About UsBy virtue of Department Order Number 110, Series of 1993 (DO 110, S.1993) of the Department of Public Works and Highways (DPWH), the function for the administration and enforcement of PD 1096, otherwise known as National Building Code (NBC) of the Philippines, was devolved to Local Government Units (LGUs). With this devolved function, the Office of the City Building Official (OCBO) implements regulations and requirements for the construction, alteration, repair, conversion, use, occupancy and demolition of buildings pursuant to Section 301 of PD 1906, as well as enforcement of related orders and decisions.
SECURING A BUILDING PERMITABOUT THE SERVICE
A BUILDING PERMIT is required prior to the construction, erection, alteration, major repair, or renovation or conversion of any building/structure owned by government of private entities.
The permit becomes null and void if work does not commence within one year from the date of such permit, or if the building or work is suspended or abandoned at any time after it has been commenced for a period of 120 days.
The Office of the City Building Official regulates and/or issues the following:
Building Permit Occupancy Permit Electrical Permit Certificate of Final Electrical Inspection (CFEI) Mechanical Permit Sanitary / Plumbing Permit Miscellaneous/ Ancillary Permits (Fence, Demolition, Temporay
Service Connection, Excavation, & Ground Preparation, Sidewalk Construction , Scaffolding,)
Sign Permit (Billboard, Signboard, Temporary Business Signs) Cerificate of Annual Inspection Certificate of Exemption
1
OFFICE OF THE CITY BUILDING OFFICIALENGINEERING ENGINEERING DEPARTMENTG/F Lucena City Hall bldg.Brgy. Kanlurang Mayao, Lucena City(042) 710-5866 / (042) 373-5947Department Head/OIC – Engr. Rhodencio L. Tolentino
WHO MAY AVAIL OF THE SERVICE
General public, firm or corporations, agencies or instrumentalities of the government.
WHAT ARE THE REQUIREMENTS
See BUILDING PERMIT checklist of requirements
FEES
Please refer to the revised National Building Code.
SCHEDULE OF AVAILABILITY OF SERVICE
Monday to Friday - 8:00 am to 5:00 pm - NO NOON BREAK
PROCESSING TIME
2 To 3 days
BUILDING PERMITChecklist of Requirements
Five (5) Sets of Building plans - prepared, signed and sealeda. By a duly licensed Architect or Civil Engineer, in case of
Architectural and Structural plans;b. By a duly licensed Sanitary Engineer or Master Plumber, in case
of plumbing, sanitary installation plans;c. By a duly licensed Professional Electrical Engineer, in case of
Electrical plans;d. By a duly licensed Professional Mechanical Engineer, in case of
Mechanical plans;e. Duly accomplished Building permit application form signed &
sealed by Architect / Civil Engineer, in case of full time inspector & supervisor of construction works (Box 2 & Box 5) & Box 3 applicant and or authorize representative;
f. Duly accomplished Electrical permit application form signed and sealed by a Professional Electrical Engineer who designed electrical plan and a registered electrical practitioner for person-in-charge in case of Electrical permit;
g. Duly accomplished Sanitary permit application form signed and sealed by a Sanitary Engineer in case of Sanitary permit;
2
h. Duly accomplished Mechanical permit application form signed and sealed by a Professional Mechanical Engineer in case of Mechanical permit;
i. Photocopy of PRC ID and PTR of the Architect / Engineers who signed & sealed the plans.
Three (3) sets Sketch/Lot Plan with Vicinity Map (signed & sealed by a licensed Geodetic Engineer)
Three (3) copies of Certified True Copy of Land Title(TCT), Three (3) copies of Tax Declaration Three (3) copies of Tax Receipt for the current year If property is not registered under the name of the applicant:
Submit Three (3) copies of the following:a. Duly Notarized Copy of Deed of Absolute Sale, or Lease Contract
or Contract to Sell orb. Association’s Board Resolutionc. Applicant’s Certificate of Membershipd. Authorization Lettere. Duly notarized copy of Special Power of Attorney (SPA)f. Secretary’s Certificateg. Duly notarized copy of Affidavit of Consent of the Lot Owner for
the construction of building/house or Authority to Construct (whichever is applicable)
Certificate of Zoning Compliance Barangay Clearance Fire Code Clearance DOLE Clearance (Construction Safety and Health Program) DPWH Clearance (if Project is along National Road) Five (5) copies of Bill of Materials & Cost Estimates (signed & sealed
by Architect/Civil Engineer) Five (5) copies of Technical Specifications (signed & sealed by
Architect/Civil Engineer) Five (5) copies of Structural Design Analysis /Structural Computation
(signed & sealed by Civil / Structural Engineers) Five (5) copies of Seismic Analysis (except for Residential Buildings
with Height less than 7.5 meters) (signed & sealed by Civil / Structural Engineers)
Boring and Plate Load Tests (for Structures THREE (3) Stories and above)
Two (2) copies of Certification regarding structural stability of existing foundation in case of addition
Previous approved plan or permit in case of addition, alteration, and renovation
Environmental Compliance Certificate (ECC) Clearance Department Of Health (DOH) Clearance Air Traffic Clearance (ATO) National Telecommunication Company Clearance (NTC) Sanitary Treatment Plant (STP) w/ DOLE Clearance Standard Construction Signboard Construction Logbook
HOW TO AVAIL OF THE SERVICE3
FOLLOW THESE STEPS IT WILL TAKE YOU
PLEASE APPROACH
1. Secure and accomplish Building Permit Application Forms
Secure and accomplish building permit application. Submit forms with the list of
requirements
5 minutes
Receiving Staff
Petula Buno
Engr. Leticia Emradora
2. Initial review of requirements
Present the plans and the required supporting documents to any member of
the Building Official Staff for initial verification of the requirements.
10 minutesReceiving Staff
Petula Buno
Engr. Leticia Emradora
3. Line and Grade Verification
Technical staff in-charge conducts site inspection to establish and determine
setbacks and grades in relation to road lots, property lines, streets or highways whether
existing or proposed, including road widening and construction of various public utilities and other infrastructure projects.
30 minutes
Geodetic Engineer /
Building Site Inspectors
Engr. Cesar Gaela
William SangcapJewel Nivadura
Luigi LibiranMedardo
Letargo, Jr.Roderick Sares
Rex Suarez
4. Evaluation and Assessment
Evaluation and assessment done by:
Civil Engineer – Line and Grade, Structural Plans and related documents
Architect – architectural plans and related documents
Sanitary Engineer/Master Plumber – plumbing/sanitary plans and related
documents Professional Mechanical Engineer –
mechanical plans and related documents Professional Electrical Engineer –
electrical plans and related documents.
1 hr
Building Official Technical Staff
Engr. Cesar Gaela
Engr. Lydia Faller
Ar. Warren Quiambao
Engr. Leticia Emradora
Engr. Estelito Ebreo
Engr. Romeo Maano,Jr.
2 days from receipt of
Building Official
4
5. Inquiry on the Status of Application
Inquire about the results of evaluation and assessment after 2 days from submission of
requirements.
If there are no deficiencies, proceed to
step 9.
documents
Staff
Petula Buno
Engr. Leticia Emradora
6. Returned Plans and Documents
Get the plans and documents that need correction. You will also be informed about
lacking documents, if any.30 minutes
Building Official Staff
Petula Buno
Engr. Leticia Emradora
7. Submit Lacking Documents/Corrected Plans
Submit the lacking documents/corrected plans to any member of the Building Staff
for review.
Based on applicant’s
actions
Building Official Staff
Petula Buno
Engr. Leticia Emradora
8. Review of Corrected Plans/Documents
The technical staff reviews the corrected plans and checks completeness of
documents.
30 minutes
Building Official Technical Staff
Engr. Cesar Gaela
Engr. Lydia Faller
Ar. Warren Quiambao
Engr. Leticia Emradora
Engr. Estelito Ebreo
Engr. Romeo Maano,Jr.
9. Processing of Permits
Building Staff processes the plans and
2 days Building Official Staff
5
pertinent documents and prepares the Order of Payment for final approval of the
Building Official.
Petula Buno
Engr. Leticia Emradora
10. Endorsement to Building Official for Final Evaluation Issuance of Order
of Payment
If the documents are in order, the applicant receives an Order of Payment stating the
fees to be paid.
10 minutes
Building Official
Ar. Warren Quiambao,
Chief Processing & Evaluation
Division
Engr. Leonardo Salonga,
Assistant City Engineer
11. Payment of Fees
Proceed to the City Treasurer’s Office and pay the requisite fees.
You will be issued an Official Receipt
10 minutesCashier, City Treasurer’s
Office
12. Submit Official Receipt
Go back to the Office of the City Building Official and submit your Official Receipt.
10 minutes
Building Official Staff
William Cusi
13. Approval of Permit
City Building Official approves the permit.10 minutes
Building Official
Engr. Rhodencio Tolentino,OIC-City Engineer
14. Endorsement to Mayor’s Office for Final Release of Building Permit
Proceed to Mayor’s Office15 minutes
Building Official Staff
William Cusi
Luigi Libiran
15. Release of Building Permit
The Building Permit is issued after endorsement from the Office of the
15 minutes Releasing Staff
Mayor’s Office Staff
6
Building Official.
APPLYING FOR AN OCCUPANCY PERMITABOUT THE SERVICE
An Occupancy Permit is required before any building/structure is used or occupied. It is usually secured after the completion of a structure. It is also required if there is any change in the existing use or occupancy classification of a building, structure or any portion thereof.
GENERAL REQUIREMENTS:
Certificate of Completion from the Building Official Certificate of Completion-Mechanical, Electrical and Sanitary/Plumbing Logbook of building construction and Building Inspection Sheet duly
accomplished by the contractor (if undertaken by contract) and signed and sealed by the Architect or Civil Engineer in charge of construction
Certificate of Final Electrical Inspection Final Fire Safety Inspection Report by the Bureau of Fire Protection
(BFP) Zoning Conformance issued by the Zoning Administrator As built plans (for any deviations from the approved plans)
WHO MAY AVAIL OF THE SERVICE
General public, firm or corporations, agencies or instrumentalities of the government.
FEE(S)
Please refer to the revised National Building Code.
SCHEDULE OF AVAILABILITY OF SERVICE
Monday to Friday - 8:00 am to 5:00 pm - NO NOON BREAK
PROCESSING TIME
3 to 5 days
HOW TO AVAIL OF THE SERVICE
7
FOLLOW THESE STEPS IT WILL TAKE YOU
PLEASE APPROACH
1. Secure and accomplish Certificate of Completion
Forms
Ask for completion forms from any member of the Building
Staff.
5 minutes
Receiving staff
Petula Buno
Engr. Leticia Emradora
2. Submit accomplished forms together with the
requirements to the Receiving Staff.
5 minutes
3. Review/Evaluation
Technical staff reviews the forms and the construction
activity entries in the construction logbook. Upon
review, if found to be completed, Technical Staff will
schedule the conduction of final inspection
30 minutes
Building Official Technical Staff
Engr. Ronan Muzares
Engr. Estelito Ebreo
4. Building Inspection
Building inspectors/members of technical staff conduct actual inspection of the completed
building/structure; and check if the same is in accordance with
the approved plans and specifications.
1 hour
Building Official Technical Staff
Engr. Norberto Querubin
Ar. Judy David-Verayin
Engr. Ronan Muzares
Engr. Estelito Ramos, Jr.
Engr. Estelito Ebreo
Engr. Isaias Villaruel, Jr.
Building Official Technical Staff
Engr. Norberto Querubin
Ar. Judy David-
8
5. Preparation of Inspection Report(
Building inspectors will give detailed inspection report
indicating lists of corrections & documents to be submitted
1-day
VerayinEngr. Ronan
MuzaresEngr. Estelito
Ramos, Jr.Engr. Estelito
EbreoEngr. Isaias Villaruel, Jr.
6. Perform Corrections/Submit
additional Documents
Make the necessary corrections/submit additional
documents listed in the inspection report.
Inform the building inspectors when these are completed.
Subject to client’s actions
Building Official Staff
Petula Buno
Engr. Leticia Emradora
7. Processing of Permits
Building Staff processes the plans and pertinent documents
and prepares the Order of Payment for final approval of
the Building Official.
20 minutes
Building Official Staff
Petula Buno
Engr. Leticia Emradora
8.Endorsement to Building Official for Final Evaluation
Issuance of Order of Payment
If the documents are in order, the applicant receives an Order of Payment stating the fees to
be paid.
1 hour
Building Official
Engr. Ronan Muzares,
Chief, Inspection & Enforcement
Engr. Leonardo Salonga
Asst. City Engineer
9.Payment of Fees
Proceed to the City Treasurer’s Office and pay the requisite
fees.
You will be issued an Official Receipt
10 minutes
(subject to client’s action)
Cashier,
City Treasurer’s
Office
9
10.Submit Official Receipt
Go back to the office of the Building Official and submit
your Official Receipt.
Submission of Certificate of Final Inspection from City
Zoning Office w/ Official Receipt
Submission of Fire Safety Inspection Certificate from
Bureau of Fire Protection (BFP) w/ Official Receipt
5 minutes
(subject to client’s action)
Building Official Staff
Petula Buno
Engr. Leticia Emradora
William Cusi
11. Signatories for Permit
Building Official Technical Staff signs Certificate of Occupancy
1 hour
Building Official Technical Staff
Engr. Norberto Querubin
Ar. Judy David-Verayin
Engr. Ronan Muzares
Engr. Estelito Ramos, Jr.
Engr. Estelito Ebreo
Engr. Isaias Villaruel, Jr.Ar. Warren Quiambao
12. Approval of Permit
Building Official approves the Certificate of Occupancy 15 minutes
Building Official
Engr. Rhodencio Tolentino, OIC, City Engineer
13. Release of Permit
The Certificate of Occupancy is issued after approval of the City
Building Official5 minutes
Releasing Staff
William Cusi
SECURING OTHER BUILDING-RELATED PERMITSABOUT THE SERVICE
10
Aside from a building permit, the Office of the City Building Official/City Engineer’s Office issues other permits that are required before the renovation, construction or demolition of any structure.
TYPES OF PERMITS AND REQUIREMENT(S)
APPLYING FOR ELECTRICAL PERMITElectrical Permit is a required document before putting up new or additional, or altering electrical installations involving at least 20 outlets or a capacity of 4 Kw.
REQUIREMENTS:
Electrical Permit Application Form signed & sealed by a Professional Electrical Engineer
Electrical Plans signed & sealed by a Professional Electrical Engineer Electrical Specifications signed & sealed by a Professional Electrical Engineer Bill of Materials and Cost Estimates.
FOR NEW CONNECTION OR SEPARATION OF KWHR METER:
REQUIREMENTS:
Notarized consent of lot owner ( if the applicant is not the owner) Certification from Urban Poor Association Office (if considered for
Depressed Area Electrification Program) Certification from the Office of the City Mayor (if lot is government
property) Photocopy of any valid I.D. of the applicant) Electrical Plan/Sketch (signed & sealed by a Professional Electrical
Engineer) Location/Sketch Notarized Authorization Letter for representative of the applicant
FOR RECONNECTION / REMODEL OF SERVICE FACILITIES:
REQUIREMENTS:
Monthly Bill of Utility Company (Meralco) Photocopy of any valid I.D. of the applicant Electrical Plan/Sketch (signed & sealed by a Professional Electrical
Engineer) Location/Sketch Notarized Authorization Letter for representative of the applicant
HOW TO AVAIL OF THE SERVICE
FOLLOW THESE STEPS IT WILL TAKE YOU
PLEASE APPROACH
11
1. Submit Electrical permit application and
required documents
Submit accomplished Electrical permit form and the required
documents for evaluation
5 minutes
Receiving Staff
Sherwin Digma
2. Inspection of the bldg. for feasibility of issuance of
Electrical permit
Building Inspector inspect the bldg. to assess if feasible for issuance of Electrical Permit
2 hoursBuilding
Inspectors
3. Assessment of Fees
Evaluator will assess the required payment for Electrical
Permit5 min.
Any of the Electrical Evaluator
(Dominic Ariles; Joselito Ginga;
Christian Lacerna)
4. Payment of Electrical Permit Fee
Proceed to City Treasurer’s Office for payment of Electrical
permit Fee
15 min.
Office of the City Treasurer
5. Claim approved Electrical Permit
Present the receipt to Electrical Division to claim approved
Electrical Permit5 min. Sherwin Digma
12
APPLYING FOR CERTIFICATE OF FINAL ELECTRICAL INSPECTION (CFEI)Certificate of Final Electrical Inspection or CFEI is required document for the operation of the electrical facilities of the building. It is also requirement to the power utility company (Meralco) for their energization.
REQUIREMENTS:
Approved Electrical Permit Duly accomplished CFEI form signed and sealed by a registered
electrical practitioner, person-in-charge of electrical works Notarized Authorization Letter for representative of the applicant
HOW TO AVAIL OF THE SERVICE
FOLLOW THESE STEPS IT WILL TAKE YOU
PLEASE APPROACH
1. Submit duly Certificate of Electrical Inspection form
Submit duly accomplished Certificate of Electrical
inspection form signed by the applicant & by registered
electrical practitioner, person-in-charge of electrical works
5 minutes
Receiving Staff
Sherwin Digma
2. Inspection
The Inspector inspect the applied building in scheduled date of the inspection (Comply all necessary corrections as per
advice of the inspector and proceed for another inspection
if corrections are made
2 hours
Any of the Electrical Evaluator
(Dominic Ariles; Joselito Ginga;
Christian Lacerna)
3. Claim approved Certificate of Final Electrical
Inspection Proceed to Electrical Division for claiming
5 min. Sherwin Digma
13
of approved Certificate of Final Electrical Inspection
APPLYING FOR MECHANICAL PERMITThis is required before the installation of new or additional, removal or alteration of equipment and machinery. For new buildings, this forms part of the requirements for a Building Permit application.
REQUIREMENTS:
Mechanical Permit Application Form (signed & sealed by a Professional Mechanical Engineer)
Mechanical Plans (signed & sealed by a Professional Mechanical Engineer)
Mechanical Specifications (signed & sealed by a Professional Mechanical Engineer)
Bill of Materials and Cost Estimates (signed & sealed by a Professional Mechanical Engineer)
APPLYING FOR SANITARY/PLUMBING PERMITThis document is required before the construction of new or additional, or altering existing plumbing installations, water supply, storm drainage, water purification and sewerage treatment plants. For new buildings, this forms part of the requirements for a Building Permit application.
REQUIREMENTS:
Sanitary/Plumbing Permit Application Form (signed & sealed by a Sanitary Engineer or Master Plumber)
Sanitary/Plumbing Plans ((signed & sealed by a Sanitary Engineer or Master Plumber)
Sanitary/Plumbing Specifications (signed & sealed by a Sanitary Engineer or Master Plumber)
Bill of Materials and Cost Estimates (signed & sealed by a Sanitary Engineer or Master Plumber)
APPLYING FOR MISCELLANEOUS/ANCILLARY PERMITS
FENCING PERMIT14
This is permit secured prior to actual construction of a fence.
REQUIREMENTS:
Fencing Permit Application Form ((signed & sealed by an Architect or Civil Engineer)
Fencing Plan (signed & sealed by an Architect or Civil Engineer) Bill of Materials and Cost Estimates (signed & sealed by an Architect or
Civil Engineer) Lot Plan with certification of a Geodetic Engineer that the proposed
fence will not encroach on adjoining properties DPWH Clearance (if Project is along National Road) Transfer Certificate of Title (TCT) Deed of Sale/Lease Contract/Contract to Sell (if the TCT is not in the
name of the owner/applicant) Updated Real Property Tax Declaration Certificate of Real Property Tax Payment
DEMOLITION PERMITThis permit is secured prior to the systematic dismantling or destruction of a building or structure in whole or in part.
REQUIREMENTS:
Demolition Permit Application Form (signed & sealed by an Architect or Civil Engineer)
Sketch Plan of area to be demolished (signed & sealed by an Architect or Civil Engineer)
Certified True Copy of Land Title(TCT), Copy of Tax Declaration Copy of Tax Receipt for the current Certificate of Real Property Tax Payment
TEMPORARY SERVICE CONNECTION PERMITThis permit is secured for temporary service connection to a power utility for lighting and power for construction, Christmas decorative lighting, lighting of cemeteries, temporary lighting for carnivals/fiestas, testing, etc.
REQUIREMENTS:
Permit Form (DPWH Form NO. 96-005-E) Building Permit (for new construction) Electrical Plan/Layout Fire Safety Inspection Certificate (FSIC)
15
EXCAVATION AND GROUND PREPARATION PERMITThis permit is secured prior to actual ground preparation and excavation after the building line is established. It is also a requirement for a water connection request to Quezon Metro Water District (QMWD)
REQUIREMENTS:
Accomplished Permit Form (MPW Form No. 77-014-B) For MWSI connection purposes, present accomplished MWSI
Application Form
SIDEWALK CONSTRUCTION PERMITThis permit is secured prior to the construction and repair of sidewalks
REQUIREMENTS:
Accomplished Permit Form (MPW Form No. 77-015-B) Sketch plan of sidewalk to be constructed/repaired
SCAFFOLDING PERMITThis permit is secured whenever the erection of scaffolding occupies street lines
REQUIREMENTS:
Accomplished Permit Form (MPW Form No. 77-017-B) Sketch plan of street line to be occupied
SIGN PERMITThis permit is secured prior to the installation, erection, attachment painting of any form of signage.
REQUIREMENTS:
Sign Permit Form Building Permit Form whenever there is a concrete structure. Structural Analysis Zoning Clearance Electrical Permit Form, whenever there is an electrical connection Fire Clearance whenever there is an electrical connection Sketch plan of signage to be installed/erected Location/vicinity plan Lot documents whenever it occupies a private lot DPWH clearance (for national roads/highways)
16
WHO MAY AVAIL OF THE SERVICE
General public, firm or corporations, agencies or instrumentalities of the government.
FEE(S)
Please refer to the revised National Building Code.
SCHEDULE OF AVAILABILITY OF SERVICE
Monday to Friday - 8:00 am to 5:00 pm - NO NOON BREAK
PROCESSING TIME
1 to 2 days
HOW TO AVAIL OF THE SERVICE
FOLLOW THESE STEPS IT WILL TAKE YOU PLEASE APPROACH
1. Secure Application FormsSecure the relevant permit
forms from the Building Official Staff. 5 minutes
Building Official Staff
Petula Buno
Engr. Leticia Emradora
2. Line and Grade Verification
Technical staff in-charge conducts site inspection to
establish and determine setbacks and grades in relation
to road lots, property lines, streets or highways whether
existing or proposed, including road widening and construction
of various public utilities and other infrastructure projects.
30 minutes
Geodetic Engineer / Building Site Inspectors
Engr. Cesar Gaela
William SangcapJewel Nivadura
Luigi LibiranMedardo Letargo, Jr.
Roderick SaresRex Suarez
17
3. Evaluation and Assessment
The technical staff evaluates and assesses the submitted
plans and pertinent documents for compliance with the
requirements of the building code, referral codes, laws and
ordinances.
1 hour
Building OfficialTechnical Staff
Engr. Cesar GaelaEngr. Lydia Faller
Ar. Warren QuiambaoEngr. Leticia
EmradoraEngr. Estelito Ebreo
Engr. Romeo Maano,Jr.
4. Processing of PermitsBuilding Staff processes the
plans and pertinent documents and prepares the Order of
Payment for final approval of the Building Official.
2 days
Building Official Staff
Petula Buno
Engr. Leticia Emradora
5. Endorsement to Building Official for Final Evaluation
Issuance of Order of Payment
If the documents are in order, the applicant receives an Order of Payment stating the fees to
be paid.
10 minutes
Building Official
Ar. Warren Quiambao, Chief Processing & Evaluation Division
Engr. Leonardo Salonga,
Assistant City Engineer
6. Payment of FeesProceed to the City Treasurers
Office and pay the requisite fees.
You will be issued an Official Receipt
10 minutesCashier,
City Treasurers Office
7. Submit Official ReceiptGo back to the Office of the Building Official and submit
your Official Receipt.
10 minutesBuilding Official Staff
William Cusi
8. Approval of PermitBuilding Official approves the
15 minutes
Building Official
18
permit. Engr. Rhodencio Tolentino,OIC-City
Engineer9. Release of Permit
The Building Permit is issued after submission of the Official
Receipt.15 minutes
Releasing Staff
William Cusi
CERTIFICATE OF ANNUAL INSPECTIONREQUIREMENTS:
Compliance of Indorsement (PWD compliance, structural stability certificate, electrical certificate, mechanical certificate etc.)
Copy of Official Receipt of Annual inspection fee.
CERTIFICATE OF EXEMPTIONREQUIREMENTS:
Duly accomplished business permit application form Location / sketch Copy of Official Receipt of Certification
For recommendations, suggestions, and complaints, contact the Department Head concerned or the City Personnel Office.
ISSUANCE OF EXCAVATION PERMITABOUT THE SERVICE
This permit is secured prior to actual ground preparation and excavation after the building line is established. It is also a requirement for a water connection request to Quezon Metro Water District (QMWD)
GENERAL REQUIREMENTS:
19
Letter of Request Location / Sketch Barangay Clearance
WHO MAY AVAIL OF THE SERVICE
General public, firm or corporations, agencies or instrumentalities of the government.
FEE(S)
Php 400.00 / sq.m.
SCHEDULE OF AVAILABILITY OF SERVICE
Monday to Friday - 8:00 am to 5:00 pm - NO NOON BREAK
PROCESSING TIME
1 to 2 days
HOW TO AVAIL OF THE SERVICE
FOLLOW THESE STEPS IT WILL TAKE YOU
PLEASE APPROACH
1. Submit the documents for Initial review of requirements 10 minutes
Receiving staff
Ricardo Par
2. Review/Evaluation
Upon review, if found to be completed, Field Inspector will schedule the site inspection
20 minutes
Field Inspector
Elpidio Garcia,Jr
3. Inspection
25 min. Field Inspector
Elpidio Garcia,Jr
20
Field Inspector will conduct actual inspection and after the inspection, he will assess the
required payment for the excavation permit
4. Payment of Excavation Permit Fee
Proceed to Office of the City Treasurer for payment of
excavation permit fee
25 min. Office of the City Treasurer
5. Claim approved Excavation Permit
Present the receipt to Office of the Bldg. Official to claim
approved Excavation Permit
2 min.
Engr. Isaias Villaruel
Engr. Rhodencio Tolentino
Jocelyn Herbulinggo