Contents Basic information PPP projects in Poznan Western Gate Car Park projects Za Bramką Project...

Preview:

Citation preview

Contents

Basic information PPP projects in Poznan Western Gate Car Park projects Za Bramką Project Golf Course

Poznan is…

A Connection between East and West

Member of Eurocities

Domicile of global brands

Best managed city in Poland

Leader and pioneer among Polish cities

Poznan – basic information

Inhabitants:Agglomeration - 897 thousandradius 100 km – ca. 3 mln Poznan is a city of business and students

GDP in Poznan (2009) - EUR 9.7 billionForeign investments 1990-2009 – 4.9 billion EUR 27 higher education establishments, including 5

universities,140 thousand students

Investments in Poznan

FDI in Poznan - services

SSC (IT, F&A, other) R&D (IT, other) BPO

FDI in Poznan - production

Biggest production field investments

PPP Projects in Poznan

The City of Poznan plannes to execute investments with the participationof private partners in the following areas:

Construction of multi-level car parks, Environmental protection infrastructure – Waste Management System

for the City of Poznan, Construction of sports and recreation venues, Construction of communal flats, and service and multi-functional

buildings.

The Western Gate Project

The Western Gate Project

Type of project, type of activity: transport infrastructure, multi-level car park

Detailed description of the project:

a tram route and a loop a bus station with an underground car park – around 300 parking

spaces a multi-level car park – maximum 6 above-ground levels and

underground levels

Moreover, the plan allows for the construction of: trade and services facilities multi-family residential buildings

The Western Gate Project

Investment model (PPP, licence): PPP or licence

Estimated value of the investment (in million EUR): Tram route and loop ca. 26, 300 000 Bus station (and car park) ca. 8, 780 000 Multi-level car park ca. 17, 300 000

total ca. 52, 380 000

Project implementation plan: the commencement of the procedure of granting the licence on

construction work and services concluding the procedure, the choice of licence holder - The

construction of the structure

Car Park projects

Car Park under Bernardyński Square

Type of project, type of activity: multi-level car parkCar park description:

Underground car park Park&Go type of car park 3 levels Approx. 200 parking spaces Total area of approx. 6,000 m² Location in the Paid Parking Zone In the neighbourhood of 2 hospitals, a church and other public institutions The possibility of liquidating approx. 250 ground level parking spaces in the surroundings

Car Park under Bernardyński Square

Investment model (PPP, licence): PPP

Estimated value of the investment (in million EUR):

ca. 7 mln

Project implementation plan:

Launching the procedure for the selection of a private partner

and

concluding a public-private partnership agreement in the

competitive

dialogue mode – 2012/2013

Commencing the construction of the facility –2015

CAR PARK AT POZNAŃSKA STREET

Type of project, type of activity: transport infrastructure, multi-level car parkThe basic parameters of the car park:

A Park&Go type of car park, located on the periphery of the Paid Parking Zone

Underground/overground car park 3 levels 180-250 parking spaces Total area of approx. 1,200 m²

Location on the periphery of the Paid Parking Zone:within the borders of the functional City Centre in the neighbourhood of the existing tramway route

CAR PARK AT POZNAŃSKA STREET

Investment model (PPP, licence): PPP

Estimated value of the investment (in million EUR):

ca. 2.5-4 million

Project implementation plan (in months):

Launching the procedure for the selection of a private partner and

concluding a public-private partnership agreement in the

competitive

dialogue mode – 2012/2013

Commencing the construction of the facility –2015

SZYMANOWSKIEGO / STRÓŻYŃSKIEGO CAR PARK

Type of project, type of activity: transport infrastructure and multi-level car parkThe basic parameters of the car park:

A Park&Ride type car park Underground/overground car park 3 levels 450 parking spaces Total area of approx. 4,500 m² Location on the periphery of the city:

near the Poznań Fast Tram – Szymanowskiego Stop

SZYMANOWSKIEGO / STRÓŻYŃSKIEGO CAR PARK

Investment model (PPP, licence): PPP

Estimated value of the investment (in million EUR):

ca. 4,5 – 7,5 million

Project implementation plan:

Launching the procedure for the selection of a private partner and

concluding a public-private partnership agreement in the

competitive

dialogue mode – 2012/2013

Commencing the construction of the facility - 2015

”Za Bramką” project

Old Market Square

Town Hall

Poznan City Hall

Cathedral500 m

Project description:

Construction of a commercial or commercial and housing building together with a multi-storey car park for around 400 cars in Za Bramką Street (A) Renovation of a historic building of commercial function and construction of a commercial building in an annex on Garbary Street (B) Renovation of a commercial and housing tenement in Garbary Street (C) Construction of a commercial and housing building in Garbary Street (D)

”Za Bramką” project

Za Bramką Project

Investment scheme: PPP

Estimated value of the investment project (in mln EUR):

13,5 mln

Project's time line:

The investment process about 18 months, the operation about 40

years

Opening of the emerging private partner is expected

in the third quarter of 2012

Golf course

Golf course

Type of project: Leisure facilities, investment project in the field of design, construction and operation of the above-mentioned facilities

Detailed description of the project: In Poznań, along with the auxiliary infrastructure The project proposes the arrangement of an investment consisting of:

the construction of a full-length, 18 -hole golf course the construction of, depending on the selected variant, either a hotel and conference centre, or a club house, stables and a single-family housing development

Golf course

Model of investment (PPP, concession): PPP

The plan for the implementation of the project (in months): The investment process – around 38 months

Estimated value of the investment (in millions of EUR): Net value of 8 – 32 mln EUR

Thank you for your attention

Katja Lozina

Deputy Head of Investor Relations Department

Poznan City Hall

Recommended