CIPREL III
Vridi - Thermal Power Plant Extension of the existing CIPREL power plant as EPC contractor of the CIPREL III (115 MW at site ambient conditions). The scope of work included : . the complete civil works, . the GE “9E” gas turbine and its auxiliaries, . the electrical and mechanical balance of plant, and its integration within the existing one, . the automation & monitoring and control, . the connection to the 90 kV grid through a new switchyard bay, . the transportation, customs clearance, erection and commissioning.
SOLUTION IMPLEMENTED
TURNKEY PROJECT Activity
Civil Works, Structures, Mechanics, Automation & monitoring and control
Technologies Used GE 9 FA Gas turbine, Dual Fuel
Customer Benefits . Ability to deliver a turnkey solution, customized to CIPREL’s requirements . Addition 50% capacity to its existing plant without disturbing its operation
Business Units Involved Omexom Power Plants - Thermal
Philippe LENTZ - philippe.lentz@cegelec.comXavier DUCLOS - xavier.duclos@omexom.com
Country: Ivory Coast Site: Vridi, suburbs of Abidjan Budget (k€): 54,000 Start Date: 05/2008 End Date: 03/2010
Contacts
SCAN WITH UBLEAM APPLICATION