California Water CommissionDecember 13, 2017 1

CWC Meeting December 13, 2017

2

Existing Los Vaqueros Reservoir

• Los Vaqueros Reservoir is an off-stream reservoir in Contra Costa County with a capacity of 160 TAF

• Contra Costa Water District (CCWD) operates Los Vaqueros Reservoir in conjunction with four Delta intakes

• Benefits:– Water quality improvements – Drought supply reliability– Emergency supply

CWC Meeting December 13, 2017

3

Proposed Los Vaqueros Reservoir Expansion Project

What are the objectives?• Environmental Water• Water Supply Reliability• Improved Water Quality• Enhanced Recreation

Who will benefit?• San Joaquin Wildlife Refuges • Bay Area Water Agencies• South-of-Delta CVP Contractors• Statewide Water System

How will benefits be achieved?• Construct new pipelines, new pump stations, raise the dam• Operate project using existing intakes • Integrate regional systems• Coordinate with other state-wide water operations

CWC Meeting December 13, 2017

4

Public Benefits

• Ecosystem– Increased water supply for San Joaquin

Valley wildlife refuges– Improved survival of salmonids migrating

through Delta

• Emergency Response– Catastrophic emergency– Drought emergency

• Recreation– Enhance recreation at Los Vaqueros

Reservoir & Watershed

CWC Meeting December 13, 2017

5

Non-Public Benefits

• Increased Municipal & Industrial Supply

• Drinking Water Quality Improvements

• Agricultural Supply

Potential Partners• Alameda County Water District• Bay Area Water Supply and

Conservation Agency• Byron-Bethany Irrigation District• City of Brentwood• Grassland Water District• East Bay Municipal Utility District• East Contra Costa Irrigation District• San Francisco Public Utilities

Commission• San Luis & Delta-Mendota Water

Authority• Santa Clara Valley Water District• Zone 7 Water Agency

CCWD

EBMUD

SFPUC

BAWSCA ACWD

SCVWD

Zone 7

ECCIDBrentwood

BBID

SLDMWA

Los Vaqueros Reservoir

CWC Meeting December 13, 2017

7

CVPIA South-of-Delta Wildlife Refuges

Habitat managed by• California Department of Fish and

Wildlife (state)• Grassland Water District (local)• U.S. Fish and Wildlife Service

(federal)South-of-Delta Refuge Demands

Level 2 271,000Incremental Level 4 105,500*Total 376,500 acre-feet*not including conveyance losses

Priority placed on meeting Incremental Level 4

CWC Meeting December 13, 2017

8

Proposed Facilities

• New Neroly High-Lift Pump Station

• EBMUD system improvements for increased use of EBMUD-CCWD Intertie

• New Delta-Transfer Pipeline• Expanded Transfer Facility• New Transfer-Bethany pipeline • Expanded reservoir capacity of

275 TAF• New local interties to serve

Brentwood & ECCIDContra Costa Water District 5/30/17

Contra Costa Canal

Expanded Los Vaqueros

Reservoir

Mokelumne Aqueduct

Possible New Facilities

Existing Facilities

Clifton Court Forebay

Delta-Transfer Pipeline

Old River Pipeline Expanded Transfer Facility

EBMUD Intertie Pump Station

EBMUD Walnut Creek Pump Plant VFDs

CWC Meeting December 13, 2017

9

Sources of Water

• Existing water rights of potential partners

– CCWD, Los Vaqueros Water Right– DWR, State Water Project– EBMUD– ECCID– Reclamation, Central Valley Project

• Modification to rights, contracts and agreements may be required

CWC Meeting December 13, 2017

10

Proposed Operations

CWC Meeting December 13, 2017

11

Deliveries to Local Agencies and Wildlife Refuges

CWC Meeting December 13, 2017

12

Recreation Benefits

• 20,000 acres managed in watershed

• 50+ miles of trails• Upgraded Marina

– 2 Fishing piers– 50 Rental boats– Fish stocking

• Upgraded Interpretive Center– Educational programs

CWC Meeting December 13, 2017

13

Potential Integration with Other Projects

• Evaluated with other projects seeking WSIP funding

– Increase in carryover storage in existing upstream reservoirs by 250 TAF

– Increase in annual water deliveries up to 400 TAF/yr

– Increase in groundwater storage of 250 TAF

• Potential for future improvement and integration

CWC Meeting December 13, 2017

14

Valuation of Benefits

Ecosystem, $1,033 38%

Recreation, $34 1%

Emergency Response, $487 18%

M&I Water Supply,

$875 32%

Agricultural Water

Supply, $255 10%

Water Quality, $34 1%

Project Cost & Public Benefit Ratio

Present Value of Total Project Costs $1,327 M

Present Value of Total Project Benefits $2,709 M

Total Benefits : Total Project Costs 2.05

Total Capital Costs $795 MPresent Value of Public Benefits $1,544 M

Total Requested Program Cost Share $434 M

Public Benefit Ratio 3.58

CWC Meeting December 13, 2017

CWC Meeting December 13, 2017

16

Schedule

January 2018 Public Draft Federal Feasibility ReportJune 2018 Preliminary CWC eligibility and funding

decisionsNovember 2018 Final Supplement to the Final EIS/EIR

Final Federal Feasibility Report2019 - 2021 Finalize design, permitting, local

agreements, state agency agreementsJanuary 2022 Final CWC funding agreements

2022-2024 Construct bid package #1 (pipes, pumps) and operations begin

2024-2027 Construct bid package #2 (dam raise, recreation) and public benefits begin

CWC Meeting December 13, 2017

17

ReferencesSlide Number Location in Application

2. Project Description (Section 3-4)3. Executive Summary 4. Executive Summary & Project Description (Section 3-4)5. Executive Summary & Project Description (Section 3-4)6. Executive Summary & Project Description (Section 3-4)7. Executive Summary & Project Description (Section 3-4)8. Project Conditions (Section 6-2)9. Project Description (Section 3-4)10. Executive Summary & Project Operations (Section 6-3)11. Executive Summary & Physical Public Benefits (Section 4)12. Project Description (Section 3-4) & Recreation (Section 4-4)13. Executive Summary & Project Description (Section 3-4)14. Executive Summary & Cost Allocation (Section 6-11)15. Executive Summary & Summary Tables (Section 6-12)16. Executive Summary & Feasibility & Implementation Risk

(Section 5-3)

CWC Meeting December 13, 2017

18

Thank youQuestions?

Project Informationhttp://www.ccwater.com/lvstudies

Contact InformationMarguerite PatilSpecial Assistant to the General ManagerContra Costa Water DistrictP.O. Box H20Concord, CA 94524(925) 688-8018mpatil@ccwater.com