an “Output” and the receiving end of the
dependency will Tag or Flag the dependency as an
“Input”. The example below shows two
Milestones that represent an External Dependency
from Project A to Project B.
External Dependency Relationship Types can be any of the following:
One-to-One - the Output from one project is
used by just one other project.
One-to-Many – the Output from one project is
used by more than one project.
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 6
Enabling Microsoft Project Tools
Microsoft Project has Text and Flag fields that are useful for Coding and Tagging/Flagging External
Dependencies. Select One Text field and designate its use for External Dependency Codes. Pick one
Flag field and designate its use to tag the Output side of the External Dependency. Pick another Flag
field and designate its use to tag the Input side of the External Dependency. Figure 1 – Unsynchronized Example (not yet linked to source and target project) of Code and Tag/Flag used by a project Providing 2
External Dependencies and Receiving 1 External Dependency using Microsoft Project Text and Flag fields
Figure 2- Unsynchronized Example (not yet linked to source and target project) of Code and Tag/Flag used by a project Receiving 2
External Dependencies and Providing 1 External Dependency using Microsoft Project Text and Flag fields
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 7
Exercise – Code and Flag External Dependencies
Practice – Session Exercise
Start a new project in Microsoft Project with a Top level Summary in row 1 named “Project A
Requirements”
1. Add the following tasks: a. Write the Requirements Document (3 Day Duration) b. Requirements Document Published by Project A (Zero Day Milestone) c. Write the Requirements Verification Document (2 Day Duration) d. Requirements Verification Document Published by Project A (Zero Day Milestone) e. Receive Test Report From Project B (Zero Day Milestone) f. Review Test Report (2 Day Duration)
2. Add the columns named Text9, Flag8, Flag9 3. Rename Text9 to “Ext Dep Code”, Flag8 to “Input” and Flag9 to “Output” 4. Enter “ProjA-001” in Text9 of item b. above (“Requirements Document Published by
Project”) and mark it as an Output by setting Flag9 = Yes
5. Enter “ProjA-002” in Text9 of item d. above (“Requirements Verification Document Published by Project A”) and mark it as an Output by setting Flag9 = Yes
6. Enter “ProjB-001” in Text9 of item e. above (“Receive Test Report From Project B”) and mark it as an Input by setting Flag8 = Yes
7. Save this project as ProjectA.mpp
Start a new project in Microsoft Project with a Top level Summary in row 1 named “Project B
(Product)”
1. Add the following tasks: a. Requirements Document Published by Project A (Zero Day Milestone) b. Design Product Via Requirements (2 Day Duration) c. Requirements Verification Document Published by Project A (Zero Day Milestone) d. Test and Verify Product Performance (2 Day Duration) e. Deliver Test Report (Zero Day Milestone)
2. Add the columns named Text9, Flag8, Flag9 3. Rename Text9 to “Ext Dep Code”, Flag8 to “Input” and Flag9 to “Output” 4. Enter “ProjA-001” in Text9 of item a. above (“Requirements Document Published by
Project”) and mark it as an Input by setting Flag8 = Yes
5. Enter “ProjA-002” in Text9 of item c. above (“Requirements Verification Document Published by Project A”) and mark it as an Input by setting Flag8 = Yes
6. Enter “ProjB-001” in Text9 of item e. above (“Receive Test Report From Project B”) and mark it as an Output by setting Flag9 = Yes
7. Save this project as ProjectB.mpp
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 8
Tips & Tricks
External Dependency Code Assignment - Have the Providing Project or Subproject assign the Code for
External Dependencies. Using a convention that includes the provider’s project code can be helpful.
“ProjA-001”, for example makes it clear that the item is provided by Project A. The Output codes
shown in the example below will work well, but it’s hard to tell where the item is coming from.
Use SSI Tools to code and Tag/Flag External Dependencies
Use the tool named Identify
Input/Output on the SSI
Analysis Tools menu to enter
Codes and Flags for External
Dependencies
1. Select a row in a project that represents an External
Dependency
2. Click Identify Input/Output on the SSI Analysis Tools
menu
3. Enter the I/O Code. If the active project is the Provider,
make sure the code has not
already been used by listing
all existing Outputs by
checking “Show Outputs”
4. If the active project provides the item, Check Output. If
the active project receives the
item Check Input
5. Click Apply to Selected Row 6. Use the Up/Down button to
go to the next or previous
item if needed
Exercise – Use SSI Tools to See External Dependency Codes and Flags
Practice – Session Exercise
Open ProjectA from the previous exercise
1. Click Identify Input/Output from the SSI Analysis Tools Multi Project menu 2. Use Go Next and Go Previous to see the External Dependency Codes and Flags used in the project 3. Click Show Outputs and Show Inputs to see all External Dependencies used in the project
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 9
Link External Dependencies from Predecessors in the Providing Project and to Successors in the Receiving Project
Definitions
If an External Dependency is an Output of the active project, it should have one or more predecessors.
Notice that “Requirements Document Published by Project A” is preceded by the task named “Write the
Requirements Document”. In this example, “Write the Requirements Document” is a predecessor to
“Requirements Document Published by Project A” using a Start to Start link with a 1 day lag.
If an External Dependency is an Input to the active project, it should have one or more Successors.
Notice that “Requirements Document Published by Project A” is succeeded by the task named “Design
Product Via Requirements”. In this example, “Requirements Document Published by Project A” is a
predecessor to “Design Product Via Requirements” using a Finish to Start link with 0 lag.
Enabling Microsoft Project Tools
Display the Microsoft field named Predecessors and Successors or display the Predecessor/Successor
form. Add Predecessors to Outputs and Successors to Inputs.
Tips & Tricks
Use zero duration milestones for External Dependencies in Microsoft Project. Though this is not a
requirement, it makes for easy identification of External items in a project. Notice in the example below
that External Dependencies (shown in yellow) are Milestones.
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 10
Exercise – Adding Predecessors to External Outputs and Successors to External Inputs
Practice – Session Exercise
Open ProjectA from the previous exercise
Add Predecessors to External Outputs
1. Link the Task named “Write the Requirements Document” to the Milestones named “Requirements Document Published by Project A” using a Start to Start dependency with 1 day of lag
2. Link the Task named “Write the Requirements Verification Document” to the Milestones named “Requirements Verification Document Published by Project A” using a Finish to Start dependency
with 0 lag
Add Successors to External Inputs
3. Link the Milestone named “Receive Test Report From Project B” to the task named “Review Test Report” using a Finish to Start dependency with 0 lag
Add Remaining Dependencies in ProjectA
4. Link the Task named “Write the Requirements Document” to the Task named “Write the Requirements Verification Document” using a Finish to Start dependency with 0 lag
5. Link the Task named “Write the Requirements Verification Document” to the Task named “Review Test Report” using a Finish to Start dependency with 0 lag
Open ProjectB from the previous exercise
Add Successors to External Inputs
1. Link the Milestone named “Requirements Document Published by Project A” to the task named “Design Product Via Requirements” using a Finish to Start dependency with 0 lag
2. Link the Milestone named “Requirements Verification Document Published by Project A” to the task named “Test and Verify Product Performance” using a Finish to Start dependency with 0 lag
Add Predecessors to External Outputs
1. Link the Task named “Test and Verify Product Performance” to the Milestones named “Deliver Test Report” using a Finish to Start dependency with 0 lag
Add Remaining Dependencies in ProjectB
2. Link the Task named “Design Product Via Requirements” to the Task named “Test and Verify Product Performance” using a Finish to Start dependency with 0 lag
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 11
Synchronize Dates in Providing and Receiving Project
Definitions
Synchronized External Dependencies have the same date and completion status in the providing and
receiving project. Both the date and the completion status is usually determined by the provider.
Enabling Microsoft Project Tools
Post status in Microsoft Project to tasks that precede External Dependencies that are Output. Inform
stakeholders in receiving or using project of the Date and Completion status of External Dependencies
so they can apply the same date and status to External Dependencies that are Inputs.
Tips & Tricks
After Identifying, Coding, Tagging/Flagging and Linking External Dependencies you can make a
consolidated project, sometimes called an Integrated Master Schedule (IMS) and synchronize External
Dependences as follows:
Combine Projects/Subprojects into a Consolidated IMS
Record an Interim Plan before Synchronizing External Dependencies to enable Change Tracking in the Consolidated IMS
Link and Synchronize External Dependencies in the Consolidated IMS
Perform Analysis of Schedule Variances caused by Synchronized External Dependencies
Distribute the Synchronized dates of External Dependencies to the projects Receiving/Using External Dependency items
Combine Projects/Subprojects into a Consolidated IMS
Consolidated IMS Preparation:
Calendars
Resource Tables
Fields
Project Status date
A consolidated project (or IMS) and all its subprojects should be
using a common set of Calendars, Resource Tables and Fields.
The IMS and each subproject should have the same Project Status
date with all tasks updated through the Project Status date.
Insert Subprojects into the
Consolidated IMS using
Microsoft Project tools.
1. Select Subproject from the Insert group on Microsoft
Project’s Project menu
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 12
2. Browse to the location of each project/subproject to
insert into the Consolidated
IMS
3. Remove the option to Link to Project
4. Press the Insert button
Inserted Projects in a Consolidated IMS
Consolidated Project with Project A and Project B Combined
Projects have not been Synchronized yet
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 13
Exercise – Use Microsoft Project Tools to Combine Projects A & B
Practice – Session Exercise
Open a new Project in Microsoft Project and set its Project Start date to 2/23/2017 (Use Project
Information from the Project menu in Microsoft Project)
1. Select Subproject from the Insert group on Microsoft Project’s Project menu
2. Browse to the location of ProjectA and ProjectB
3. Remove the option to Link to Project 4. Press the Insert button
5. Save this combined project as “IntegratedProject-A-Plus-B.mpp”
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 14
Using SSI Link and Synchronize Tools
SSI Tools - Link Inputs/Outputs
Link and Synchronize External Dependencies in the Consolidated IMS
Use the SSI Tool named Link
Inputs/Outputs on the Multi
Project group of the SSI
Analysis Tools menu to find,
link and synchronize External
Dependencies
1. Press the button named Code & Flag Field Setup and
select the Microsoft Project
fields used for the External
Dependency Code and Flags
Note - The setup page
includes a user defined
project field that is used to
Log each link or link error.
2. Press the button named Link to find, link and synchronize
External Dependencies
3. Check the Log field for the following
a. Linked @ Date & Time b. Link Error No Successor c. Link Error No
Predecessor
Note the Option Named Copy Current Input/Output Dates to
When using this option, the current Dates for Inputs and Outputs are recorded in a date field before
the synchronizaton is performed. This enables change tracking of the schedule impact caused by
linking Outputs to their respective Inputs
Note the Option Named If Output is 100% Complete then
Use this option to pass actual comletion status from Outputs to their respective Input.
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 15
After Linking, Input/Output dates are Synchronized in each Project
Exercise – Use SSI Tools to Link and Synchronize Projects A & B
Practice – Session Exercise
Open the combined project named “IntegratedProject-A-Plus-B.mpp” from the previous Exercise
1. Click Link Inputs/Outputs from the Multi Project group on the SSI Analysis Tools menu and select the options shown below
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 16
2. Select Code & Flag Field Setup and Apply the Setup shown below
3. Click Link on the form named Link Inputs/Outputs
4. Save the Project as “IntegratedProject-A-Plus-B.mpp”
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 17
SSI Tools - Sync Remote Projects
Importing or Exporting Synchronized Dates Between a Local Project and Remote Projects
Now that Input/Output dates have been synchronized in a combined project, you can export (or
“Post”) those dates to each respective individual project or import (“Get”) those dates from the
Integrated Project using Sync Remote Projects
1. Select Sync Remote Projects from the Multi Project group of the SSI Analysis Tools menu 1. Browse and select Remote Projects 2. Post Dates to Remote Subprojects uses Output dates in the current project to synchronize
Input dates in remote projects
3. Get Dates from Remote Subprojects does just the opposite. It uses the Output dates in Remote subprojects to update matching Input dates in the current project
Export (“Post”) Output dates from the Integrated Project to corresponding Inputs in Remote Projects
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 18
Import (“Get”) Output dates from the Integrated Project to corresponding Inputs in Remote Projects
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 19
Inputs and Output dates are Synchronized after using Post (to Export dates to Individual Projects) or
Get (to import dates from Consolidated Project)
Exercise – Use SSI Tools Sync Remote Projects
Practice – On your own
Open the combined project named “IntegratedProject-A-Plus-B.mpp” from the previous Exercise
or open ProjectA.mpp or ProjectB.mpp
1. Use Sync Remote Projects to Get or Post External Dependency dates using the instructions shown in the previous section.
2. Try the same using Options on the page named Synchronization Options (See the instructions below)
3. Try generating Synchronization Reports
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 20
SSI Tools - Synchronization Options
Select the tab named Synchronization Options to make changes to the Text and Flag fields used to
Code and Tag/Flag Inputs and Outputs. This page also shows options for Synchronization of Inputs
and Outputs in remote Subprojects.
Select the option named “If Output is 100% Complete Make Input 100%
Complete if Input is a Milestone” to
automatically post status to zero
duration Inputs in the remote
subproject if the corresponding
Output is complete
Select the option named “Log Synchronization Transaction
Notes… to record each Post or Get
transaction in the active project
Options when Posting dates from the
active project to remote projects:*
Select the option named “Post Output Dates in this Project…” to
record Output dates from the active
project to matching Outputs in
remote projects
Select the option named “Post Input Dates in this Project…” to record
Input dates from the active project to
matching Inputs in remote projects
Options when Getting dates from
remote projects:*
Select the option named “Get Outputs in Remote Projects…” to
record Output dates found in Remote
Projects to the corresponding Inputs
in the active project
Input/Output Identification Settings:
Select the button named “Change Settings” to change the fields used to
Code and Tag/Flag Inputs and
Outputs
Different treatment of Input/Output matching when using
Get vs. Post actions:
*When Getting dates from remote projects, SSI tools looks
for Outputs in remote projects having codes that match
Inputs in the active project. (Matching via. Output-to-
Input).
When Posting to remote projects Outputs are matched to
Outputs and Inputs are matched to Inputs (Matching via.
Output-to-Output and Input-to-Input)
Why the difference?
The reason for different treatment of Input/Output
matching when using Get vs. Post is based on the different
role of a Schedule Integrator (who uses Post from an IMS)
vs. that of a Schedule Contributor (who may use Get while
working in a subproject)
See the illustration of “Scheduler Roles” on the next page
for a pictorial explanation of the
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 21
Schedule Roles Explained
Schedule Integrator
The role of a Schedule Integrator is to combine two or more subprojects and link them through their
Inputs and Outputs as an Integrated Master Schedule or IMS. Once linked, the IMS has calculated the
cumulative effect of Outputs that drive Inputs. The Schedule Integrator may be responsible for Posting
synchronized dates to subprojects.
In an IMS, there is often a “daisy chain” effect where an output in one subproject is being driven by
external dependencies from another subproject. The IMS calculates more accurate dates for Inputs and
Outputs because it takes “daisy chaining” into account.
Once the IMS is integrated, synchronized Inputs in the IMS should be posted to corresponding Inputs in
subprojects (Input in IMS to Input in subproject). The process of posting Input dates this way
automatically synchronizes Outputs in subprojects as well. But… just to be sure, SSI Tools includes an
option to post IMS Output dates to corresponding Outputs in subprojects (Output in IMS to Output in
subproject)
Figure 3 - Integrated Master Schedule (IMS) is a schedule that combines two or more subprojects
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 22
Schedule Contributor (Subproject owner)
The role of a Schedule Contributor is to develop a credible schedule that yields accurate dates -
including the dates for their own Outputs. From time to time, a Schedule Contributor may need to Get
dates from the IMS. When doing this action, the subproject needs to receive Output dates from the IMS
and use those dates to synchronize Inputs dates in their own project. (IMS Output to Input in the
subproject)
Figure 4 - Subproject Gets its Input dates from outputs in the IMS or another Subproject
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 23
Supported Environments
Separate Subprojects are Always Controlled by Their Respective Subproject Owner
In this environment, Subprojects (Microsoft project files) are owned and maintained by more than one
project team. Though they may be combined from time to time (as an IMS) to synchronize External
Inputs/Outputs between teams, they are never “locked” or “checked out” to the IMS “integrator” and are
always available for use by their individual owner.
1. Two or more Subprojects are developed and maintained by separate “owning” teams 2. Teams collaborate via a “dependency workshop” to identify External Inputs & Outputs and
agree on their scope/content and deadline dates
3. From time to time, Subprojects are integrated into an IMS and External Inputs & Outputs are validated and synchronized
o Using Microsoft Project - Insert Subproject tools (with or without “Link to Project” option)
o Using SSI Tools – Link Inputs/Outputs
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 24
4. Synchronized Dates for Inputs are given to Subproject owners for implementation in each subproject
o Using SSI Tools – Synchronize External Dependencies
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 25
Summary Master Project with Milestones from Subprojects
In this environment, Subprojects (Microsoft project files) are owned and maintained by more than one
project team. Subprojects are never combined but a “Summary Master Project” containing Key
Milestones only is maintained at the “Program” level
1. A collection of projects or subprojects (Project portfolio) is developed by separate “owning” teams
2. From time to time, information from the Project portfolio is queried for use in a Summary Master Project
o Using SSI Tools – Synchronize External Dependencies
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 26
Split one Project into Two or More Subprojects
In this environment, the team has developed an Integrated Master Schedule (IMS) and wants to split it
into Subprojects (Microsoft project files) that can be owned and maintained by more than one project
team.
1. Identify “split” points of the IMS’s Work Breakdown Structure 2. Log the dependencies that are external to each split
o Using SSI Tools – Automatic Identification of External Dependencies
http://www.ssitools.com/
Cross Project Dependencies
386 Rim Trail, Prescott, Arizona | www.ssitools.com | E-mail: ssi@ssitools.com Page 27
3. Separate the Subprojects o Using SSI Tools - Distribute
http://www.ssitools.com/Recommended