Commercial Points for 86th OCC meeting
Requisition of MTOA before 10am
• Some of the MTOAs are not being scheduled • KSK Mahanadi-AP and CPL-AP are not
requisitioned.• Cl 17.a mandates release of such margin for
STOA • Request states to intimate such Under-
requisition well in advance so that Adv / FCFS STOA can be approved
• Atleast before 10am on Day Ahead basis so that it can be released to Px.
Letter
Treatment of Kudankulam infirm injection
• SRPC issued Allocation order dt 30-07-13 on unallocated quota of Kudankulam
• Order specified allocation ratios for 1)prior to CoD and 2) from CoD
• allocation ratios for prior to CoD for accounting purpose of infirm injection
• SRLDC will not Schedule the infirm injection
• Nor give any relief in Real Time O/D messages etc.
NO OF INSTANCES OF DELAY IN WEEKLY SEM DATA RECEIPT DURING July’ 2013
AP KARNATAKA POWERGRID
KTPS(kothagudam)KTPP
2 each Kodasally 2Udumalpet, Kalivanthapattu, Munirabad
1 each
Mamidipally 1 Kadra 1 Hyderabad 2
Yerandahally 1 Talcher Aux 1
GOA Kadakola 1 KSEB
ponda 1 Hoody 1 Edomon 2
Guttur 1
PONDY Sedam 2
vilianur 1 TN
Mettur 1 Others
Theni 1 SEPL 1
TIME DRIFT STATEMENT NOT RECEIVED in the month of July’13
ANDHRAPRADESH:Gajwel, Gooty RS, Kakinada, Kakatheeya, Kothagudom, Karnool & Mehboob nagarKARNATAKA:All stations except Nelamangala & RaichurTAMILNADU: Arni, SP Koil, & Thiruvelam Pondicherry: nil
ISGS STATIONS: nil
CTU STATIONS:Munirabad ,Vijayawada, Hyderabad, Nellore, Nellore PS, kadapa, Kalivanthapattu , Pondy & Udumalpet
•Tamilnadu Rs.2635 Lakhs (TN opened LC for Rs.8.49Cr only in lieu of Rs.32.84Cr)
•APTRANSCO Rs.247.50 Lakhs Due to delay of wk40(31.12.12-06.01.13) UI payment(APTRANSCO opened LC for Rs. 62 Lakhs only )
•LKPPL Rs.2.44 Lakhs Due to delay of wk40(31.12.12-06.01.13) UI payment
•MEPL to enhance LC to Rs. 17.23 Lakhs from Rs.7Lakhs Due to delay of wk41(07.01.13-13.01.13) UI payment
OPENING OF LC DUE TO DELAYED UI PAYMENT
PoC status for Q3 of 2013-14
Status of RRF Mock Exercise
• Implemented from 15-07-13• TNEB started furnishing data
– for 11 pooling stations in full shape. – For 3 stations Scheduling yet to start – For 2 stations Actual Energy to be recd
• AP not submitting data • Karnataka discontinued from week (220713-
280713) and (290713-040813)
Metering Scheme and Accounting methodology for new stations
• Henceforth SRLDC will not be advising the locations of SEMs for new projects or Connection points
• Installation of SEMs to be done by concerned agencies themselves as per CEA Metering regulations 2010
• Data format to be in line with existing SEMs• New stations to get the Metering Scheme and
Accounting methodology finalised in Commercial subcommittee of SRPC
Before amendment
After amendment
Recommended