View
0
Download
0
Category
Preview:
Citation preview
© Husch Blackwell LLP
Best Practices for Managing Construction Delay and Interference Claims
Kenneth A. Slavens314.345.6419
WELCOME
Topics to be covered
DelayAccelerationDisruption
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Impact on Project Participants
For the contractorAdjustments in timeAdjustment in costs
For the ownerLoss of useLiquidated damages
© 2014 Husch Blackwell LLP. All rights reserved.
Escalation – Impact on Project Participants
More resources need to complete the project on schedule
Completion date need not be delayedIncreased cost attributable to performing work at a date later than plannedImpact of changes in sequence can cause escalation in costs
© 2014 Husch Blackwell LLP. All rights reserved.
Disruption – Effect on Project
Potential impact of extra work:Disruption in the planned sequence of the workExtend the work into inclement weatherImpact productivity of the trades
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Why talk about it?
For the contractorMay need additional timeMay consume additional resources
For the ownerProject not delivered when promised (loss of use)Not generating revenueEntitlement to Actual or Liquidated Damages
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Entitlement to Additional Time
Contractor's entitlement to additional time to complete:
If the delay is excusable
Potentially can recover increased costs as well
© 2014 Husch Blackwell LLP. All rights reserved.
Delays – If an excusable delay
For the contractor, an excusable delay will:Justify time extensionsPreclude termination of the contract for the delayPreclude recovery of actual or liquidated damage
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Is the delay excusable?
Read the Contract: frequently defines “excusable” delays
Examples common in contracts or if the contract is silentOwner or architect delaysActs of God / Unforeseeable EventsStrikesOwner Supplied materials
© 2014 Husch Blackwell LLP. All rights reserved.
Delays – What if the delay was foreseeability?
Some circumstances, even if the cause of the delay is an otherwise “excusable” event, it may not be excused
If the event is "known or knowable," i.e.: contractor knows that there is an impending strike when the contract is signed
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Impact of foreseeability on an otherwise excusable delay
Dicon, Inc. v. Marben Corp.
Contractor knew the owner would be late delivering plans and specs
Cannot rely on this owner delay for extra time
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Foundation Underlying an Excusable Delay
Implied term of every contract: Neither party will do anything to prevent performance by the other party or permit an act that will hinder or delay performance
Owner prevents or hinders the contractor's performance: excusable
Changes in the work at the direction of the Owner, for example, may cause an excusable delay
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Liquidated Damages
Generally enforceable
May need to show that the calculation of damages from late completion is impossible or very difficult to estimate at time of execution of the contract
Amount is a reasonable forecast of the harm of late completion
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Liquidated Damages and the Public Project
For public works contracts a reasonable approximate is not necessary
Public body needs to only show unexcused late completion
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Liquidated Damages
Liquidated Damage are the owner’s sole recovery for late completion
Even if the actual damages exceed the liquidated damage amount - as long a not “unreasonably disproportionate” to actual damages
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Notice of Delay
Read the contractFrequently required by the contractWhen in doubt – give the notice even if the contract is unclear
Failure to give the notice can bar an extension for an otherwise excusable delay.
See: Southwest Engineering Co. v. Reorganized School District R-9
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – It's Excusable, but is it compensable?
May be excusable, but does not equate to compensable (more money)
Excusable delay will entitle a contractor to more time
Must be compensable to be entitled to more money
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – What is compensable?
Compensable: damages are recoverable from the party that "caused" the delay
Neither party caused the delay: neither is entitled to recover from the other
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Compensable Delay
Examples of events for which the owner may have liability:
Work suspensionsInterferencesHindrancesDesign DefectsDiffering site conditions
© 2014 Husch Blackwell LLP. All rights reserved.
Protection from Delay Damages: No Damage for Delay Clauses
“No Damage for Delay” clauses – theoretically Protect the owner from all delays
Downside: contractor may build additional funds into the bid to account for the risk and drive up the cost (you may end up paying for an event that never happens)
Generally enforceable on private projects
© 2014 Husch Blackwell LLP. All rights reserved.
Protection from Delay Damages: No Damage for Delay Clauses
For public projects:
Many states have statutes invalidating these clauses on public works projects
Void in Missouri: Section 34.058, RSMo 2000
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – What Damages can be Recovered
Reasonably foreseeable damages caused by a compensable delay are recoverable
Increased labor Equipment Office overheadGeneral conditionsInterest
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – What Damages can be Recovered
Owner Damages:
Loss of use of the projectLoss of revenue which would have been generatedLiquidated Damages
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Overriding Principal to Damage Recovery
Increased costs are recoverableif the costs would not have been incurred, but for the delay
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Proving Damages
Methods of proving damages
Total Cost MethodModified Total Cost MethodJury Verdict Method
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Total Cost
Total Cost Method is highly disfavoredViewed with caution Considered a last resort
Underlying premise of Total Cost MethodContractor’s compensable damages are the difference between the costs expected at the outset (the contractor’s estimate) and the actual costs
Assumes the only reason for the delay is the owner-caused delay
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Total Cost
Assumes the project would have occurred exactly as expected, but for the excusable delay
Assumes:Original estimate of the contractor was accurateAll increased costs were caused by the other party
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Total Cost
To have the Total Cost Method accepted, must show:Impossible to estimate actual damages with a reasonable degree of certaintyThe estimate was accurateActual cost of performing the work was reasonableNo other causes for increased costs aside from the compensable delayContractor used a reasonable accounting system to accumulate job costs
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Total Cost
Fundamental Concept of Total Cost Recovery: the contractor cannot share any of the liability for the delays
Concept is virtually impossible to prove
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Modified Total Cost
Avoids inflexibility of Total Cost Method
Allows flexibility – particularly two main elementsAccuracy of the estimate
Can address inaccuraciesCan address mistakes
Actual Costs incurred: remove those costs not the responsibility of the Owner
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Jury Verdict Method
Different spin on the Total Cost MethodNeed to establish:
Contractor is damagedDefendant is responsible
Must prove damages "beyond speculation"Allows the “jury” to make a fair and reasonable approximation of the contractor’s damages
No Missouri case has accepted this method
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Schedule Analysis
Generally accepted – more reliable than the Total Cost Method, Modified Total Cost, or Jury Verdict
Use General Conditions ApproachSpecifically identify the effect of the delay on each element of increased costQuantify
The delay The increased costs
© 2014 Husch Blackwell LLP. All rights reserved.
Common Components of Delay Damages
Most commonly associated with a delay claimGeneral conditions (direct overhead)Office overhead (indirect overhead)Equipment CostsProductivity LossesAdditional Interest
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – General Conditions / Direct Overhead
Common elementsProject managers and project administratorsUtilitiesProject Trailer or OfficeSecurityEquipment
Generally can show a direct connection between increased project time and increased costs
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages - Extended Home Office Overhead / Indirect Overhead
Often called “indirect overhead” or “general and administrative costs”
Damages claimed in this area are often attackedThey are often thought of as “soft” damagesThey vary greatly depending on the accounting methods
No generally accepted protocol for what is included in home office overhead
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Extended Home Office Overhead / Indirect Overhead
Most of the home office overhead is time drivenIf a project is extended beyond the reasonable projection, home office costs are also extended
Not absorbed by the project
Costs incurred benefit all of the contractor’s projects
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Extended Home Office Overhead / Indirect Overhead
Virtually impossible to directly allocate overhead costs to a specific delay period
Fraught with accounting difficulties
Multiple jobs with varying start dates and completion dates makes it almost impossible
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Extended Home Office Overhead / Indirect Overhead
Recovery is based on the argument that there should be recovery because the delay precluded other projects from being able to absorb the overhead
Need to prove: Other work is available and the contractor would have been able to obtain that work; orThe contractor tried to obtain that work to absorb the overhead
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Extended Home Office Overhead / Indirect Overhead
Eichleay allocates home office overhead on a ratioDelayed project’s billings to the firm’s total contract billingsDuring the period of the performance of the delayed project
Total overhead amount for the period of the delayed project is divided by the number of actual contract days to determine daily rate
Multiply the number of days of delay by the daily overhead rate
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Home Office Overhead / Indirect Overhead
Use of Eichleay: still “estimates” the overhead
Fails to consider:Inefficient managementTiming of the delay on the overhead levelsImpact of other work during the project’s delay
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Recovery of Equipment Costs
Idle or under-utilized equipmentConsider
Ownership costsMaintenance RepairStorage Depreciation
Rental Rates
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Interest
Review the contractMay have circumstances when you can recoverMay have the rate for interest
Refer to the statute if no contract provisionSection 408.020 RSMo 2000Interest at 9%
If liquidatedLiquidated: amount can be determined by mathematical computation
© 2014 Husch Blackwell LLP. All rights reserved.
Delay Damages – Interest
Interest generally does not begin to accrue until there is a demand for payment
Make your liquidated claim as soon as possible to trigger the interest
© 2014 Husch Blackwell LLP. All rights reserved.
Delays – Problems caused by Concurrent or Joint Cause
General proposition: no liability for the other party’s delays unless
Caused by the partyCaused by circumstances under the party’s control
Contractual clauses can change this allocation of risk
© 2014 Husch Blackwell LLP. All rights reserved.
Delay – Early Completion
Even if the contractor finishes earlier than the contractual completion date
Can still claim a delay if the party can show the project would have finished earlier than it did but for the compensable delay
© 2014 Husch Blackwell LLP. All rights reserved.
Impact, Escalation, and Acceleration
Conduct of others may hinder productivity - even if finished on time
May cause:Out of sequence workStacking of tradesCongestionShift workAccess issues
© 2014 Husch Blackwell LLP. All rights reserved.
Impact, Escalation, and Acceleration
Escalation: increased cost attributable to performing the work at a later date than planned
Acceleration: process of adding resources to the project to complete on schedule
© 2014 Husch Blackwell LLP. All rights reserved.
Disruption
Generally associated with change ordersRipple effect impacts the project aside from the direct costs associated with the changeContractors will often try to preserve the indirect impact from the changesAbsent the preservation, the Owner may well have a valid defense to subsequent claims
The Change Order is “accord and satisfaction”Relieves the Owner from responsibility for the ripple effect
© 2014 Husch Blackwell LLP. All rights reserved.
Delays and Interference Claims
Ken Slavensken.slavens@huschblackwell.com
314-345-6419
© 2014 Husch Blackwell LLP. All rights reserved.
Best Practices for Managing Construction Delay
and Interference Claims
Prepared and Presented by:
Quackenbush & Associates
April 23, 2014
© 2014 Husch Blackwell LLP. All rights reserved.
A step by step presentation of a contemporaneous schedule
analysis performed during the project.
(Resolving delays as they occur)
© 2014 Husch Blackwell LLP. All rights reserved.
A RESTAURANT RENOVATION
30
Final Trimout - Project
Complete
47 3 89 3 7 4
Floor & Wall Tile In Kitchen
Laminate Panels In Kitchen
Sawcut Concrete Slab -Install Gas &
Plumbing Patch
Concrete
Kitchen WallFraming
Kitchen Rough-In Electrical
20 24 284 8 12 16
5 5 4 35 4 5 6
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
NTP & Complete Interior
Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
14 18 22 261 2 6 10
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37
5 14 14 17 17 24 24 28 28 35 35 38 38 46 46 50
A RESTAURANT RENOVATION
+9 +9 +9 +90 +3 +3 +4
1 2 6 10 14 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5 4 5 6 5 5 4 3
0 0 00 0 0 0
20 24 284 8 12 16
Floor & Wall Tile In Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 89 3 7 4
0
30
4
FLOAT
CRITICAL PATH KitchenDrywall
Set, Hook-Up & Test
All KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37
5 14 16 19 19 26 26 30 30 37 37 40 40 48 49 53
14 16 48 49
A RESTAURANT RENOVATIONIMPACT #1 - ADD 2ND DEEP FRYER
1
0
I10
2
0
I11
0
30
47 3 89 3 7 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
20 24 284 8 12 16
0 0 00 0 0 0
5 5 4 35 4 5 6
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
14 18 22 261 2 6 10
0 +5 +5 +6 +12 +12 +12 +12
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Original CompletionDate = 50Net Delay -3
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2nd
Deep Fryer
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
100% 5 75% 4
55% 9
UPDATE A - END OF DAY 10
1
I10
2
I11
30
47 3 83 7 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
20 24 284 8 12 16
4 35 6 5 5
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
14 18 22 261 2 6 10
KitchenDrywall
Set, Hook-Up
& Test
All KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
0 1
4
Update AEnd of Day 10
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
11 11 16 16 22 22 27 27 32 32 36 36 39
100% 5 75% 4
14 16 19 19 26 26 30 30 37 37 40 40 48 49 53
55% 9
14 16 48 49
UPDATE A - END OF DAY 10
+10 +10 +10 +10+3 +3 +4
1 2 6 10 14 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5 6 5 5 4 3
0 0 00 0 0 0
20 24 284 8 12 16
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 83 7 4
0
30
4
1
0
I10
2
0
I11
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Project CompletionUnchanged - NetDelay = 0Some Float UsedOn Non-CriticalActivities
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
0 1
4
Update AEnd of Day 10
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
5
100% 0 75% 1
55% 4
IMPACT #2 - FIND AND MOBILIZE NEW ELECTRICAL SUBCONTRACTOR
I20
New Electrical Sub
1 2 6 10 14 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5 6 5 5
20 24 284 8 12 16
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 83 7 4
30
4
I11
4 3
1
I10
2
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE15
5
11 15 20 20 26 26 31 31 36 36 40 40 43
100% 0 75% 1
14 16 19 20 27 27 31 31 38 38 41 41 49 50 54
55% 4
14 16 49 50
IMPACT #2 - FIND AND MOBILIZE NEW ELECTRICAL SUBCONTRACTOR
1
I10
2
I11
4 3
30
47 3 83 7 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
20 24 284 8 12 16
5 6 5 5
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
14 18 22 261 2 6 10
I20
New Electrical Sub
KitchenDrywall
Set, Hook-Up
& Test
All KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Project CompletionExtended by 1 Day = Total Delays to Date -4
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
© 2014 Husch Blackwell LLP. All rights reserved.
Was Impact #2 – Electrical Subcontractor Replacement paced?What other options did contractor have?1. Pay premium to start ASAP.2. Hire on time and materials basis.
What if contractor mis-judges the amount of pacing time available?Is it still pacing?
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR
54 -1 SEE BELOW
Summary of Delays (If Impact #2 Was Paced)
Owner Responsible (Impact #1 & #3)
Contractor Responsible (Impact #2)
Summary of Delays (If Impact #2 Was Not Paced)
Owner Responsible (Impact #3)
Contractor Responsible (Last Day Impact #2)
Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
100% 5
20 20 26 26 31 31 36 36 40 40 43
100% 0 75% 1 60% 5
20 20 27 27 31 31 38 38 41 41 49 50 54
55% 4 3
49 50
UPDATE B - END OF DAY 18
47 3 8
3020 24 284 8 12
1
I10
2
I11
4 3
7 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
16
6 5 5
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
14 18 22 261 2 6 10
I20
New Electrical Sub
KitchenDrywall
Set, Hook-Up
& Test
All KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
Update BEnd of Day 18
2
0
0100%
100% 0
100% 0
30% 2
Project CompletionDate UnchangedDelays to Date -4
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR
54 -1 SEE BELOW
4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0
Summary of Delays (If Impact #2 Was Paced)
Owner Responsible (Impact #1 & #3)
Contractor Responsible (Impact #2)
Summary of Delays (If Impact #2 Was Not Paced)
Owner Responsible (Impact #3)
Contractor Responsible (Last Day Impact #2)
Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
100% 0
20 20 26 26 31 31 36 36 40 40 43
100% 0 100% 0 60% 2
20 20 27 30 34 34 41 41 44 44 52 53 57
100% 0 2
27 30 52 53
IMPACT #3 CITY REQUIRES ELECTRICAL IMPROVEMENTS
I30
3
I20
New Electrical Sub
14
6 5
1 2 6 10 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5
20 24 284 8 12 16
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 87 4
30
4
4 3
1
I10
0
I11
KitchenDrywall
Set, Hook-Up
& Test
All KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
Piping
For 2nd Deep Fryer
Install 2ndDeep Fryer
100%
30%
Project CompletionExtended by -3 DaysProject Delay to Date = -7
CityRequiresElectrical
Improvements
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR
54 -1 SEE BELOW
4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0
5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE
57 -3
Summary of Delays (If Impact #2 Was Paced)
Owner Responsible (Impact #1 & #3)
Contractor Responsible (Impact #2)
Summary of Delays (If Impact #2 Was Not Paced)
Owner Responsible (Impact #3)
Contractor Responsible (Last Day Impact #2)
Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
100% 0
35 35 40 40 44 44 47
100% 0 100% 0 60% 2
34 34 41 41 44 44 52 53 57
100% 0 2
52 53
UPDATE C END OF DAY 31
1
I10
0
I11
4 3
30
47 3 87 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
24 284 8 12 16 20
Dining Area Carpet
5
18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
1 2 6 10
I30
3
I20
New Electrical Sub
14
6 5
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
100%
30%
Project CompletionDate - UnchangedDelays to Date -7
CityRequiresElectrical
Improvements
100%0
100%0 100% 0
100% 0
100% 20% 4
25% 3
0
Update CEnd of Day 31
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR
54 -1 SEE BELOW
4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0
5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE
57 -3
6 N/A DAY 31 6 STATUS UPDATE – END OF DAY 31 57 0
Summary of Delays (If Impact #2 Was Paced)
Owner Responsible (Impact #1 & #3)
Contractor Responsible (Impact #2)
Summary of Delays (If Impact #2 Was Not Paced)
Owner Responsible (Impact #3)
Contractor Responsible (Last Day Impact #2)
Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
100% 0
41 41 46 46 50 50 53
100% 0 100% 0 100% 0
41 41 44 44 52 53 57
100% 0 100% 0
52 53
UPDATE D END OF DAY 40
I30
0
I20
New Electrical Sub
14
0 5
1 2 6 10 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5
20 24 284 8 12 16
Floor & Wall Tile In Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 80 4
30
4
4 3
1
I10
0
I11
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
100%
Project CompletionDate - UnchangedDelays to Date -7
CityRequiresElectrical
Improvements
100%
100%
100% 80% 1
100% 0
Update DEnd of Day 40
90% 1
Update DEnd of Day 40
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR
54 -1 SEE BELOW
4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0
5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE
57 -3
6 N/A DAY 31 6 STATUS UPDATE – END OF DAY 31 57 0
7 N/A DAY 40 7 STATUS UPDATE – END OF DAY 40 57 0
Summary of Delays (If Impact #2 Was Paced)
Owner Responsible (Impact #1 & #3)
Contractor Responsible (Impact #2)
Summary of Delays (If Impact #2 Was Not Paced)
Owner Responsible (Impact #3)
Contractor Responsible (Last Day Impact #2)
Concurrent (Impact #1 & First 3 Days of Impact #2)© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS TECHNIQUE
100% 0
53
100% 0 100% 0 100% 0
53 57
100% 0 100% 0
51 52
UPDATE E END OF DAY 51
1
I10
0
I11
4 3
30
47 3 80 0
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
24 284 8 12 16 20
Dining Area Carpet
5
18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
1 2 6 10
I30
0
I20
New Electrical Sub
14
0 15
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
100%
CityRequiresElectrical
Improvements
100%
100%
100% 100%
100%
Update EEnd of Day 51
100% 0
Update EEnd of Day 51
100% 0
100% 0 100% 0 30% 2
100% 0
0
Project CompletionDate - UnchangedDelays to Date -7
© 2014 Husch Blackwell LLP. All rights reserved.
CONTEMPORANEOUS SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
IMPACTSTEP
DELAYSTARTDATE
DATADATE
SCHEDULERUN
NUMBER DESCRIPTION
PROJECTEDCOMPLETION
DATE
DAYSOF
DELAY CONCURRENCY
0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0
1 DAY 2 DAY 0 1 IMPACT #1 – ADD 2ND DEEP FRYER 53 -3
2 N/A DAY 10 2 STATUS UPDATE – END OF DAY 10 53 0
3 DAY 10 DAY 10 3 IMPACT #2 – REPLACE ELECTRICAL SUBCONTRACTOR
54 -1 SEE BELOW
4 N/A DAY 18 4 STATUS UPDATE – END OF DAY 18 54 0
5 DAY 22 DAY 18 5 IMPACT #3 – CITY REQUIRES ELECTRICAL UPGRADE
57 -3
6 N/A DAY 31 6 STATUS UPDATE – END OF DAY 31 57 0
7 N/A DAY 40 7 STATUS UPDATE – END OF DAY 40 57 0
8 N/A DAY 51 8 STATUS UPDATE – END OF DAY 51 57 0
Summary of Delays (If Impact #2 Was Paced)
Owner Responsible (Impact #1 & #3) = -6 Compensable Days
Contractor Responsible (Impact #2) = -1 Non-Compensable Days
Summary of Delays (If Impact #2 Was Not Paced)
Owner Responsible (Impact #3) = -3 Compensable Days
Contractor Responsible (Last Day Impact #2) = -1 Non-Compensable Days
Concurrent (Impact #1 & First 3 Days of Impact #2) = -3 Excusable/Non-Compensable Days© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS
5 4 5
9 3
14
6 5
6 10 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
1 2
4 8 12 16
Kitchen WallFraming
Kitchen Rough-In Electrical
7 4
Floor & Wall Tile In
Kitchen
30
47 3 8
24 2820
4 3
Dining Area Carpet
5
18 22
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
RESTAURANT RENOVATION - AS-PLANNED SCHEDULE
© 2014 Husch Blackwell LLP. All rights reserved.
THE BUT-FOR LEGAL CONCEPT
You can only claim damages (money and/or time) for delays that would not have been experienced “but-for” the delay in question.– Basis of concurrent delay theory– If you would have finished the project at the
same time – even if delay in question had not occurred – then you have a concurrent delay.
(Maybe! – Must Consider Pacing!)© 2014 Husch Blackwell LLP. All rights reserved.
“BUT-FOR” SCHEDULE ANALYSIS
(If it makes sense in evaluating concurrent delays – why doesn’t it make sense in schedule analysis?)
© 2014 Husch Blackwell LLP. All rights reserved.
THE PIT BULL PROJECT
© 2014 Husch Blackwell LLP. All rights reserved.
© 2014 Husch Blackwell LLP. All rights reserved.
PIT BULL MOVES IN NEXT DOOR
Pit Bulls can jump 3’ wall.Pit Bulls cannot jump 6’ wall.Owner directs contractor to build wall 6’ high instead of 3’ high.Contractor says – ok – but it will cost more and take 2 weeks longer.Owner OK’s added work
© 2014 Husch Blackwell LLP. All rights reserved.
© 2014 Husch Blackwell LLP. All rights reserved.
© 2014 Husch Blackwell LLP. All rights reserved.
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS
0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37
5 4 5
5 14 14 17 17 24 24 28 28 35 35 38 38 46 46 50
9 3
24 28
8
30
47 37 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
4 8 12 16 20
Dining Area Carpet
5 4 3
18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
1 2 6 14
6 5
10
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
RESTAURANT RENOVATION - AS-PLANNED SCHEDULE
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS0 15
15
0 5 5 9 15 20 20 26 26 41 41 46 46 50 50 53
5 4 5
5 14 16 20 20 27 30 34 34 41 41 44 44 51 53 57
9 4
14 16 27 30 51 52
AS-BUILT SCHEDULE
1
I10
2
I11
4 3
30
47 3 77 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
24 284 8 12 16 20
Dining Area Carpet
5
18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Dining Area Décor &
Woodwork
1 2 6 10
I30
3
I20
New Electrical Sub
14
6 15
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
CityRequires
ElectricalImprovements
As-BuiltCritical Path
LightFixtures
& ElectricalTerminations
Note: this work took longer than planned.
Note: this work was performed faster than planned.
Note: this work was paced to known project delays.
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS
15
5 4 5
9 4
COLLAPSE OWNER DELAYS
1
I10
2
I11
4 3
30
47 3 77 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
24 284 8 12 16 20
Dining Area Carpet
5
18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
1 2 6 10
I30
3
I20
New Electrical Sub
14
6 15
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
CityRequiresElectrical
ImprovementsWhen would project have been completed if owner delays had not occurred?
0 0 0
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS0 15
15
0 5 5 9 15 20 20 26 26 41 41 46 46 50 50 53
5 4 5
5 14 14 18 20 27 27 31 31 38 38 41 41 48 53 57
9 4
COLLAPSE OWNER DELAYS - RECALCULATE CRITICAL PATH
I30
3
I20
New Electrical Sub
14
6 15
1 2 6 10 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5
20 24 284 8 12 16
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 77 4
30
4
4 3
1
I10
2
I11
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
CityRequiresElectrical
ImprovementsWhen would project have been completed if owner delays had not occurred?0 0 0
Owner Delays Collapsed From Schedule - No Change In Completion Date - No Compensable Delays
Critical Path With Owner's Delays Collapsed Out
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS
15
5 4 5
9 4
COLLAPSE CONTRACTOR DELAYS
1
I10
2
I11
4 3
30
47 3 77 4
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
24 284 8 12 16 20
Dining Area Carpet
5
18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
1 2 6 10
I30
3
I20
New Electrical Sub
14
6 15
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
Sawcut Concrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
CityRequiresElectrical
ImprovementsIf contractor delays had not occurred when would the project have finished?
3
5
0
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT ANALYSIS0 0
15
0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37
5 4 5
5 14 16 19 19 26 29 33 33 40 40 43 43 50 51 55
9 4
14 16 26 29 50 51
COLLAPSE CONTRACTOR DELAYS - RECALCULATE CRITICAL PATH
I30
3
I20
New Electrical Sub
14
6 15
1 2 6 10 18 22 26
NTP & Complete
Interior Demolition
Wall & Soffit Framing
Dining Area
Electrical Rough-In
Dining Area
Drywall In Dining Area
Painting Dining Area
Light Fixtures & Electrical
Terminations
Dining Area Décor &
Woodwork
Dining Area Carpet
5
20 24 284 8 12 16
Floor & Wall Tile In
Kitchen
Kitchen WallFraming
Kitchen Rough-In Electrical
7 3 77 4
30
4
4 3
1
I10
2
I11
KitchenDrywall
Set, Hook-Up
& TestAll KitchenEquipment
Laminate Panels InKitchen
Final Trimout -Project
Complete
SawcutConcrete
Slab - Install Gas
& Plumbing Patch Conc.
Saw Cutting &
PipingFor 2nd
Deep Fryer
Install 2ndDeep Fryer
CityRequiresElectrical
ImprovementsIf contractor delays had not occurred when would the project have finished?
3
5
0
Contractor Delays Collapsed From Schedule Completion Date 2 Days Earlier, Contractor Responsible for 2 Days of Delay
Critical Path With Contractor's Delays Collapsed Out
© 2014 Husch Blackwell LLP. All rights reserved.
COLLAPSED AS-BUILT SCHEDULE ANALYSISRESTAURANT RENOVATION
QUACKENBUSH & ASSOCIATES, INC.
PROJECTED DAYSCOMPLETION OF
STEP DESCRIPTION DATE DELAY CONCURRENCY
1 As-Planned Schedule 50 0
2 As-Built Schedule 57 -7
3 Collapse Owner Delays 57 0
4 Collapse Contractor Delays 55 -2
5 Remainder of Delays Concurrent Between Owner & Contractor 55-50 -5
Summary of Delays:Owner Responsible 0Contractor Responsible 2Concurrent Responsible 5
© 2014 Husch Blackwell LLP. All rights reserved.
Concurrency CriteriaTwo or More Delays in Same Time FrameBoth Delays Must be on Critical Path– Both Must Control the Project Completion
DateBut – For The Other Delay
Both Delays Must be Completely Independent
PhysicallyManagerially (No Pacing)
© 2014 Husch Blackwell LLP. All rights reserved.
CONCURRENT DELAYSMEETING AT DENNY’S
SCENARIO #1Bill and Dan agree to have a business meeting at Denny’s the next morning at 7:00AM. Both Bill and Dan leave their home with enough time to arrive at Denny’s by 7:00 AM.Bill decides to stop at the dry cleaners on the way, which consumes 10 minutes.Dan has a flat tire and it takes him 15 minutes to change the tire.Bill arrives at Denny’s at 7:10 AM and is relieved to see that Dan has not yet arrived.Dan arrives at 7:15AM. Bill says “Boy, Dan you are 15 minutes late. I have been waiting here a long time. You really need to be more responsible.”
WHO DELAYED THIS BREAKFAST MEETING AND BY HOW MANY MINUTES?
Answer: Dan and Bill jointly delayed the meeting by 10 minutes, Dan delayed the meeting an additional 5 minutes. Reason: Both Bill and Dan were required at the meeting or it could not occur, thus they were both on the critical path, and both individuals acted independently. (Neither party knew the other was running late.) Thus a 10 minute Concurrent Delay. © 2014 Husch Blackwell LLP. All rights reserved.
CONCURRENT DELAYSMEETING AT DENNY’S
SCENARIO #2Bill and Dan agree to have a business meeting at Denny’s the next morning at 7:00AM. Both Bill and Dan leave home with enough time to arrive at Denny’s by 7:00 AM.Bill has dry-cleaning to drop off but decides he better do that later so he can be on time to the meeting.Dan gets a flat tire and he immediately calls Bill on his cell phone to tell him he will be 15 minutes late. Bill decides he now has the time to drop the dry cleaning off and arrives at Denny’s at 7:10 AM. Dan arrives at 7:15 AM.
WHO DELAYED THIS BREAKFAST MEETING AND BY HOW MANY MINUTES?
Answer: Dan delayed the meeting by 15 minutes. Bill did not delay the meeting at all. No Concurrent Delay Reason: Both Bill and Dan were required at the meeting, thus they were both on the critical path, but both individuals did not act independently. (Bill modified his planned approach based on information provided by Dan.) THIS IS COMMONLY CALLED PACING. Bill adjusted his activities based on Dan’s delay.
© 2014 Husch Blackwell LLP. All rights reserved.
QUESTIONS?THANK YOUhuschblackwell.com
© 2014 Husch Blackwell LLP. All rights reserved.
Recommended