Bond Construction Bond Construction UpdateUpdateCitizens’ Oversight Citizens’ Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdateCitizens’ Oversight Citizens’ Oversight CommitteeCommittee
Long Beach Community College DistrictApril 21, 2008
BUILDING TOMORROW TODAY
Cordoba Corporation
Agenda Completed Construction Projects Current & Upcoming Construction Projects
South Quad Complex Structure LAC Central Plant Structure LAC Learning Resources Center – Structure LAC Building A, Student Services Retrofit PCC Central Plant PCC Learning Resources Center PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Administration Building)
Q & A
Construction Progress
Completed Construction Projects
PCC Industrial Technology Center Phase 2 – 7/07
PCC Central Plant Utilities, LAC Central Plant & SQC Utilities – 6/07
LAC/LRC Interim – 5/07 East Campus Demo – 12/06 LAC Men’s Gym Façade
Replacement (FEMA & Insurance Funded) – 8/06
LAC/LRC Utilities – 6/06 PCC CDC – 4/06 Men’s Gym Boiler
Replacement – 4/06 LAC Athletic Field – 3/06 District Facilities &
Warehouse Complex – 1/06
Various Projects – Completed in 2006 & 2007Various Projects – Completed in 2006 & 2007
LAC Facility Site Plan
l i b
e r
a l
a r
t s
Current and UpcomingConstruction Projects
Part of Infrastructure Master Plan Improvements
Awarded to Siemens on DBOM Contract
Construction 82% Complete Completion Anticipated
Summer 2008
LAC Central Plant – StructureLAC Central Plant – Structure
Current and UpcomingConstruction Projects
Construction 55% Complete
Combined into Single Construction Phase
Completion Anticipated December 2008
LAC/Learning Resources Center – StructureLAC/Learning Resources Center – Structure
Current and UpcomingConstruction Projects
Construction Approx. 52% Complete
Additional Modern Classrooms, Multi-purpose Rm., Offices, etc.
Shifts Campus Center South of Carson off Lew Davis
Completion Anticipated December 2008
South Quad Complex Structure (Bid Pkg. #3)South Quad Complex Structure (Bid Pkg. #3)
Current and UpcomingConstruction Projects
Martinez Architects received Board Approval as the Architect of Record
Contract was negotiated/signed and Notice to Proceed was issued
Programming work began on April 10, 2008
LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
PCC Facility Site Plan
p a
c i f
i c
c
o a
s t
Current and UpcomingConstruction Projects
Part of Infrastructure Master Plan Improvements
Early Utility Package Construction Complete
DBOM Contract Awarded to Siemens; Finalizing Value Engineering Negotiations
Construction Approximately 36% Complete
Completion Anticipated Summer 2008
PCC Central PlantPCC Central Plant
Current and UpcomingConstruction Projects
Construction 78% Complete Modern Facility with
Computer Lab and Multimedia
New Facility Bridge to Bldg. EE Completion Anticipated
July/August 2008
PCC Learning Resources CenterPCC Learning Resources Center
Current and UpcomingConstruction Projects
Replaces Existing Antiquated Structures
Construction is 12% Complete
Modern Facility Houses Machine Tool and Welding Departments
New Northern Face of the Campus
Completion Anticipated Spring 2009
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
Current and UpcomingConstruction Projects
Programming is completed and submitted to the State for Approval
Schematic Design was completed in February 2008
PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) (Multi-Disciplinary Academic Building)
QUESTIONS & ANSWERS
Prepared byBond Management Team
April 21, 2008
BUILDING TOMORROW TODAY
Cordoba Corporation