Citation preview
Micro Planner X-Pert
Micro Planning International LtdJanuary 2013
America – Australia – Europe Project Management Software ,
Training and ConsultancyBy Raf Düa
1/3/2013 1
Critical Path Scheduling
18th Century – Bar Charts Invented
1/3/2013 2©2012 Micro Planning International Ltd
“…a longer or a shorter space of time may be most commodiously and advantageously represented by a longer or a shorter line.”
Joseph Priestley (1733-1804)William Playfair (1759-1823)
Critical Path Scheduling19th Century – Bar Charts In effective use
1/3/2013 3
Critical Path SchedulingEarly 20th Century – Gantt developed Production
Management Systems for Factories
1/3/2013 4
Critical Path Scheduling20th Century – 1957 CPM Invented
1/3/2013 5
CPM is based on a logical networkDiagram!
Planning the logical precedes calculating the schedule
Critical Path Scheduling20th Century – 1961 PDM Invented
1/3/2013 6
As a manual process –drawing the logic precedes calculating the schedule
PMI / PMBOK® Guide6.1 – Plan schedule6.2 – Define Activities6.3 – Sequence Activities6.4 – Estimate Resources 6.5 – Estimate Durations6.6 – Develop Schedule6.7 – control Schedule
Micro Planner X-Pert
Critical Path Scheduling
If CPM scheduling is supposed to be a logical process why do so many tools and planners
work from 250 year old Bar Charts?
CPM was supposed to be an improvement!
1/3/2013 7
Critical Path Scheduling
1/3/2013 8
Micro Planner X-Pert is a true CPM System that supports the PMI schedule development process
And lets you chose the networking stylePDM or ADM
Micro Planner Products
Macintosh Windows
X-Pert XPM XPW
Manager MPM MPW
Plus•Product Training and Support•PM Consultancy, Consultancy and Mentoring
1/3/2013 9©2012 Micro Planning International Ltd
Micro Planner X-Pert
• Superior Project Management– Network logic - excellent visualisation– Time– Resource– Cost– Earned Value Program Management (EVPM)– Reports - with built in report writer
1/3/2013 10©2012 Micro Planning International Ltd
Micro Planner X-Pert
The preferred tool
• For the professional planner and scheduler
• Used for Project Management
• Has the best arithmetic scheduler for– Time– Resources– Costs
1/3/2013 11©2012 Micro Planning International Ltd
How X-Pert Works
• Network logic generated (not Bar Charts)• Critical Path networks using either
– ADM Arrow Diagram Method– PDM Precedent Diagram Method
• ADM means– No “lag drags”– Use of “ladders” for schedule compression
• Micro Planner uses “SS” & “FF” without lag drag
1/3/2013 12©2012 Micro Planning International Ltd
Micro Planner X-Pert
X-Pert Capacity
• Maximum Num of Tasks/ Activities 15,000
• Maximum number of Sub Projects 100• Maximum Num of Tasks/ Acts per Sub Project 1,364
• Maximum Number of Labels– Zones 500
– Responsibility 500
– Cost 500Maximum Number of Calendars 250
Maximum Number of Resources 250Maximum Number of Resources per Task/Act 20
1/3/2013 ©2012 Micro Planning International Ltd 13
Calendars
1/3/2013 ©2012 Micro Planning International Ltd
X-Pert translates the various duration types into abasic unit of numbers of minutes per day.
This is carried out by the Calendars
Calendars are constructed of several objects
•The number of hours per day•Non-Working days•Overtime days
1/3/2013 ©2007 Micro Planning International Ltd
Calendars
The objects are defined by the Weekly Cycle
The cycle defines for every day, how many hours are worked in 15 minute intervals
Thus a week can have days of varying length
X-Pert provides six standard calendars, the user may specify a further 194, giving a maximum of 200
15
Calendars
• The following record types need a calendar specification
• Work Breakdown Element
• Activity / Task
• Link
• Specified Nodes
• Resource Definition
1/3/2013 ©2007 Micro Planning International Ltd
1/3/2013 ©2007 Micro Planning International Ltd
Calendars
Micro Planner X-Pert durations for tasks may be expressed in either• Weeks• Days• Hours• Minutes• Shifts
Or in combination, eg
• Weeks and Days• Weeks, Days and Hours• Days and Hours• Shifts and minutes
17 1/3/2013 ©2012 Micro Planning International Ltd
CalendarsThe Calendars and Weekly Cycles are found on the desktop in their own folders
18
Micro Planner X-Pert
1/3/2013 ©2012 Micro Planning International Ltd
Calendars
The Standard six calendars provided in the Calendar Folder
19
Calendars
1/3/2013 ©2012 Micro Planning International Ltd 20
Calendar Folder showing standard X-Pert Calendars withthree user defined calendars
1/3/2013 ©2012 Micro Planning International Ltd
Calendars
Italicised characterIndicates aNon-Working day
Indicates Normal Working Day
21 1/3/2013 ©2012 Micro Planning International Ltd
Weekly CyclesThe Standard six weekly cycles provided in the WeeklyCycles Folder
22
1/3/2013 ©2007 Micro Planning International Ltd
Weekly CyclesStandard Five Day Weekly Cycle Showing Standard Eight Hour Day
23
Holidays
1/3/2013 ©2007 Micro Planning International Ltd 24
Ensure Overlay Cycle Is set to Holiday
Ensure Click Action is set to Change Cycle
Micro Planner X-Pert
Holidays
1/3/2013 ©2007 Micro Planning International Ltd 25
Ensure Overlay Cycle Is set to Holiday
Ensure Click Action is set to Change Cycle
Holidays
1/3/2013 ©2007 Micro Planning International Ltd 26
Place Mouse Pointer on Selected Holiday and click
1/3/2013 ©2012 Micro Planning International Ltd
Overtime Weekly CycleNote Extra Hours on Monday, Wednesday and Saturday Morning
27 1/3/2013 ©2012 Micro Planning International Ltd
Changing Cycles
28
Overtime Cycle
1/3/2013 ©2007 Micro Planning International Ltd 29
Select Overtime as Cycle Overlay
Place Mouse Pointer on Selected Overtime dayand click
1/3/2013 ©2007 Micro Planning International Ltd
Overtime Cycle
Overtime applied to day
Click on View Day Details
30
Micro Planner X-Pert
1/3/2013 ©2007 Micro Planning International Ltd
Overtime Cycle
Indicates the extra hours overtime
31 1/3/2013 ©2012Micro Planning International Ltd
Introduction to Resources
32
1/3/2013 ©2012Micro Planning International Ltd
Why Plan Resources?
• Need to know what resources are required by your project
• Thus the project manager MUST carry out resource planning
33
Resource Planning
• When you analyze a project on timing alone, the results show how soon the project can complete and what the deadlines are for each operation.
• Analysis of time does not tell you whether there are enough people to meet this schedule or whether the available machines can cope or how much cash you need.
• Time Analysis calculates when each operation could happen but to find
out when each operation should happen, you need to consider resources.
1/3/2013 ©2012 Micro Planning International Ltd 34
1/3/2013 ©2012 Micro Planning International Ltd
Time vs Resources
• Note: In calculating task durations some consideration has been made about resource levels – what we are discussing today is the optimisation of time and resources.
35
Defining Resource Information
• Before you can allocate resources to individual operations and analyze the workloads, you need to know the following information…
• The resources available to the project
• The cost of each resource (optional)
1/3/2013 ©2012 Micro Planning International Ltd 36
Micro Planner X-Pert
Resource profile
• Need to define the name of the Resource and how much is available and when e.g.
1/3/2013 ©2012Micro Planning International Ltd 37 1/3/2013 ©2012 Micro Planning International Ltd
Resource Types
• Having named the Resource need to know whether it is either– Normal
– Pool
38
1/3/2013 ©2012 Micro Planning International Ltd
Normal Resources
• Normal resources are those which are available for work each time period (day) as in people
39 1/3/2013 ©2012 Micro Planning International Ltd
Pool Resources
• Pool resources are ones which are actually consumed, e.g bricks
• Which may be replenished at various time periods
40
1/3/2013 ©2012 Micro Planning International Ltd
Utilisation of a Pool Resource
41
Replenishing Pool Resource
1/3/2013 ©2012 Micro Planning International Ltd 42
Micro Planner X-Pert
Resource Usage Method
• Before you enter a quantity, decide whether to specify how many resources are required (as a Rate) or
• whether to enter the Total number of People Days (or machine days, bricks, cash etc.) for the entire duration. (Also known as Level of Effort)
1/3/2013 ©2012 Micro Planning International Ltd 43 1/3/2013 ©2012 Micro Planning International Ltd
Rate or Total (1) ?
• Specifying usage as a Rate means the specified resource quantity will be used at a steady rate, regardless of length of day, week or duration. If the duration changes so does the total resource usage – the resource allocation is variable.
44
1/3/2013 ©2012 Micro Planning International Ltd
Rate or Total (2) ?
• If you specify a Total allocation then a specific amount of work time is spread evenly over the duration.
• As a result, no matter how much the duration changes, the overall allocation does not – it is constant.
• For example, imagine you have an operation that would take 1 person 4 days and you want it done in 2 days…
45 1/3/2013 ©2012 Micro Planning International Ltd
Rate or Total (3) ?
46
1/3/2013 ©2012 Micro Planning International Ltd
Rate or Total (4) ?
• You could express the work content either as a Rate of 2 people per day, or as a Total of 4 Man Days. At this point, the resource allocation is the same – 2 people per day for 2 days.
47 1/3/2013 ©2012 Micro Planning International Ltd
Rate or Total (5) ?
48
Micro Planner X-Pert
1/3/2013 ©2012 Micro Planning International Ltd
Rate or Total (6) ?
• However! If the duration were greater, say, 4 days then the Rate method uses 2 people per day for 4 days – a total of 8 man days.
• Whereas a Total allocation of 4 man days does not change – allocating 1 person per day for 4 days.
49
Resource Analysis
• Resource Analysis is the process by which you examine the availability of resources and figure out when tasks should be scheduled to work within that availability. During this process, the analysis tends to level out the usage of resources.
1/3/2013 ©2012 Micro Planning International Ltd 50
Resource Analysis (Cont)
• X-Pert Resource Analysis produces a schedule of dates for every task in the project showing when they should start and finish and also produces totals for the usage of resources throughout the project.
1/3/2013 ©2012 Micro Planning International Ltd 51
What Does Resource Analysis do?
The Parallel Scheduling by Resource Analysis could best be described as a bulldozer technique.
Imagine that every task on a project is able to happen at its earliest time –as calculated by Time Analysis. The result could be usage which fluctuates regardless of how many resources are available.
1/3/2013 ©2012 Micro Planning International Ltd 52
Preparing to Resource Schedule
1/3/2013 ©2012 Micro Planning International Ltd 53
What Does Resource Analysis do (2)?
The availability of resources can be set at a specific level – like a bulldozer blade.
As the Resource Analysis bulldozer starts up and moves forward from Time Now, it pushes the peaks of excess resources into the troughs of unused resources.
1/3/2013 ©2012 Micro Planning International Ltd 54
Micro Planner X-Pert
1/3/2013 ©2012 Micro Planning International Ltd
What Does Resource Analysis do (3)?
There will be times when there is too much earth for the required level to be reached.
There may also be insufficient earth to maintain continuity at the required level.
That is the theory, in practice it works like this…
55
The Time Analysis Schedule of Tasks
1/3/2013 ©2012 Micro Planning International Ltd 56
Resourcing After Day 1
1/3/2013 ©2012 Micro Planning International Ltd 57
Resourcing After Day 2
1/3/2013 ©2012 Micro Planning International Ltd 58
1/3/2013 ©2012 Micro Planning International Ltd
Resourcing After Day 3
59 1/3/2013 ©2012 Micro Planning International Ltd
Resourcing After Day 4
60
Micro Planner X-Pert
1/3/2013 ©2007 Micro Planning International Ltd
Splitting
61 1/3/2013 ©2007 Micro Planning International Ltd
Defining Minimum Split
62
Stretching Tasks in Resourcing
1/3/2013 ©2007 Micro Planning International Ltd 63 1/3/2013 ©2012 Micro Planning International Ltd
Resourcing after Day 1
64
Resourcing after Day 2
1/3/2013 ©2012 Micro Planning International Ltd 65
Resourcing after Day 4
1/3/2013 ©2012 Micro Planning International Ltd 66
Micro Planner X-Pert
Full Impact of Stretching Schedule by Day 7
1/3/2013 ©2012 Micro Planning International Ltd 67
Deadlines or Resources?
During Resource Analysis, you may meet a situation in which there are insufficient resources available for an task which has no more float. You are, therefore, faced with a decision – do you delay the task so that the project completion or some other deadline is delayed, or do you overload the availableresources?
1/3/2013 ©2012Micro Planning International Ltd 68
Types of Resource Analysis
The answer comes in the form of two types of Resource Analysis – Deadline Critical and Resource Critical.
• Deadline Critical calculates how many extra resources, if any, are needed to finish the project on time.
• Resource Critical calculates how much extra time, if any, is required for the existing resources to complete their allotted workloads.
1/3/2013 ©2012 Micro Planning International Ltd 69
Deadline Critical
1/3/2013 ©2012 Micro Planning International Ltd 70
Resource Limited
1/3/2013 ©2012 Micro Planning International Ltd 71
Time and resource thresholds
From the previous slides you may have imagined a certain amount of anarchy going on in X-Pert when the chips are down.
First, during a Deadline Critical analysis, the resources can be overloaded. You may have asked yourself two questions:
1. Can I limit this overloading so that, at least, it is within reason?
2. Is it possible to specify that some resources cannot be overloaded even during Deadline Critical analysis – a kind of selective Resource Critical analysis?
1/3/2013 ©2012 Micro Planning International Ltd 72
Micro Planner X-Pert
Time and resource thresholds (2)
During Resource Critical analysis, the project can be delayed beyond its deadline. You may have asked yourself:
Is there any way that I can limit this delay?
The answers to these questions come in the shape of Thresholds…
1/3/2013 ©2007 Micro Planning International Ltd 73
Resource thresholds in deadline critical
1/3/2013 ©2007 Micro Planning International Ltd 74
Time thresholds
1/3/2013 ©2007 Micro Planning International Ltd 75
Unavoidable split/overload
When you choose a Resource Critical Resource Analysis, you specify that the resources must not be overloaded and, under certain circumstances, the only way of achieving this may be the interruption of oneor more tasks...
... but what happens if these tasks are Non-Split or Consecutive?
1/3/2013 ©2012 Micro Planning International Ltd 76
1/3/2013 ©2012 Micro Planning International Ltd
The Solid Fixed Block:
Imagine that tasks A and B require the same resource and that task Bis forced to start on day 3 because of a Fixed Earliest date. A fixed
date takes priority over everything else
77
Resource Distribution
1/3/2013 ©2012 Micro Planning International Ltd 78
Micro Planner X-Pert
1/3/2013 ©2012 Micro Planning International Ltd
Deadline Resource Histogram
79 1/3/2013 ©2012 Micro Planning International Ltd
Resource Limited Resource Histogram
80
1/3/2013 ©2012 Micro Planning International Ltd
Cost forecasting
Cost Analysis in X-Pert
81 1/3/2013 ©2012 Micro Planning International Ltd
Costing Rates
82
1/3/2013 ©2012 Micro Planning International Ltd
The Cost of Each Task
83 1/3/2013 ©2012 Micro Planning International Ltd
Costing details
84
Micro Planner X-Pert
Daily Wastage Costs
1/3/2013 ©2012 Micro Planning International Ltd 85
Total Estimated Costs or Cash Flow Profile
1/3/2013 ©2007 Micro Planning International Ltd 86
1/3/2013 ©2012 Micro Planning International Ltd
Comparing schedule costs
87 1/3/2013 ©2012 Micro Planning International Ltd
Updating a Micro Planner X-Pert Project Plan
Reporting Progress on Tasks, Resources and Costs
88
1/3/2013 ©2012 Micro Planning International Ltd
Reporting Progress
• Opened the file, go to the Analysis menu and highlight Progress Details and click.
89 1/3/2013 ©2012 Micro Planning International Ltd
Reporting Progress
• Opened the file, go to the Analysis menu and highlight Progress Details and click.
90
Micro Planner X-Pert
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Enter the appropriate Time Now date,
• Eg 15-Sep-03
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Go to File on the Menu bar and select
• Save As ..
• Eg HOMUpdt1.xpj
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Go to the desktop and open the sub project to be progressed
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• X-Pert shows all the tasks and events which should have started and finished since the last Time Now, with a “cross” or diagonal line through the task box
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Double Click on the first event/task to be progressed
Micro Planner X-Pert
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• The progress cells now appear
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Enter the actual achieved date for the “Start” event; eg “18Aug03”
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
Progressing Tasks• Double Click the first task to be progressed
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Enter the Task’s “Actual Start and / or Actual Finish Dates”• Eg Actual Start was 18Aug03 and Actual Finish was 22Aug03
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Reporting “Actual Resources Used”
• Click on the Resource Usage button
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Click on Actual Usage
Micro Planner X-Pert
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Click on “Copy Planned to Actual”
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Note that cells are filled for you, with the data originally entered
• Click OK and the progress data is now entered
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
Continue to report progress
• For a Task which has started but not finished, you must report abalance to go or a % Done to date, as shown
Reporting Progress
• Note: A task should not have a balance duration reported if both the started and finished dates have been entered. Also % Done will not be used as reporting percentage work done is rather subjective and the more objective form of estimating time to complete a task is preferred.
• If a task is reported with an Actual Start Date and the rest of the fields are left blank, X-Pert will assume progress has occurred since the reported Actual Start Date and Time Now. Should there be insufficient balance left at Time Now, then the task will be assumed completed
1/3/2013 ©2012 Micro Planning International Ltd 106
Reporting Progress
1/3/2013 ©2012 Micro Planning International Ltd
• Run a Analysis to view the results of “Progress”
• EG Resource Analysis – Deadline Critical
1/3/2013 ©2012 Micro Planning International Ltd
Reporting Progress
108
Micro Planner X-Pert
1/3/2013 ©2012 Micro Planning International Ltd
Reporting Progress
109