Breakfast Seminar Building Information Modeling...1 Building Information Modeling 6 March 2008...

Preview:

Citation preview

1

Building Information Modeling

6 March 2008

Breakfast Seminar6 March 2008

Building Information Modeling

Alberto Cavallero AIA LEEDDesign PrincipalKlingStubbins

Douglas Palladino AIAPrincipalRTKL Associates Inc.

Ray Doyle PE LEEDEngineering Design Principal KlingStubbins

Alex ZolotovTechnical Lead, BIMClark Construction

Dirk HairePartnerHolland + Knight

2

Building Information Modeling

6 March 2008

DIVISION 1 – 3D Design Coordination

DIVISION 2 – Design Optimization

DIVISION 3 – Construction Implementation

DIVISION 4 – Long-Term Building Operation

3

Building Information Modeling

6 March 2008

DIVISION 1 – 3D Design Coordination

DIVISION 2 – Design Optimization

DIVISION 3 – Construction Implementation

DIVISION 4 – Long-Term Building Operation

Douglas Palladino AIAPrincipalRTKL Associates Inc.

Ray Doyle PE LEEDEngineering Design Principal KlingStubbins

Alex ZolotovTechnical Lead, BIMClark Construction

Dirk HairePartnerHolland + Knight

4

Building Information Modeling

6 March 2008

Division 1 – 3D Modeling and Coordination

The Master Builder Concept

5

Building Information Modeling

6 March 2008

DIVISION 1 – 3D Design Coordination

DIVISION 2 – Design Optimization

DIVISION 3 – Construction Implementation

DIVISION 4 – Long-Term Building Operation

Douglas Palladino AIAPrincipalRTKL Associates Inc.

Ray Doyle PE LEEDEngineering Design Principal KlingStubbins

Alex ZolotovTechnical Lead, BIMClark Construction

Dirk HairePartnerHolland + Knight

6

Building Information Modeling

6 March 2008

Project Time Line

`

Cost of C

hangeAbility to Change

Architect Effort

Architect Effort – BIM process

Division 2 – Design Optimization

7

Building Information Modeling

6 March 2008

DIVISION 1 – 3D Design Coordination

DIVISION 2 – Design Optimization

DIVISION 3 – Construction Implementation

DIVISION 4 – Long-Term Building Operation

Douglas Palladino AIAPrincipalRTKL Associates Inc.

Ray Doyle PE LEEDEngineering Design Principal KlingStubbins

Alex ZolotovTechnical Lead, BIMClark Construction

Dirk HairePartnerHolland + Knight

8

Building Information Modeling

6 March 2008

Division 3 – Construction Implementation

2D Info (Plans & Specs)3D Info

Component IntelligenceParametric Logic

BIM Team

2D Info3D

IntelligenceParametrics

Owner or Consultant

BIM-Based Team

Member

BIM-Based Team

Member

Defined by Team / Enabled by Software

Contractually Limited

9

Building Information Modeling

6 March 2008

DIVISION 1 – 3D Design Coordination

DIVISION 2 – Design Optimization

DIVISION 3 – Construction Implementation

DIVISION 4 – Long-Term Building Operation –the future of BIM

10

Building Information Modeling

6 March 2008

• Links to Computer-Aided Facility Management (CAFM) • Links to Building Automation Systems (BAS)

• Life Cycle Studies • Ease of Future Renovation

Project Time Line

`

Design & Construction Life of the Building

Division 4 – Long-Term Building Operation

13

Building Information Modeling

6 March 2008

DIVISION 1 – 3D Design Coordination

DIVISION 2 – Design Optimization

DIVISION 3 – Construction Implementation

Douglas Palladino AIAPrincipalRTKL Associates Inc.

Ray Doyle PE LEEDEngineering Design Principal KlingStubbins

Alex ZolotovTechnical Lead, BIMClark Construction

Dirk HairePartnerHolland + Knight

ENABLING INTEGRATED PRACTICE

11

Building Information Modeling

6 March 2008

ARCHITECT CONTRACTOR

OWNER

TRADITIONAL TEAM

RELATIONSHIPS

Implications – Contractual Relationships

SubsConsultants SubsConsultants

12

Building Information Modeling

6 March 2008

ARCHITECT CONTRACTOR

INTEGRATED PRACTICE

Implications – Contractual Relationships

SubsConsultants SubsConsultants

OWNER

Recommended