Site Overview
Reliance CSP Project Snapshot
May 2014
100% Receivers lifted (35 in total)
Receiver with Boiler tube
ICP
ICP Line
Phase 2 ICP Steam blow
Power Block
Insulation Towers
Steam production
Steam column around 100m high
Safety Stand Down
Physical Progress on site (as of May 2014)
Mechanical completion
100%
Electrical completion
97%
I & C completion
97%
25 SSGs commissioned (out of 35) Preparing for the synchronization with grid