Architect: Greg Miller, Georgia Tech Engineer: Stratton Newbert, Stanford Construction: Lori...

Preview:

Citation preview

Architect: Greg Miller, Georgia Tech

Engineer: Stratton Newbert, Stanford

Construction: Lori Huneryager, Stanford

Apprentice: Forest Flager, Stanford

Owner: Hans Verheij, Georgia Tech

Architect: Greg Miller, Georgia Tech

Engineer: Stratton Newbert, StanfordConstruction: Lori Huneryager, Stanford

Apprentice: Forest Flager, Stanford

Owner: Hans Verheij, Georgia Tech

Atlantic Team 2000Atlantic Team 2000

Picking a Site

• Boston, MA

• Engineering School of Atlantic University

Alternative T

BASEMENT FLOOR 1 FLOOR 2

SECTION THROUGH AUDITORIUM

Alternative C

BASEMENT FLOOR 1 FLOOR 2

SECTION THROUGH AUDITORIUM

Alternative

Alternative O

BASEMENT

FLOOR 1FLOOR 2

SECTION THROUGH AUDITORIUM

ENTRY

AUD.

Alternative L

BASEMENT FLOOR 1 FLOOR 2

SECTION THROUGH AUDITORIUM

SOUTH ELEVATION

Construction Comparisons

T L O C

May 1 +$15,000+$10,000

ConcreteSteel *38 Weeks*42 Weeks

May 1

Alternative Comparisons

•Strong A&E•Early lab access•Challenging

•Vertical circulation•Efficient layout•Dramatic dome

•Strong architecture•Vertical light & circulation

•Simple structure•Strong circulation•Early lab

•Truss assembly•Most expensive•Second egress system

•3rd Floor construction•No early lab access

•“Opening” •Life-cycle costs•Cantilevered corners

•High % circulation space•Exterior design not strong

T L O C

Architectural Architectural Vision…Vision…

High Museum, Atlanta

Building EE, Downtown DisneyArchitect

Architectural Collage

Architect

Main Entrance

Architect

Small Classrooms

Large Classrooms

Computer Lab

Faculty Lounge

Mechanical Room

Storage

Restrooms

Technical Support

Basement Level

Architect

Faculty Offices

Chair’s Office

Administration

Restrooms

Mechanical Room

Storage

First Floor

Secretarial Space

Architect

Auditorium

Student Offices

Laboratories

Seminar Rooms

Mechanical Room

Restrooms

Second Floor

Architect

Basement Level

Basement Level

Construction Site Plan8-10’

8-10’

20-25’

Braced Excavation OptionsSLURRY WALLS SOLDIER PILES

Prevents horizontal flow of water

Can be used as permanent retaining wall

Excavation time doubled

Excavation cost increased by 30%

Time & Cost Benefits

Groundwater should not be an issue

Proper Spacing of planks can eliminate water pressure

SHEET PILES

Good to control seepage, construction below water table

Bracing needed – beyond property line

Soldier Piles

Excavation

Finished Mats

Mats in Progress

Finished Walls

Walls in Progress

Milestone #1 Complete – 14 weeks

EXCAVATION SEQUENCE 1

Soldier Piles

Excavation

Finished Mats

Mats in Progress

Finished Walls

Walls in Progress

Milestone #1 Complete – 11.5 weeks

EXCAVATION SEQUENCE 2

Elapsed Time = 7 weeks

FINAL EXCAVATION SEQUENCE

Basement Level

First Floor

First Floor

Second Floor

Second Floor

Roof

Roof

Structural Sequencing1

2

Roof

Roof

STRUCTURAL STEEL COSTS

Column WeightsColumn Length (ft) Column Weight (lbs/l.f.) Quantity Total Weight (lbs)

W14x90 40 90 12 43200W14x90 30 90 2 5400W14x49 40 49 4 7840W14x50 12 49 1 588W14x51 24 49 1 1176

First Floor Beam WeightsBeam Length (ft) Beam Weight (lbs/l.f.) Quantity Total Weight (lbs)

W16x36 30 36 17 18360W14x26 30 26 23 17940W16x50 30 50 0 0W12x19 10 19 4 760W12x14 5 14 22 1540

Channels 30 34 10 10200

Second Floor Beam WeightsBeam Length (ft) Beam Weight (lbs/l.f.) Quantity Total Weight (lbs)

W14x26 30 26 14 10920W16x36 30 36 18 19440W16x50 30 50 10 15000W12x19 10 19 20 3800W12x14 5 14 22 1540

W36x135 40 135 1 5400W21x50 40 50 5 10000W24x62 40 62 4 9920

Roof Beam WeightsBeam Length (ft) Beam Weight (lbs/l.f.) Quantity Total Weight (lbs)

W14x38 30 38 20 22800W16x50 30 50 14 21000W21x50 40 50 5 10000W24x76 40 76 2 6080

Dome WeightsBeam Length (ft) Beam Weight (lbs/l.f.) Quantity Total Weight (lbs)

W10x12 45 12 16 8640C6x20 8 20 32 5120

Total Weight 256664x Connection & Misc. 1.2

x Price per Lb. $1.00COST $307,997

Structural CostBudget: $450,000

NPV = $335,000 (3% inflation)

*Actual Cost includes Steel Members and HVAC Penetrations

Cost Comparison

Dome

Seismic Base Shear

0

0.01

0.02

0.03

0.04

0.05

0.06

0.07

0 2 4 6 8 10

T

Sa

SV C W

23

1.2 2.5V aS

A S AC

RRT

Response Spectrum

Structural System

R Cs W(k)

V(k)

Steel 4.5 6.7% 3100 207

Concrete 3 10% 4000 400

Building Behavior

Mode 1Mode 2

Mode 4

Mode 3

MEP Considerations

Boston Annual Extremes:

Max = 96 F

Min = 0 F

Mechanical Equipment:

AHU: Carrier 48MP10R – Electric Cooling, Gas Heating

W = 27,100 lbs, Dims = 48’8” x 11’3” x 8’5”

Chiller: Carrier 16DF013 – Absorption Chiller & Heater

W = 13,450 lbs, Dims = 12’6” x 6’8” x 7’9”

HVAC LayoutsFirst Floor Second Floor

Roof Roof

28 girder penetrations ~ $150,000

Equipment Needs

Grove TMC9210:

Capacity = 120 tons

Main Boom = 34-105 feet

Driving Piles: Vibratory HammerExcavation = 3650 c.y.

Gradall Hydraulic Excavator XL4100:

• Digging Depth = 22’6”

Gradall Material Handler 534D-6

Maximum Lift Height = 36’

Maximum Reach = 23’

attached to crane or backhoe

Cost EstimatingDIVISION Unit # Units Unit Cost COST 2000 COST AFTER INFLATION

1 - FoundationsConcrete in Place, Foundation mat, over 20 CY CY 748 $188 $140,624 $149,188

033 130 4050

Reinforcing TON 9.87 $1,275 $12,584 $13,351032 107 0600

Forms in place, Mat Foundation, 3 Use SFCA 3712 $6.65 $24,685 $26,188031 100 0100

Retaining Walls, CIP, pumped, 12' high, 12" thick LF 464 $145.50 $67,512 $71,6231.1-210 7260

Retaining Walls, CIP, pumped, 10' high, 12" thick LF 0 $117.00 $0 $01.1-210 6260

Retaining Walls, CIP, pumped, 8' high, 12" thick LF 0 $94.00 $0 $01.1-210 5260

Foundation Dampproofing, Bituminous, 1 Coat, 12' high LF 58 $9.34 $542 $575A1.1-292 1800

Foundation Dampproofing, Bituminous, 1 Coat, 8' high LF 406 $6.06 $2,460 $2,610A1.1-292 1400

$263,535

2 - Substructure$0

3 - SuperstructureComposite Deck, Slab SF 18584 $13.10 $243,450 $258,277

Stairs, grate type, 12 risers with landing FLIGHT 4 $3,325 $13,300 $14,110A3.9-100 0640

Structural Steel LB 256664 $1.20 $307,997 $326,754

Girder Penetration EA 28 $5,000 $140,000 $148,526

Fireproofing of Steel LF 4640 $4.57 $21,205 $22,496$770,162

7 - ConveyingElevators EA 1 $75,000 $75,000 $79,568

$79,568

8 - MechanicalTotal Mechanical Systems $1,200,000 $1,200,000

$1,200,000

9 - Electrical$650,000 $650,000

$650,000

11 - Special Construction$0

12 - Site WorkExcavation, hydraulic excavator CY 3650 $5.50 $20,075 $21,298

022 238 1800

Hauling, 3 mile round trip CY 4200 $8.20 $34,440 $36,537022 266 0150

Soldier Piles - W24x76 LF 3190 $56.50 $180,235 $191,211051 250 5500

Lagging, 3" thick wood between piles SF 3712 $8.00 $29,696 $31,504021 620 2400

Chain Link Fence LF 536 $11.15 $5,976 $6,340015 304 0010

$286,891

$3,884,322

Budget vs. Actual CostBudget: $5.5 million NPV = $4.1 million (3% inflation)

SchedulingStart Date: October 2, 2011

Finish Date: April 26, 2012

Elapsed Time: 7 months

Architectural Review

Security

Daylight

Views

Total SF

Percentage of Requirements Met

Square Footage Comparison

Architect

Atlantic Team Dynamics

A

EC

I like the feel of

the space

Apprentice

can make it fit into our budget?

but what about the structure

Owner

I’m so HAPPY

Winter Quarter

Atlantic Team Dynamics

A

EC

Well, I’ve graduated, so I’m out of here!

Apprentice

Now, how do we make our ideas

buildable?

Get your own coffee Stratton

Owner

I’m still HAPPY

Spring Quarter

Thank You !Atlantic Team 2000Atlantic Team 2000

Mentors•Greg Luth, KL&A

•Eric Elssesser, Frorell Elssesser

•Chuck Madewell

•Bob Tatum, Stanford

•Ronald Borja, Stanford

Recommended