CEP-SwitchgearRetrofill Upgrade SellSheet

Preview:

Citation preview

Client Type: Electric Utility

Challenge/Issue: Design and install (37) retrofill applications in a (4) week outage

Equipment Involved: Vertical lift air magnetic circuit breakers replaced with draw-out vacuum circuit breakers, 4160V switchgear

Solutions: Design, build and install a retrofill application to replace existing switchgear with draw-out vacuum circuit breakers

Scope/Deliverables: Design and install (34) switchgear cells including new doors, relays, switches and indicating lights. Custom bus connection interfacing with existing horizontal bus and cable terminations

Timeframe: 4 weeks for Engineering and 4 weeks for install

CE POWER SOLUTIONS FAMILY OF COMPANIES

CE Power - Kentucky

CE Power - Florida

CE Power - Tennessee

Hope Engineering - Michigan

3rd Party NETA Independent Testing Companies

CE Power - Ohio

CE Power - Minnesota

Switchgear Retrofill Upgrade

SOLUTION PROFILE