TECHNOTE
Cost to Completion
2 | TECHNOTE – Cost to Completion
Copyright © 2020 by Construction Computer Software (RIB CCS)
This publication is protected by copyright, and permission must be
obtained from the publisher prior to any prohibited reproduction, storage
in a retrieval system, or transmission in any form or by any means,
electronic, mechanical, photocopying, recording, or likewise.
Technote Reference: CAN-TCH-NTE-0014
Technote Version: 00
Technote Date: May 2020
Information is correct as per the functionality present in
Candy V 2.01e09.6.
3 | TECHNOTE – Cost to Completion
TABLE OF CONTENTS
INTRODUCTION ..................................................................................................... 4
CANDY COST RATE ................................................................................................. 5
CANDY COST WORKSHEET ..................................................................................... 8
4 | TECHNOTE – Cost to Completion
INTRODUCTION
Candy cost rates or worksheets are used to make cost adjustments to the remaining cost during the
post tender stage. Changes can be to Resource cost rates, Production output, Wastage allowances
and Construction methods. The Cost rate however also integrates with BuildSmart procurement. In
BuildSmart it is used as a Buying rate. If the QS is aware of a mistake made at estimate, for example
the concrete price allowed is not adequate, the Cost rate can be updated to an adequate rate and
uploaded into BuildSmart. The Procurement manager can then import the new resources but using
the Cost/Buying rate. This will then allow a buyer to exceed the allowable, up to the new Buying rate.
This will allow users to lock rates and quantities and will give the QS full control.
5 | TECHNOTE – Cost to Completion
CANDY COST RATE
Before the use of the Cost rate can be viewed there is some pre-setup requirements that need to be
in place, these requirements are:
• First Principal estimating for all bill items.
• Accurate actual quantity measure is key in the true reflection of the project performance to date.
(Valuation needs to be in place).
• Accurate final quantity measure is key for an accurate reflection of the remaining; and at
completion Cost & Allowables.
• Imported Cost (Optional).
Looking at the current cost report we can see the following:
• Allowable to date – Actual quantity x Net rate. 37,037,426.
• Cost to date – Imported cost to date from the accounting system 37,037,716.
• Variance to date – Allowable to date less Cost to date -290.
• Allowable remaining – Remaining quantity x Net rate 274,472,951.
• Cost remaining – Remaining quantity x Cost rate in Candy 274,472,951.
• Variance remaining – Remaining allowable less Remaining cost 0.
• Allowable at completion – Final quantity x Net rate 311,510,377.
• Cost at completion – Cost to date + Remaining cost 311,510,667.
• Variance at completion – Allowable at completion less Cost at completion -290.
To change Cost Rates, take the following steps:
• Step 1: Under the Cost & Allowables tab > Documents > Cost & Allowables documents.
Alternatively, you may select the icon to open the Document Manager.
6 | TECHNOTE – Cost to Completion
• Step 2: Select document 7.1 Resource Cost Rate to completion.
• Step 3: Change the details given below under the Cost Rate column.
o LABOUR ARTISAN 125/hr
o GANG BOSS 70/hr
o CEMENT OPC 115/bag
o BEDDING SAND COMMERCIAL 210/m3
o REINFORCING MESH REF.100 12.60/m2
7 | TECHNOTE – Cost to Completion
View the effects on the 1.1 Cost & Allowable by period document / report.
Changing 5 cost rates, increased 3 costs and decreased 2 and the following effects can be viewed.
Remaining
Description Remaining Allowable Remaining Cost Remaining Variance
Before 274,472,951 274,472,951 0
After 274,472,951 274,377,013 95,938
At Completion
Description At completion Allowable At completion Cost At completion Variance
Before 311,510,377 311,510,667 -290
After 311,510,377 311,414,729 95,648
Notice the Allowable remains the same. But the Remaining Cost and at completion cost are affected.
These 5 changes made, caused an increase in the contracts cost of 95,648. The QS can now use this
information to try and minimalize the effects this has on the project. By changing productions,
wastages, suppliers and trying to get discount on other high value items or fixing cost for the remaining
duration of the project. Therefore, the Cost rate can be used to try and make accurate future
predictions for the project.
8 | TECHNOTE – Cost to Completion
CANDY COST WORKSHEET
Cost worksheets are used to change productions, wastage factors and construction methods on bill
items using actual site information to predict the effect it will have on the project. To do this, take
the following steps:
• Step 1: Under the Cost & Allowables tab > Documents > Cost & Allowables documents.
Alternatively, you may select the icon to open the Document Manager.
• Step 2: Select document 7.1 Resource Cost Rate to completion.
9 | TECHNOTE – Cost to Completion
• Step 3: Open the worksheet for the item you would like to change the Cost worksheet.
• Step 4: Click View > Flip to Cost worksheet.
A Worksheet currently identical to the Net worksheet will be displayed.
10 | TECHNOTE – Cost to Completion
Let’s say the site team informed you that they are only achieving 20m3/day. Make this change to
the Cost worksheet.
Let’s say the estimator forgot to apply wastage to an item. Make this change to the Cost worksheet.
View the effects on the cost report.
Remaining
Description Remaining Allowable Remaining Cost Remaining Variance
Valuation 1 274,472,951 274,472,951
Cost rate 274,472,951 274,377,013 95,938
Cost worksheet 274,472,951 281,252,417 -6,779,465
11 | TECHNOTE – Cost to Completion
At Completion
Description At completion Allowable At completion Cost At completion Variance
Valuation 1 311,510,377 311,510,667 -290
Cost rate 311,510,377 311,414,729 95,648
Cost worksheet 311,510,377 318,290,132 -6,779,755
These 2 changes made, caused an increase in the contracts cost of an additional 6,875,403 bringing
the total increase to 6,779,755. The QS can now use this information to try and minimalize the effects
this has on the project. By changing productions, wastages, suppliers and trying to get discount on
other high value items or fixing cost for the remaining duration of the project. Therefore, the Cost
Worksheet can be used to try and make accurate future predictions for the project.