City of Austin Water Treatment Plant No....

Preview:

Citation preview

City of AustinWater Treatment Plant No. 4

June 23, 2017

Raw Water Tunnels

John N. Buser, PE

AGENDAProject History and Overview

Raw Water System Design and Construction

Project Delivery

Key Tunneling Risks

Conclusions

Project History and Overview

Project History and Overview

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 4

Project History and Overview

WTP4 History• 1980 - 2000• 2000 – 2010• 2010 - 2014

Project Location• RM620 and Bullick Hollow Road

o Off-site Pump Station

Project Construction• Alternative Delivery

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 5

Project History and Overview

Project Components• Raw Water Intake (300MGD)• Raw Water Tunnel (300MGD)• Raw Water Pump Station

(50MGD)• Raw Water Transmission Main

(150MGD)• Water Treatment Plant

(50MGD)• Jollyville Transmission Main

(150MGD)

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 6

Project History and Overview

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 7

Project History and Overview

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 8

Raw Water Intake

Raw Water Tunnel

Raw Water Pump Station

Raw Water Trans. Main

Water Treatment Plant

Project History and Overview

Team Qualifications• Knowledge of local geologic

conditions• Specialty Tunnel Expertise• Specialty Structural Expertise

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 9

Project History and Overview

Raw Water Intake• 300 MGD capacity• Sloping Intake on Bottom of Lake

Travis• Three Intake Elevations

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 10

Project History and OverviewRaw Water Intake

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 11

Project History and Overview

Raw Water Tunnel• 300 MGD capacity• 75 ft below Lake Travis• 450 ft below the Surface

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 12

Project History and Overview

Raw Water Pump Station• 50 MGD capacity• Vertical Turbine Pumps• Expandable to 150MGD• 2nd Station for 300MGD

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 13

Project History and Overview

Raw Water Transmission Main• 150 MGD capacity• Portal Entry, Steel Liner• Two 150MGD Tunnels

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 14

Raw Water System Design and Construction

Raw Water System Design and Construction

The Raw Water system has to accommodate fluctuating lake level

• 614ft-msl to 711ft-msl

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 16

And then there was a drought

Raw Water System Design and Construction

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 17

Raw Water Tunnel

Raw Water Trans. Main

Raw Water System Design and Construction

Intake Removes Water From Three Different Lake Levels• 568 Ft-MSL• 607 Ft-MSL• 652 Ft-MSL

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 18

Raw Water System Design and Construction

Large % of tunnel & underground project cost in the excavation

Underground construction subject to unknowns

Materials for Excavation • the (Soil, Rock) properties

can vary considerably

Means and Methods• Tunnel Boring Machine (TBM)• Roadheader• Support

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 19

Raw Water System Design and ConstructionTunnel Easements and Alignment

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 20

Raw Water System Design and ConstructionGeotechnical Investigation

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 21

Raw Water System Design and Construction

Geotechnical Investigation• Number Of Borings

o Supplemental Data

• Geotechnical Data Reporto Used by designers to locate tunnel elevation

• Three Main Geologic Stratao Edwards Limestoneo Walnut Limestoneo Glen Rose Limestone

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 22

Raw Water System Design and Construction

Geotechnical Baseline Report• Contract document that provides interpretations and baseline statements

(means of apportioning risk sharing)• Translates data into conditions for bidding• Not a warranty that conditions will be encountered• Baseline will be used when interpreting the Differing Site Conditions Clause• Example: For baseline purposes, the Contractor shall assume that 15% to

20% of the tunnel alignment will encounter mixed face (rock & soil) conditions.

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 23

Raw Water System Design and Construction

Raw Water Tunnel Challenges• Temporary Support• Permanent Lining• Access Shaft• Connection to Intake• Material Transport• Muck Hauling

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 24

Raw Water System Design and Construction

Raw Water Tunnel Temporary and Permanent Support

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 25

Raw Water System Design and Construction

Raw Water Tunnel Access Shaft

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 26

Raw Water System Design and Construction

Raw Water Tunnel Intake Connection

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 27

Raw Water System Design and Construction

Raw Water Tunnel Intake Connection

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 28

Raw Water System Design and Construction

Raw Water Tunnel Material Transport

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 29

Raw Water System Design and Construction

Raw Water Tunnel Muck Hauling

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 30

Raw Water Access Shaft

Trans. Main Portal

Raw Water System Design and Construction

Raw Water Transmission Main Challenges• ROW• Temporary Support• Permanent Lining• Access• Connection to WTP• Material Transport• Muck Hauling

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 31

Raw Water System Design and Construction

Raw Water Transmission Main ROW

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 32

Raw Water System Design and Construction

Raw Water Transmission Main Support and Lining

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 33

Raw Water System Design and Construction

Raw Water Transmission Main Access

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 34

Raw Water System Design and Construction

Raw Water Transmission Main Connection at WTP• Passed through Multiple

Formations• Thrust Restraint

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 35

Gravel Collar in Edwards

Project Delivery

Nature of tunneling contractors• Generally small, close-knit community• Good understanding of project risks & contract savvy • Frequently team on large projects

Contractor’s expectations• Contract documents tailored to industry standards

o Differing Site Conditions (DSC), Geotechnical Baseline Reports (GBR), Dispute Review Boards (DRB)

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 36

Project Delivery

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels

Construction Manager at Risk• COA selected CMAR delivery method• Obayashi Construction for the Tunnels • Joint Venture – Hill Country Contractors (Manson and Obayashi)

Engineer’s Role During Construction• Daily Inspection / Logs / Photos• Monitor Alignment of Access Shaft / Tunnel• Monitor Vibration

Page 37

Key Tunneling Risks

Insufficient geological informationUnstable face during tunneling Settlement and damage to structuresGassy tunneling conditionsGroundwater InflowsMixed-face tunneling conditionsChoice of primary liningInexperienced personnel

Disruption to residents and loss of public amenity

Disruption to business commerce

Disruption to traffic increased accidents

Disruption to adjacent utilities

Environmental impacts

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 38

Conclusions

Understand the Geology• Mapping, Borings, Geophysics• Analysis using experienced

tunnel personnelProvide accommodations in design for variable tunneling methodsIndependent Peer ReviewAllow adequate Bid TimeDisclose all Subsurface information to biddersEstablish a Dispute Resolution Board

Anticipate access, hauling, and materials delivery challenges

Contractor is responsible for selection of Means of Construction, Equipment, and Methods for execution of work

Contractor retains responsibility for Safety & Excavation

Conduct pre-construction condition surveys

Establish Construction Monitoring Program

Be Flexible

June 23, 2017Water Treatment Plant No. 4 –Raw Water Tunnels Page 39

Thank You

June 23, 2017

Recommended