View
224
Download
1
Category
Preview:
Citation preview
American University Revision 1.1
Master Commissioning Plan Page 1 March 5, 2012
American University Master Commissioning Plan
Revision 1.1
Table of Contents
Section Page
1 Introduction ......................................................................................... 2
2 Commissioning Team Members ......................................................... 3
3 Systems to be Commissioned ........................................................... 4
4 Commissioning Process Matrix ......................................................... 6
5 Commissioning Process Flowchart ................................................... 9
6 Commissioning Activities Narratives .............................................. 10
7 Commissioning Documentation ....................................................... 29
American University Revision 1.1
Master Commissioning Plan Page 2 March 5, 2012
1 Introduction Commissioning is defined as a systematic process of assuring by verification and documentation,
from the design phase to a minimum of one year after construction that all building facility
systems perform interactively in accordance with the design documentation and intent, and in
accordance with the owner’s operational needs, including preparation of operations personnel.
This Commissioning Plan is intended to be a roadmap for the parties involved in the
Commissioning process. It lists the systems to be commissioned, the Commissioning process
activities, and the roles and responsibilities for each party involved.
The goals of the Commissioning Plan are to identify and define the following:
Systems to be commissioned.
Commissioning team members.
Commissioning activities.
Commissioning Team member responsibilities for each Commissioning activity.
Documentation requirements from each activity and Commissioning Team member.
Schedule parameters (i.e., how will Commissioning activities integrate into the other
project delivery milestones?).
Acceptance criteria for the completion of commissioning.
The Commissioning Process Matrix and Flowchart graphically depict the commissioning process
and its flow from the Planning Phase through the Warranty Phase. These are intended to be a
quick reference for identifying the fundamental components of commissioning and their
relationship to each other. The Master Commissioning Process Narrative provides more detail
regarding the activities, responsibilities, and deliverables associated with each activity in the
Commissioning Process Matrix and Flowchart. For each Matrix row and Flowchart box, there is
a corresponding narrative description. To supplement these sections, Section 7 includes
Commissioning documentation templates and examples.
American University Revision 1.1
Master Commissioning Plan Page 3 March 5, 2012
2 Commissioning Team Members
Role Company Title Name
Phone
Number Email Address
Project
Manager
American
University Project Manager
Construction
Manager
American
University
Construction
Manager
Facilities
Management
American
University Cx Authority
Other
University
Departments
American
University
American
University
American
University
American
University
Design Team
Architect
Mechanical
Engineer
Electrical Engineer
Construction
Team
General Contractor
Mechanical
Contractor
Electrical Contractor
TAB Contractor
Controls Contractor
Commissioning
Manager
Project Manager
Lead Mechanical
Lead Electrical
American University Revision 1.1
Master Commissioning Plan Page 4 March 5, 2012
3 Systems to be Commissioned
SYSTEMS SAMPLING
Mechanical Systems
HVAC System TBD
Indoor Air Quality Monitoring System TBD
Energy Management System TBD
Domestic Water Booster System TBD
Domestic Hot Water System TBD
Irrigation Controls TBD
Grey Water Systems TBD
Life Safety Systems
Fire Suppression System TBD
Fire Alarm System 100%
Smoke Management Systems TBD
Electrical Systems
Normal Power Systems (mains, power distribution, and breakers) TBD
Emergency Electrical Power (emergency generators, automatic
transfer switches, mains, power distribution, and breakers)
TBD
Critical Power (mains, power distribution, breakers, and
uninterruptible power supplies)
TBD
Lighting Controls TBD
Vertical Transport Systems TBD
Building A/V & Communications Systems TBD
Security Systems
Card Access TBD
Cameras TBD
American University Revision 1.1
Master Commissioning Plan Page 5 March 5, 2012
Building Envelope
Walls TBD
Windows TBD
Roof/Flashing TBD
Subgrade Waterproofing TBD
Insulation TBD
Air and Vapor Barriers TBD
Expansion Joints TBD
Specialty Systems
Classroom/Conference Room Audio-Visual, Lighting, &
Communications
TBD
Kitchen Systems TBD
Laboratory Support Systems TBD
American University Revision 1.1
Master Commissioning Plan Page 6 March 5, 2012
4 Commissioning Process Matrix The following matrix tabulates the major commissioning activities; when they occur during the
project life cycle; and the commissioning team member roles and responsibilities for each
activity. For additional detail, please refer to Section 6: Commissioning Activities Narratives.
In the Commissioning Team Member columns an “R” indicates the responsible team member for
each activity, and a “✓” indicates a team member who needs to participate in the activity.
PROJECT PHASES COMMISSIONING TEAM MEMBERS
Pla
nn
ing
Des
ign
Co
nst
ruct
ion
Acc
epta
nce
War
ran
ty
AU
Pro
ject
Man
ager
AU
Co
nst
ruct
ion M
gr
AU
Fac
ilit
ies
Cx
Au
thori
ty
Oth
er A
U D
epar
tmen
ts
Des
ign
Tea
m
Co
nst
ruct
ion T
eam
Cx
Man
ager
Preliminary Commissioning Plan ✓ R
Owner’s Project Requirements
(OPR) Document ✓ ✓ ✓ ✓ R ✓ ✓
Design Phase Commissioning
Coordination Meetings ✓ ✓ ✓ ✓ ✓ R
Basis of Design (BOD) Document ✓ ✓ ✓ ✓ R ✓
O&M Documentation Planning ✓ R ✓
O&M Training Planning ✓ R ✓
Warranty Planning ✓ ✓ R ✓
Commissioning Design Reviews ✓ ✓ ✓ ✓ ✓ ✓ R
Preliminary Prefunctional
Checklists & Functional Performance Tests
✓ ✓ R
Final Commissioning Plan ✓ ✓ ✓ ✓ ✓ R
Commissioning Specification ✓ ✓ ✓ R
Construction Phase
Commissioning Coordination
Meetings ✓ ✓ ✓ ✓ R
American University Revision 1.1
Master Commissioning Plan Page 7 March 5, 2012
PROJECT PHASES COMMISSIONING TEAM MEMBERS
Pla
nn
ing
Des
ign
Co
nst
ruct
ion
Acc
epta
nce
War
ran
ty
AU
Pro
ject
Man
ager
AU
Co
nst
ruct
ion M
gr
AU
Fac
ilit
ies
Cx
Au
thori
ty
Oth
er A
U D
epar
tmen
ts
Des
ign
Tea
m
Co
nst
ruct
ion T
eam
Cx
Man
ager
Commissioning Schedule ✓ ✓ ✓ R ✓
Submittal Reviews ✓ ✓ ✓ ✓ R
O&M Manual Reviews ✓ ✓ ✓ R
O&M Training Agenda Reviews ✓ ✓ ✓ R
Systems Training Planning ✓ ✓ ✓ ✓ R
Occupant Training Planning ✓ ✓ ✓ R
Final Prefunctional Checklists &
Trend Log Specifications ✓ ✓ ✓ R
Final Functional Performance
Tests ✓ ✓ ✓ R
Acceptance Phase
Commissioning Coordination Meetings
✓ ✓ ✓ ✓ R
Test, Adjust, and Balance (TAB)
Report Review ✓ ✓ ✓ ✓ R
Systems Training Delivery ✓ ✓ ✓ ✓ R
O&M Training Delivery ✓ ✓ R ✓
Prefunctional Checklist
Completion ✓ R ✓
Functional Performance Test Plans ✓ ✓ ✓ R
Functional Performance Testing ✓ ✓ ✓ R
Trend Log Review ✓ ✓ ✓ R
Commissioning Action List ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ ✓ R
American University Revision 1.1
Master Commissioning Plan Page 8 March 5, 2012
PROJECT PHASES COMMISSIONING TEAM MEMBERS
Pla
nn
ing
Des
ign
Co
nst
ruct
ion
Acc
epta
nce
War
ran
ty
AU
Pro
ject
Man
ager
AU
Co
nst
ruct
ion M
gr
AU
Fac
ilit
ies
Cx
Au
thori
ty
Oth
er A
U D
epar
tmen
ts
Des
ign
Tea
m
Co
nst
ruct
ion T
eam
Cx
Man
ager
Functional Performance
Re-Testing ✓ ✓ ✓ R
Warranty Information Hand-off ✓ R ✓ ✓ ✓
Occupant Training Delivery ✓ ✓ ✓ ✓ R
Deferred Testing ✓ ✓ ✓ R
As Built Documentation Review ✓ ✓ ✓ ✓ ✓ R
Commissioning Report ✓ ✓ R
Systems Manual & On-Going Cx
Plan ✓ ✓ ✓ ✓ R
Warranty Phase Check-up &
Meeting ✓ ✓ ✓ ✓ ✓ ✓ ✓ R
On-Going Commissioning
Activities R
American University Revision 1.1
Master Commissioning Plan Page 9 March 5, 2012
5 Commissioning Process Flowchart
Planning Phase
Preliminary Commissioning
Plan
Owner’s Project Requirements (OPR)
Document
Design Phase
Basis of Design (BOD) Document
Commissioning Design Reviews
O&M Documentation
Planning
O&M Training Planning
Systems Training Planning
Preliminary Prefunctional Checklists & Functional
Performance Tests
Commissioning Specification
WarrantyPlanning
Construction Phase
Commissioning Schedule
Submittal Reviews
O&M Manual Reviews
O&M Training Delivery
Occupant Training Delivery
Prefunctional Checklists
Completion
Final Prefunctional Checklists & Trend Log Specifications
Functional Performance
Testing
Commissioning Report
Systems Manual & On-Going
Commissioning Plan
Deferred Testing
Warranty Phase Check-up & Meeting
Warranty Information
Hand-off
As-BuiltDocumentation
Review
Final Commissioning Plan
Acceptance Phase
Test, Adjust, and Balance (TAB) Report Review
Warranty Phase
Go to Design Phase
Go to Construction Phase
Go to Acceptance Phase
Go to Warranty Phase
On-Going Cx Phase
O&M Training Agenda Reviews
Occupant Training Planning
Systems Training Delivery
Final Functional Performance Tests
Functional Performance
Test Plans
Commissioning Action List
Functional Performance
Re-Testing
Design Phase Commissioning Coordination
Meetings
Construction Phase Commissioning Coordination
Meetings
Acceptance Phase Commissioning Coordination
Meetings
Trend Log Review
On-Going Cx Phase
On-Going Commissioning
Activities
On-Going Operations
American University Revision 1.1
Master Commissioning Plan Page 10 March 5, 2012
6 Commissioning Activities Narratives
Preliminary Commissioning Plan
The Preliminary Commissioning Plan will focus on identifying project-specific commissioning
activities, commissioning team members, and roles and responsibilities for all team members as
part of the commissioning process. The Preliminary Commissioning Plan will be prepared by the
Facilities Management Commissioning Authority and will be incorporated into requests for
proposal for Design Team and Commissioning Manager services.
Example prefunctional checklists (PFCs) and functional performance test procedures (FPTs) will
be included in the Preliminary Commissioning Plan as appendices to demonstrate level of rigor
required of future commissioning team members.
Owner’s Project Requirements (OPR) Document
The Owner’s Project Requirements (OPR) will quantitatively define the performance and
operational requirements for the commissioned systems. These performance requirements will be
the acceptance criteria against which the systems will be judged. They will include parameters
such as temperatures, flows, pressures, moisture content, light fixture types, light levels,
warranty information requirements, central system availability/tie-in capability, electrical spare
capacity requirements, building automation system requirements, etc.
For LEED certification purposes, the OPR must include the following sections:
Owner and User Requirements
Environmental and Sustainability Goals
Energy Efficiency Goals
Indoor Environmental Quality Requirements
Equipment and System Expectations
Building Occupant and Operations and Maintenance Requirements
The Facilities Management Commissioning Authority will oversee the development of the OPR,
but critical input will be needed from the Project Manager, Occupant/User Groups, and the
Design Team.
The Commissioning Manager will maintain the OPR throughout the duration of the project,
editing as necessary to reflect American University performance expectation changes.
American University Revision 1.1
Master Commissioning Plan Page 11 March 5, 2012
Design Phase Commissioning Coordination Meetings
The Commissioning Manager will plan, facilitate and document Design Phase Commissioning
Coordination Meetings. The coordination meetings are intended to help every team member
understand and execute their roles and responsibilities within the commissioning process, to
coordinate the details of current and upcoming commissioning activities, and to review
outstanding action items.
The first meeting will be a Design Phase Commissioning Kickoff Meeting to review the specifics
of the Commissioning process, identify representatives to the Commissioning Team, and
establish communication and documentation protocols for implementing the Commissioning
process as effectively and efficiently as possible. This meeting provides an overview so that the
team understands the big picture and the benefits they will accrue by participating in the process.
Subsequent Commissioning Coordination Meetings will be held as frequently as deemed
necessary by the Commissioning Manager to remain integrated into the Design Phase process
and to coordinate Commissioning deliverables into the bid documents.
Basis of Design (BOD) Document
The Basis of Design (BOD) documents the Design Team’s approach to achieving the
requirements of the OPR. It describes the types of equipment to be used, system configurations,
systems interactions, and general operating strategies. It also documents any general rules,
philosophies, and assumptions made by the Design Team. This document will be created and
managed by the Design Team and reviewed by the Facilities Management Commissioning
Authority and the Commissioning Manager.
Throughout the life of the project, the Commissioning Manager will monitor the design
evolution and bring any deviations from the BOD to the attention to the Design Team. If changes
to the system design and operational strategies are made during the project, a final BOD will be
prepared by the Design Team at the end of construction.
Operations & Maintenance (O&M) Documentation Planning
In the Construction Phase, the Contractor will facilitate and manage the delivery of accurate,
meaningful, and timely operation and maintenance (O&M) documentation to the Facilities
Management Commissioning Authority. Planning for this will take place in the Design Phase in
order to incorporate project-customized requirements into the contract documents.
The Commissioning Manager will participate in the discussion and definition of requirements for
O&M documentation (e.g., hardcopy & electronic copy requirements, equipment O&M criteria,
planned maintenance schedules, systems manual and on-going commissioning criteria, etc.) with
the Facilities Management Commissioning Authority. The Commissioning Manager will
American University Revision 1.1
Master Commissioning Plan Page 12 March 5, 2012
coordinate with the Design Team to confirm that project specifications reflect American
University’s O&M documentation requirements.
Operations & Maintenance (O&M) Training Planning
To achieve successful operations & Maintenance (O&M) training delivery, the Facilities
Management Commissioning Authority needs to start with a well-thought-out, un-hurried
process for planning the training process. The Commissioning Manager will involve the
Facilities Management Commissioning Authority as much as possible to define what training the
Facilities Management staff needs and wants in order to understand the systems and equipment
that they will have to operate. This will involve customizing training to match the level of
experience and detail that AU Facilities Management will require for each system.
The Commissioning Manager will participate in the discussion and definition of requirements for
O&M training (e.g., differentiating between systems and equipment training; addressing levels of
training; O&M shift coordination; video recording expectations; training agenda and
documentation requirements, etc.) with the Facilities Management Commissioning Authority.
The outcome of the training planning process will be an O&M Training Plan matrix to be
included in the bid documents. The Commissioning Manager will coordinate with the Design
Team to confirm that project specifications reflect American University’s O&M training
requirements. Refer to Section 7 for a Training Plan example.
Warranty Planning
The warranty information requirements will be defined in the contract documents and will define
how the warranty information is transitioned from the Contractor to the Facilities Management
Commissioning Authority at the end of construction. The Facilities Management Commissioning
Authority and the Commissioning Manager will work with the Project Manager to define the
warranty information format which will include, at a minimum, master equipment lists; warranty
start and end dates; manufacturer contact information; extended warranty (if any) details;
planned maintenance activities required to keep equipment under warranty; etc.
The Commissioning Manager will coordinate with the Design Team to confirm that project
specifications reflect American University’s warranty requirements.
Commissioning Design Reviews
The Facilities Management Commissioning Authority, the AU Construction Manager, AU Other
Departments, and the Commissioning Manager will review the design documents at
predetermined design phase milestones (e.g., DD, 50% CD, 100% CD/Permit documents). For
LEED certification purposes, at least one commissioning design review at the 50% CD phase is
required, along with a backcheck to confirm incorporation of commissioning review comments
into the final construction documents.
American University Revision 1.1
Master Commissioning Plan Page 13 March 5, 2012
The Commissioning Manager will review the design drawings and specifications for the
following commissioning-related items:
Compliance with the Owner’s Project Requirements.
Clarity of the design.
Clear integration requirements between equipment and systems
Equipment accessibility and maintainability.
Ability to test and validate system operation.
O&M Documentation, Training, and Warranty details
Comments will be categorized as follows:
Critical: Issues which in the Commissioning Manager’s professional opinion are
related to a system’s ability to achieve the Owner’s Project Requirements performance
criteria.
Question: Requests for clarification of intent.
Suggestion: Design features which can meet the Owner’s Project Requirements but for
which the Commissioning Manager has a recommendation for improved efficiency,
increased reliability, and/or lower life cycle cost.
Coordination: Although a commissioning review is not a coordination review, the
Commissioning Manager will note coordination items noticed during the course of the
commissioning review.
Along with the Commissioning Manager’s comments, the Commissioning Manager will collect
and consolidate comments from the Facilities Management Commissioning Authority and AU
Other Departments.
The Design Team will respond in writing to each of the comments provided. Refer to Section 7
for the Document Review Template.
Preliminary Prefunctional Checklists & Functional Performance Tests
The Commissioning Manager will prepare preliminary prefunctional checklists and functional
performance test procedures for the systems to be commissioned based on the design documents.
There shall be one prefunctional checklist and one functional performance test procedure for
each commissioned system.
These preliminary documents should be included in the Final Commissioning Plan and
incorporated into the bid documents to demonstrate anticipated level of rigor to the Contractor. If
project-specific prefunctional checklists and functional performance test procedures cannot be
developed, sample documents for similar system types will suffice.
Refer to Section 7 for examples of both Prefunctional Checklists and Functional Performance
Test Procedures. These examples are intended to communicate format and level of rigor. The
actual project checklists and test procedures will be customized to match the final design
requirements for each system.
American University Revision 1.1
Master Commissioning Plan Page 14 March 5, 2012
Final Commissioning Plan
The Commissioning Manager will prepare the Final Commissioning Plan, building on and
editing the Preliminary Commissioning Plan to reflect the project at the end of the Design Phase.
The systems to be commissioned section will be refined to represent the quantity and types of
systems in the final construction documents. Sampling strategies pertaining to the functional
performance testing will be detailed in the Final Commissioning Plan. The Final Commissioning
Plan will be incorporated into the bid documents by reference.
Commissioning Specification
The Commissioning Manager will prepare a Commissioning Specification to be included in the
construction documents. The Commissioning Specification will detail the Contractor’s
responsibilities (as outlined in the Final Commissioning Plan) during the Construction,
Acceptance, and Warranty Phases of the project. The Design Team will incorporate the
Commissioning Specification into the Division 1 specification section.
The Commissioning Specification will include, but not be limited to commissioning-related
scheduling; submittal management; prefunctional checklists; functional performance testing;
O&M and systems manuals; O&M and systems training; as-built drawings; and warranty
management. Furthermore, the Commissioning Specification will include language defining
incentive program(s), if applicable, established to encourage Contractor readiness for functional
performance testing.
The Commissioning Manager will recommend coordination language to be included in other
Design Team specification sections that will direct the Contractors’ attention to the Division 1
Commissioning Specification for required commissioning activities. The Design Team will
incorporate, as they deem appropriate, the coordination language into their respective
specification sections.
American University Revision 1.1
Master Commissioning Plan Page 15 March 5, 2012
Construction Phase Commissioning Coordination Meetings
The Commissioning Manager will plan, facilitate and document Construction Phase
Commissioning Coordination Meetings. The coordination meetings are intended to help every
team member understand and execute their roles and responsibilities within the commissioning
process, to coordinate the details of current and upcoming commissioning activities, and to
review outstanding action items.
The first meeting will be a Construction Phase Commissioning Kickoff Meeting to review the
specifics of the Commissioning process, identify new representatives to the Commissioning
Team, and establish communication and documentation protocols for implementing the
Commissioning process as efficiently and effectively as possible. This meeting provides an
overview so that the team understands the big picture and the benefits they will accrue by
participating in the process.
Subsequent Commissioning Coordination Meetings will be held as frequently as deemed
necessary by the Commissioning Manager to remain integrated into the Construction Phase
process. Frequency will vary throughout the construction as the Commissioning process
requirements vary depending on what is happening on the construction site.
Commissioning Scheduling
There will not be a separate commissioning schedule. The Contractor will be required to
incorporate commissioning activities into the master construction schedule. The Commissioning
Manager will assist the Contractor, as needed, to understand the relationship between
construction and commissioning activities. The Facilities Management Commissioning
Authority will regularly review the master construction schedule in order to coordinate the
availability of Facilities Management staff for critical commissioning activities.
Master construction schedule commissioning milestones will include, but not be limited to,
O&M manual submissions; training agenda submissions; training delivery; prefunctional
checklist completion; functional performance testing; system manual and on-going
commissioning plan submissions; as-built drawing submissions; and the warranty information
hand-off. Some of the activities may require multiple milestones due to some systems following
a different construction schedule than others.
Submittal Reviews
The Commissioning Manager will identify submittals associated with systems to be
commissioned that need to be reviewed by the Commissioning Manager and Facilities
Management staff. The Facilities Management Commissioning Authority, AU Other
Departments, and the Commissioning Manager will review the submittals concurrent with the
Design Team.
American University Revision 1.1
Master Commissioning Plan Page 16 March 5, 2012
The Contractor will send copies of the selected submittals to the Facilities Management
Commissioning Authority and to the Commissioning Manager simultaneous with issuing them to
the Design Team for review. The Facilities Management and AU Other Departments reviewers
will submit their comments to the Commissioning Manager who will consolidate all comments
and forward them to the Design Team. The Design team will incorporate the commissioning
comments, at their discretion, into their formal submittal review responses to the Contractor. The
Design Team will provide written responses to each submittal review comment to the
Commissioning Manager.
Commissioning submittal review comments will focus on the same areas as the commissioning
design reviews (e.g. compliance with the OPR, clarity of the design, integration coordination,
accessibility and maintainability, O&M training and documentation requirements, and the ability
to test and validate system operation). Refer to Section 7 for the Document Review Template.
The Commissioning Manager and Facilities Management Commissioning Authority will be
given access to all approved submittals after processing by the Design Team.
Operations & Maintenance (O&M) Manual Reviews
Early submission of the O&M manuals will help ensure they are complete and approved prior to
the start of the AU Facilities Management staff training. The manuals will serve a critical part of
the training program.
The Commissioning Manager will identify O&M manuals associated with systems to be
commissioned that need to be reviewed by the Commissioning Manager and Facilities
Management staff. The Facilities Management reviewers will submit their comments to the
Commissioning Manager who will consolidate all comments and forward them to the
Contractors.
O&M Training Agenda Reviews
Each training session - represented by a row in the Training Plan (refer to Section 7 for a
Training Plan example) - will have a Training Agenda. The Training Agenda requires specific
detailed information about the content of its respective session. The agenda will be completed by
the Contractor responsible for the training session and will be reviewed by the Facilities
Management Commissioning Authority and the Commissioning Manager. The Facilities
Management reviewers will submit their comments to the Commissioning Manager who will
consolidate all comments and forward them to the Contractors.
During delivery of the O&M training sessions, each approved Training Agenda form will be
used to document attendees of the training session and to formalize American University’s
acceptance of the training.
American University Revision 1.1
Master Commissioning Plan Page 17 March 5, 2012
System Training Planning
Whereas the O&M Training sessions will pertain to individual pieces of equipment, the Systems
Training sessions will focus on how those components are uniquely put together as systems for
the project. The Commissioning Manager will facilitate the development of a Systems Training
program. The purpose of this training will be to present all of the commissioned systems; their
design intent; schematic diagrams; sequences of operation; integration with other systems; and
areas of the building served by the systems.
Although facilitated by the Commissioning Manager, Systems Training will be a collaborative
effort between the Design Team, the Contractors, and the Commissioning Manager; each
delivering their area of expertise for each system.
Systems training planning will require defining the type and level of training required for the
systems; number of sessions; video recording expectations; training agenda; and
presentation/documentation materials. The Commissioning Manager will compile Systems
Training presentation materials from documents submitted by the Design Team and the
Construction Team.
Occupant Training Planning
With an understanding that some building systems require certain behaviors from building
occupants and system users in order to perform as intended, the Commissioning Manager will
facilitate the development of an Occupant Training program. The Occupant Training program
will introduce, in appropriately technical terms for the occupants, the systems impacting the
occupied spaces. The training will also present the various ways in which the occupants may be
able to influence system performance (i.e., opening doors and windows, adjusting thermostats,
introducing space heaters, moving furniture, overriding occupancy sensors, etc.) and establish
ground rules for building occupant behavior.
Training planning will require defining the type and level of training required for the project;
future occupant coordination; video recording expectations; training agenda; and
presentation/documentation materials.
Final Prefunctional Checklists & Trend Log Specifications
The Commissioning Manager will finalize Prefunctional Checklists (PFCs) customized for each
system to be commissioned after reviewing approved submittals, requests for information,
change orders, supplemental instructions, and other construction phase modifications and/or
additions. The Commissioning Manager will issue final PFCs to the Facilities Management
Commissioning Authority for review and comment. Upon incorporation of accepted Facilities
Management Commissioning Authority comments, the Commissioning Manager will issue final
PFCs for completion and sign-off by the Contractor during final system checkout.
The PFCs shall be used to document that key system-level installation, startup, programming,
coordination, integration, and testing activities have been completed. These are not contractor
American University Revision 1.1
Master Commissioning Plan Page 18 March 5, 2012
quality control checklists for each piece of equipment but system-level confirmation of readiness
for the system’s Functional Performance Test. The General Contractor will be responsible for
overseeing the completion of the checklists by the Subcontractors, because each system typically
requires the participation of multiple Subcontractors to be complete and ready for testing.
Examples of Prefunctional Checklist items include, but are not limited to, pipe pressure testing;
duct air leakage testing; electrical wiring; major equipment startup; variable frequency drive
setup; controls point-to-point checkout; controls programming; test, adjust, and balance
completion and issues resolution; successful completion of the contractor-only dry run of the
Functional Performance Test, etc.
PFCs for systems controlled and /or monitored by central campus energy management system
(EMS) include a requirement that building automation system graphics screen is complete,
points have been properly mapped to the central EMS, and AU Facilities Management personnel
have access to view system status and operation.
PFCs for systems controlled and/or monitored by the building automation system also include
requirements for building automation system trend logs to be programmed prior to the start of
Functional Performance Testing. These requirements will include the points to be trended, the
frequency of the trends, and the points to be included together on color graphic trend logs when
submitted for review.
Final Functional Performance Tests
The Commissioning Manager will finalize Functional Performance Test Procedures (FPTs) for
each system to be commissioned after reviewing approved submittals, requests for information,
change orders, supplemental instructions, and other construction phase modifications and/or
additions. The following are the minimum requirements for American University FPTs:
Step-by-Step Script
FPTs should dictate a chronological list of steps to be followed. The steps should be
scripted in an efficient manner, minimizing the level of redundancy between steps as
much as practical. The intent of testing is to demonstrate performance of each mode of
system operation as effectively and efficiently as possible.
Repeatable
Although the Commissioning Manager will develop and oversee the execution of FPTs
when they are implemented at the end of construction, the test procedures are required to
be designed to be referenced by future Facilities Management staff for recommissioning
purposes. As such, the test procedures should be designed to stand alone and be
understood by reasonably knowledgeable building operations personnel without the
Commissioning Manager’s involvement.
American University Revision 1.1
Master Commissioning Plan Page 19 March 5, 2012
The action required for each step should not be open to interpretation in the field. For
example, a step that reads, “Put the system into economizer mode,” does not explain how
that should be done. The Commissioning Manager should define whether that should be
accomplished by overriding outdoor air inputs, overriding return air inputs, changing
setpoints, overriding the economizer mode software point, or some other method
appropriate for the system and sequence being tested. Given the differences between
building automation systems and their programming, a systems’ reaction is likely to vary
depending on how the action is performed. To the greatest extent practical, this needs to
be understood by the Commissioning Manager prior to the start of field testing.
Unambiguous Pass/Fail Acceptance Criteria
For each step of the test procedure, there should be a pass/fail definition of acceptable
response. This typically is a description of how each device in a system is designed to
react to the scripted action imposed on the system.
In the interest of field testing efficiency, the acceptance criteria should be clearly defined
in terms that everyone in the field can understand and agree on. Valves and dampers
should “open” or “close;” fans and pumps shall “start” or “stop;” modulating devices
shall “modulate higher” or “modulate lower.” Simply stating that the system should
respond “as specified,” is not acceptable in an FPT procedure.
Customized
Each test procedure must reflect the final design and approved shop drawings for the
unique systems in each project. There should be nothing “not applicable” in a project’s
FPT, i.e., if a step or reaction is not applicable, it should be removed from the procedure.
Sampling Strategies
The Contractor can employ a sampling strategy to functionally test a fraction of the total
number of non-life safety or non-critical equipment that are identical or near identical
pieces of equipment (e.g., terminal units, occupancy sensors, exhaust fans, etc.). The
sampling strategy must be well-defined and approved by AU Facilities during the Design
Phase and documented in the Final Commissioning Plan and the Commissioning
Specification. The sampling strategy must define the applicable project-specific
equipment, the percent of randomly selected equipment to be tested, the failure rate
threshold, and recourse plan if excessive failures are discovered.
The Mechanical, Electrical, TAB, and Controls Contractors will review and comment on the
efficiency and safety of the proposed test steps, and the Facilities Management Commissioning
Authority will review for completeness and rigor. The Commissioning Manager will incorporate
Facilities Management Commissioning Authority’s and the Contractors’ recommendations as
appropriate. It is the review activity that helps prevent surprises in the field on test day. Upon
incorporation of the accepted Facilities Management Commissioning Authority and Contractor
American University Revision 1.1
Master Commissioning Plan Page 20 March 5, 2012
comments, the Commissioning Manager will issue final FPTs for use in the system functional
performance testing process.
Refer to Section 7 for examples of both Prefunctional Checklists and Functional Performance
Test Procedures. These examples are intended to communicate format and level of rigor. The
actual project checklists and test procedures will be customized to match the final design
requirements for each system.
American University Revision 1.1
Master Commissioning Plan Page 21 March 5, 2012
Acceptance Phase Commissioning Coordination Meetings
The Commissioning Manager will plan, facilitate and document Acceptance Phase
Commissioning Coordination Meetings. These meetings will be heavily focused on system
readiness for Functional Performance Testing and scheduling of that testing. Acceptance Phase
Commissioning Coordination Meetings will be held as frequently as deemed necessary by the
Commissioning Manager to keep the Commissioning process on track for completion prior to
Substantial Completion.
Test, Adjust, and Balance (TAB) Report Review
The TAB Contractor will prepare a balancing report documenting that all air and hydronic
systems have been adjusted and are within acceptable design values. The Facilities Management
Commissioning Authority and the Commissioning Manager will review the report submitted by
the TAB Contractor, concurrent with the Design Team as the TAB Contractor completes work
on individual systems (i.e., not all systems need to be balanced before the reporting process
begins). The Commissioning Manager will verify that all required data has been collected, that
the measured results are in compliance with the design documents, and that any non-compliance
items have been resolved and rebalanced prior to the start of Functional Performance Testing.
The Facilities Management reviewers will submit their comments to the Commissioning
Manager who will consolidate all comments and forward them to the Design Team. The Design
team will address these comments, incorporating them as appropriate into their formal TAB
report review response to the Contractor. The Design Team will provide written responses to
each TAB report review comment to the Commissioning Manager.
Refer to Section 7 for an example of the Document Review Template.
Systems Training Delivery
The Commissioning Manager will facilitate the scheduling of Systems Training with the
Facilities Management Commissioning Authority, the Design Team, and the Construction Team.
The training events will be coordinated for the convenience of the trainees, i.e., between shifts,
manageable amounts of training at a time to accommodate trainees’ other responsibilities, etc.
The Commissioning Manager will lead the Systems Training sessions with most agenda items
presented by members of the Design Team and Construction Team.
The Facilities Management Commissioning Authority will schedule and coordinate the video
recording of the Systems Training sessions with American University resources.
American University Revision 1.1
Master Commissioning Plan Page 22 March 5, 2012
O&M Training Delivery
After the Training Agendas have been reviewed and accepted by the Facilities Management
Commissioning Authority, the Commissioning Manager will convene a meeting with the
Contractors and the Facilities Management Commissioning Authority to schedule the individual
O&M Training sessions. The training events will be coordinated for the convenience of the
trainees, i.e., between shifts, small amounts of training at a time to accommodate trainees’ other
responsibilities, etc. Training will be concurrent with equipment start-up by the Contractor.
The Contractor will formally document each training session and the acceptance of the training.
Documentation of Facilities Management acceptance will require that someone representing the
trainees formally and in writing accept each training session as complying with that session’s
Training Agenda. The Commissioning Manager will collect this documentation in the form of
fully executed Training Agendas and include them as part of the Final Commissioning Report.
The Facilities Management Commissioning Authority will schedule and coordinate the video
recording of the O&M Training sessions with American University resources.
Prefunctional Checklists Completion
The prefunctional checklists are used to document that the systems are fully installed, connected,
started-up, programmed, integrated and have successfully passed their respective Functional
Performance Tests in a contractor-only dry run. Fully executed Prefunctional Checklists are the
Contractor’s validation that the systems are ready for successful Functional Performance Testing
witnessed by Facilities Management and the Commissioning Manager. The Prefunctional
Checklists will be documented in writing by personnel representing the responsible Contractors;
multiple Subcontractors will need to sign-off on each system’s checklist.
These checklists are primarily inspections and procedures to prepare the equipment or system for
initial operation (e.g., oil levels, fan belt tension, labels affixed, gauges in place, sensor
calibration, etc.). However, some checklist items entail simple testing of a component, a piece of
equipment or system (such as measuring the voltage imbalance on a three phase pump motor of a
chiller system). Each piece of equipment is to receive full checkout by the Contractors. No
sampling strategies will be permitted.
All building automation system trend logs required for a system must be programmed and
collecting data before the PFCs are completed and submitted by the Contractors.
Functional Performance Test Plans
The Commissioning Manager will prepare and distribute Functional Performance Test Plans
prior to the start of Functional Performance Testing. This will allow the Construction Team to
review the proposed testing schedule; to understand which test procedures will be conducted
during a specific testing period; to schedule the appropriate people to be in attendance for each
test; and to verify that the necessary equipment is available when testing begins.
American University Revision 1.1
Master Commissioning Plan Page 23 March 5, 2012
The Facilities Management Commissioning Authority will schedule Facilities Management staff
to participate in and witness Functional Performance Testing based on the schedule outlined in
each Test Plan.
Functional Performance Testing
Functional Performance Testing is the technical culmination of the Commissioning process for
systems acceptance by the Facilities Management Commissioning Authority and should be
performed prior to Substantial Completion.
The Commissioning Manager will field-direct, witness, and document the Functional
Performance Test Procedure (FPT) for each system to be commissioned. Although the
Commissioning Manager directs the tests, the Contractors will manipulate the systems and
controls in accordance with the FPTs reviewed and accepted by all team members before the
start of testing. The Facilities Management representatives will witness and participate in the
Functional Performance Testing, as determined by Facilities Management, to understand how the
systems operate and how optimal performance can be maintained.
Trend Log Review
The Contractor will download and submit electronic trend data to the Commissioning Manager
for review at a time scheduled by the Facilities Management Commissioning Authority and the
Commissioning Manager. This may be prior to the start of Functional Performance Testing,
immediately following Functional Performance Testing, or after occupancy.
The trend data will be submitted in editable spreadsheet format and in color graphs designed as
specified in the Prefunctional Checklist for each affected system.
Any trend logs demonstrating performance not meeting the construction document requirements
will be re-run, following remediation of the problems, and re-submitted to the Commissioning
Manager for review.
Commissioning Action List
The Commissioning Manager will maintain a Commissioning Action List - starting in the Design
Phase and continuing through the Warranty Phase - to track the status of all Commissioning-
related items. The Commissioning Action List includes process-related and technical-related
issues associated with successful completion of the Commissioning process.
For each deficiency found during Functional Performance Testing, the Commissioning Manager
will add the item to the Commissioning Action List. The Commissioning Action List is the
vehicle for communicating, tracking, and documenting the status and correction of each
deficiency.
The Commissioning Manager shares the Commissioning Action List with the Contractors who
inform the Commissioning Manager in writing upon correction of each problem with an
American University Revision 1.1
Master Commissioning Plan Page 24 March 5, 2012
explanation of what was done to resolve the issue. If the Functional Performance Test
demonstrates a system performs as designed but does not meet the OPR criteria for that system,
the associated Commissioning Action List item will be assigned to the Design Team to engage
them in the issue resolution process.
Upon notification of the completion of a Commissioning Action Item, the Commissioning
Manager will schedule re-testing for the affected system to verify satisfactory resolution of the
deficiency.
Refer to Section 7 for the Commissioning Action List template.
Functional Performance Re-Testing
The Commissioning Manager will field-direct, witness, and document Functional Performance
Re-Testing for each system that failed to pass its initial FPT. For systems tested with a sampling
strategy, as defined in the Final Functional Performance Test Procedures, additional samples will
need to be tested during re-testing if the failures of the initial sample exceed the failure rate
threshold.
The extent and level of rigor of retesting will be as the Commissioning Manager deems
necessary to confirm successful resolution of the initial deficiencies without sacrificing
performance elements which had originally passed the system FPT.
Although the Commissioning Manager directs the re-tests, the Contractors will manipulate the
systems and controls. Facilities Management representatives will witness and participate in the
Functional Performance Re-Testing as determined by Facilities Management.
American University Revision 1.1
Master Commissioning Plan Page 25 March 5, 2012
Warranty Information Hand-off
The Contractor and the AU Construction Manager will provide warranty information to the
Facilities Management Commissioning Authority for the commissioned systems. The warranty
information will be transferred prior to Substantial Completion and will include, but not be
limited to, master equipment list; warranty start and end dates; manufacturer contact information;
extended warranty (if any) details; planned maintenance activities required to keep equipment
under warranty; etc. The Facilities Management Commissioning Authority will review and
approve the warranty information submitted at the end of construction for compliance with the
specifications.
Occupant Training Delivery
The Commissioning Manager will facilitate the scheduling and delivery of Occupant Training
with the Facilities Management Commissioning Authority and representatives of the building
occupants. The training events will be coordinated for the convenience of the trainees, i.e.,
between shifts, manageable amounts of training at a time to accommodate trainees’ other
responsibilities, etc.
The Commissioning Manager will lead the Occupant Training sessions with participation by the
Facilities Management Commissioning Authority.
The Facilities Management Commissioning Authority will schedule and coordinate the video
recording of the Occupant Training sessions with American University resources.
Deferred Testing
Functional Performance Tests (FPTs) may need to be deferred until after Substantial Completion
for a variety of reasons. The most common reasons include (1) HVAC systems may need to have
different weather conditions than those at the end of construction and (2) commissioned systems
may need to have a load put on them before testing can be considered meaningful. FPTs that
occur after Substantial Completion will be conducted, documented, and tracked in a manner
identical to the Acceptance Phase process.
As-Built Documentation Review
The AU Construction Manager will provide the Facilities Management Commissioning
Authority with as-built documentation including, but not limited to, (1) record installation
drawings and (2) the final building automation system controls manual. The as-built building
automation system controls manual will include the final “as commissioned” system schematics,
sequences of operations, setpoints, and alarm limits.
These documents will be reviewed by the Commissioning Manager and Facilities Management
staff. The Facilities Management reviewers will submit their comments to the Commissioning
American University Revision 1.1
Master Commissioning Plan Page 26 March 5, 2012
Manager who will consolidate all comments and forward them to the AU Construction Manager
for resolution by the Design and Construction Teams.
Commissioning Report
Following resolution and/or acceptance of all Commissioning Action Items, the Commissioning
Manager will prepare the Commissioning Report. The report will be a compilation of
documentation (both technical and process-related) associated with the Commissioning process.
It will be prefaced with an Executive Summary documenting the final system status compared to
the Owner’s Project Requirements document.
The Commissioning Report will include at least the following sections:
1. Introduction
2. Executive Summary
3. Owner’s Project Requirements
4. Basis of Design
5. Commissioning Plan
6. Commissioning Specification Section
7. Commissioning Action List
8. Commissioning Coordination Meeting Minutes
9. Warranty Phase Check-up Meeting Minutes
10. Design Review Comments
11. Submittal Review Comments
12. TAB Report Review Comments
13. As-Built Documentation Review Comments
14. O&M Manual Review Comments
15. O&M Training Plan
16. O&M Training Agendas (fully executed)
17. Systems Training Agendas
18. Occupant Training Agendas
19. Prefunctional Checklists (fully executed)
20. Functional Performance Test Plans
21. Blank Functional Performance Test Procedures
The Commissioning Manager will submit the Commissioning Report to the Facilities
Management Commissioning Authority for review.
The Commissioning Manager will amend the Commissioning Report at the end of the Warranty
Phase to document pertinent Warranty Phase activities, findings, decisions, etc.
American University Revision 1.1
Master Commissioning Plan Page 27 March 5, 2012
Systems Manual & On-Going Commissioning Plan
The Commissioning Manager will collect and compile the Systems Manual & On-Going
Commissioning Plan, based on American University standards for this document. At a minimum,
these document shall include the following for the commissioned systems:
1. Owner’s Project Requirements
2. Basis of Design
3. Integrated Building Systems Operating Instructions
4. System Schematic Diagrams
5. As-Built Control Sequences of Operation and Initial Setpoints
6. Planned Maintenance Activities and Recommended Frequencies
7. Recommended Control System Sensor & Actuator Calibration Frequencies
8. Recommended Building Automation System Trend Logs for On-Going Commissioning
Monitoring and Evaluation
9. Recommended System Re-Testing Frequencies
10. Blank Functional Performance Test Procedures for Re-Testing
In the Design Phase the Commissioning Manager will prepare an outline of the Systems Manual
& On-Going Commissioning Plan along with assigned roles and responsibilities for project team
members to produce the various elements of the document. These requirements will be
incorporated into the Commissioning Specification and included in the bid documents.
During the Construction Phase, the Commissioning Manager, Design Team, and Construction
Team will prepare a preliminary schedule of when each element will be submitted to the
Commissioning Manager over the course of the project.
The Commissioning Manager will submit the Systems Manual & On-Going Commissioning
Plan to the Facilities Management Commissioning Authority for review.
Warranty Phase Check-up & Meeting
No later than 2 month before the end of the Warranty Phase, a warranty meeting will be planned,
facilitated, and documented by the Commissioning Manager. This meeting is an opportunity for
Facilities Management and other AU Department representatives to provide feedback on the
effectiveness and efficiency of the new equipment and systems. The Design Team and
Construction Team are required to participate in the warranty meeting.
The Facilities Management Commissioning Authority will oversee the collection of operations
issues, concerns, challenges, etc., throughout the Warranty Phase in order for the warranty
meeting to be as comprehensive and meaningful as practical.
Information received by the Design Team and Construction Team will be used to track and
correct warranty-related issues; to contribute to future Owner's Project Requirements documents;
and to refine American University’s project delivery process.
American University Revision 1.1
Master Commissioning Plan Page 28 March 5, 2012
On-Going Commissioning Activities
AU Facilities addresses changes in occupancy, use, maintenance and repair and makes periodic
adjustments and reviews of building operating systems and procedures essential for optimal
energy efficiency and service provision.
American University Revision 1.1
Master Commissioning Plan Page 29 March 5, 2012
7 Commissioning Documentation
A. Commissioning Action List Template
B. Document Review Template
C. Training Plan Example
D. Training Agenda Example
E. Example Prefunctional Checklists
F. Example Functional Performance Test Procedures
AMERICAN UNIVERSITY
COMMISSIONING ACTION LIST
TEMPLATE
ACTION
ITEM #
DATE
LOGGED ENTRY TYPE
TECHNICAL
CATEGORY
COMMENT
GENERATOR
RESPONSIBLE
TEAM
MEMBER(S) ITEM DESCRIPTION STATUS
EXPECTED
COMPLETION
DATE STATUS UPDATE CLOSE DATE
1 02/20/12 Meeting Minutes General MEM AU Submit requested documentation OPEN 2/22/2012
2 02/20/12Document
ReviewGeneral MEM Cx manager
Review RFIs for commissioning-
related issues.ON GOING
3 02/20/12 Verbal General MEM QSE Submit requested documentation CLOSED 2/22/2012 2/21/12: Documentation submitted 02/21/12
4 02/20/12 Site Observation General CEM QSE
Correct deficiencyREADY TO
VERIFY2/22/2012
02/21/12: This was the problem, this
is how it was fixed. Cx Manager to
verify.
5 02/20/12Verification
TestingMechanical RTE
Controls
Contractor
Correct system schematic in as-built
controls documentation.AS BUILTS 2/22/2012
6 02/20/12 Meeting Minutes Mechanical MSMControls
Contractor
Perform point-to-point checkout of
control system points mapped to the
campus front end computer after
communications have been
established.
DEFERRED 12/31/12
7
8
9
American University
Commissioning Action List Template Page 1 of 12/23/2012
AMERICAN UNIVERSITY
COMMISSIONING REVIEW COMMENTS
TEMPLATE
C = Critical
CO = Coordinate
S = Suggestion Initial
Comment Q = Question Comment Comment
Number E = Energy Date Generator Type Number Date System(s) Status Commissioning Review Comment Design Team Response Commissioning Manager Backcheck
MECHANICAL
M001 CO 3/7/2011 RTE Dwg M4.1 2/21/2012 HVAC CLOSED
The hot water supply pipe riser going up from
the 2nd floor is not shown entering the 3rd
floor.
Will be corrected in 100% CD
documents.Confirmed corrected.
M002 C 3/7/2011 RTE Spec 15823 2/21/2012 HVAC OPEN
If the boiler manufacturer's control panel is to
control the boilers and their on/off/modulating
control, this specification section should
include a sequence of operation for that
control. Also, the points to be shared between
the boiler control panel and the central
automation system need to be define.
ELECTRICAL
E001
LIFE SAFETY
L001
American University
Reference
Document Set (Name, Date)Project Name
American University
Review Comments Template Page 1 of 1 2/23/2012
Spec
Section
1Pre-Occ
Scope A
Hours
1Pre-Occ
Scope B
Hours
1Pre-Occ
Scope C
Hours
Post-Occ
Hours
Total
Hours
Video
Recorded
Primary
Responsible
Contractor Name Company E-mail Phone number Date Time Location
Agenda
Approved
Training
Session
Complete
Training
Session
Approved
MECHANICAL
Heat Pumps Heat
Pumps
4 4 8 Mech
Hydronic Pumps Hydronic
Pumps
2 2 Mech
Rooftop Units Rooftop
Units
4 4 8 Mech
Energy Recovery Units/Heat Recovery Units Energy
Recovery
4 4 8 Mech
VAV Terminal Units VAV
Terminal
2 2 Mech
Terminal Heaters (UH, BBH, IFR) Terminal
Heaters
1 1 Mech
Guard Shack Air Conditioning Unit ACU 2 2 Mech
Exhaust Fans Exhaust
Fans
1 1 Mech
Makeup Air Units Makeup
Air Units
4 4 8 Mech
HVLS Fans HVLS
Fans
1 1 Mech
Direct Steam Heater Direct
Steam
2 2 Mech
Domestic Hot Water Mixing Valves Domestic
Hot Water
1 1 Mech
VFDs VFDs 2 2 4 Mech/Elec
Plant Systems Controls Plant
Systems
8 4 12 Mech
Office Systems Controls Office
Systems
8 4 12 Mech
ELECTRICAL
Lighting Controls Lighting
Controls
8 4 12 Elec
1General Scope Codes (refer to the specific equipment Training Agenda for additional details)
A. Provide an overview of the purpose and operation of this equipment, including required interactions of trainees with the equipment. (Approximately 15 to 30 minutes)
B. At an intermediate level , provide technical information regarding the purpose, operation and maintenance of this equipment, expecting that serious malfunctions will be addressed by factory reps. (Approximately 1 to 2 hours)
C. At a very technical level , provide information regarding the purpose, operation, troubleshooting and maintenance of this equipment, expecting that almost all operation, service and repair will be provided by the trainees. (Hours vary by level of complexity.)
EXAMPLE:
O&M STAFF EQUIPMENT TRAINING PLAN
ScopeTrainer Information Scheduling Tracking
Description
EQUIPMENT
American University
Page 1 of 1
12-15-2008
Training Plan Example
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
VAV TERMINAL UNITS WITH REHEAT RADIATION
PREFUNCTIONAL CHECKLIST
VAV 0-067 VAV 1-025
1VAV box controller, reheat shutoff valves, strainer, reheat
control valve, and volume damper are easily accessible.DATE APPROVED DATE APPROVED
2VAV box, reheat coil, and radiation are replaceable without
removing other systems (ductwork, conduit, piping, etc.).DATE APPROVED DATE APPROVED
3VAV thermostat is not subjected to direct sunlight or other
temperature influencing sources.DATE APPROVED DATE APPROVED
4 Control damper responds to BMS commands. DATE APPROVED DATE APPROVED
5 Hot water reheat control valve responds to BMS commands. DATE APPROVED DATE APPROVED
6 Radiation control valve responds to BMS commands. DATE APPROVED DATE APPROVED
7
BMS graphics screen is complete and points have been
properly mapped to the central energy management system
(EMS)
DATE APPROVED DATE APPROVED
8System is able to fully execute all steps of the sequence of
operations and is able to maintain all system setpoints.DATE APPROVED DATE APPROVED
9Airflow sensor is calibrated and showing accurate values at
the BMS front-end computer.DATE APPROVED DATE APPROVED
10Thermostat temperature sensor is calibrated and showing
accurate values at the BMS front-end computer.DATE APPROVED DATE APPROVED
11Local thermostat temperature setpoint matches BMS
temperature setpoint.DATE APPROVED DATE APPROVED
12 Successful leak test results submitted (233600-3.3). DATE APPROVED DATE APPROVED
13 Successful operational test results submitted (233600-3.3). DATE APPROVED DATE APPROVED
14 Associated air handling unit PFC has been submitted. DATE APPROVED DATE APPROVED
15Air side testing, adjusting, and balancing information has
been submitted and deficiencies corrected.DATE APPROVED DATE APPROVED
16Water side testing, adjusting, and balancing information has
been submitted and deficiencies corrected.DATE APPROVED DATE APPROVED
SENSOR CALIBRATION
EQUIPMENT STARTUP AND QUALITY CONTROL TESTS
REPORTS & DOCUMENTATION
Contractor Notes
ACCEPTANCE CRITERIA
DEVICE LOCATIONS
POWER AND COMMUNICATION
American University Cx Plan
Prefunctional Checklist Page 1 of 1 E1 PFC Terminal Units EXAMPLE.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
LIGHTING CONTROLS
PREFUNCTIONAL CHECKLIST
Lighting Control
System
1Lighting Controller located and mounted in a location where
audible noise is acceptableDATE APPROVED
2Lighting Controller voltage wiring is at least six (6) feet from
sound and electronic equipment wiring.DATE APPROVED
3Clearance on left and right side of the relay cabinets is 1 1/2 " or
greaterDATE APPROVED
4Lighting Control cabinets are easily accessible for adjustment,
repair, and replacement.DATE APPROVED
5 Cabinets are cleaned of all dust, debris, metal particles. DATE APPROVED
6Relay cabinet anchored and supported per manufacturer's
recommendationsDATE APPROVED
7Boardroom Dimming system installation complete and
operationalDATE APPROVED
8Ultrasonic ceiling mounted occupancy sensors are located a
minimum of six (6) feet from HVAC supply/return ventsDATE APPROVED
9Sensors mounted over doorways are placed one (1) foot inside
threshold.DATE APPROVED
10All occupancy sensors are easily accessible for adjustment,
repair, and replacement.DATE APPROVED
11All daylight photosensors are easily accessible for adjustment,
repair, and replacement.DATE APPROVED
12Digital Pushbutton Stations are installed and operate designated
light fixtures according to the construction documents.DATE APPROVED
13Outdoor photocell is mounted facing northern sky and pointed
away from nighttime light sources.DATE APPROVED
14Component/subsystems are clearly and correctly identified with
temporary/permanent labelsDATE APPROVED
15Fluorescent ballasts are installed such that both lighting fixture
and ballast are grounded.DATE APPROVED
16Dedicated power circuit provided and used only for power
to the control electronics in the relay cabinetsDATE APPROVED
17Minimum 18AWG stranded wire installed for all low voltage
wiringDATE APPROVED
18 All field wiring is completed DATE APPROVED
ACCEPTANCE CRITERIA
Service Area
Contractor Notes
INSTALLATION
American University Cx Plan
Prefunctional Checklist Checklist Page 1 of 3 E2 PFC Lighting Controls.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
LIGHTING CONTROLS
PREFUNCTIONAL CHECKLIST
Lighting Control
System
ACCEPTANCE CRITERIA
Service Area
Contractor Notes
19All connections securely fastened in accordance with
recommended torque valuesDATE APPROVED
20 Verify labeling of field and interconnecting wiring is completed DATE APPROVED
21Verify circuit breakers feeding lighting circuits are rated for
intended purposeDATE APPROVED
22
For best lamp life, verify installed fluorescent lamps have a
logged 100 hours of operation prior to any dimming or testing of
dimming.
DATE APPROVED
23 Network installation(s) is per manufacturer's recommendations: DATE APPROVED
23.aManufacturer's recommended network wiring has been
installedDATE APPROVED
23.bNetwork cable not in close proximity to AC wiring and all
control/power wiring in conduitDATE APPROVED
23.c
Network cable is run separately from line voltage and does not
pass near any source of electrical noise such as fluorescent
circuits or motor wiring.
DATE APPROVED
23.d Network drain/shields are tied together at connectors. DATE APPROVED
23.e Network drain/shields are grounded at one point only DATE APPROVED
23.f
Last control station or dimmer cabinet on each end of network
run has been terminated with jumper per manufacturer's
requirements.
DATE APPROVED
23.gNo bare conductors showing at terminations on low voltage
input wiring.DATE APPROVED
24Emergency input contact to Lighting Controllers (including Mini Z
daylight harvest controllers) wired if applicableDATE APPROVED
SAFETY DEVICES
American University Cx Plan
Prefunctional Checklist Checklist Page 2 of 3 E2 PFC Lighting Controls.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
LIGHTING CONTROLS
PREFUNCTIONAL CHECKLIST
Lighting Control
System
ACCEPTANCE CRITERIA
Service Area
Contractor Notes
25 All occupancy sensors activate the appropriate light fixtures. DATE APPROVED
26All daylight photosensors are connected, programmed and
operating properly.DATE APPROVED
27Exterior lighting photocell connected, programmed and operating
properly.DATE APPROVED
28Digital Pushbutton Stations connected, programmed and
operating properly.DATE APPROVED
29Dimming system Class 2 Wiring installed as required by
manufacturer's requirements including use of CAT5 wiringDATE APPROVED
30 All control system programming is complete DATE APPROVED
31Control system programs backed up to prevent loss during
power outage as applicable.DATE APPROVED
32All occupancy sensors have been set to the time delays outlined
in the OPR.DATE APPROVED
33All daylight photosensors have been set to the light levels
outlined in the OPR or at minimum levels per IESNA standardsDATE APPROVED
34 Exterior photocell has been set DATE APPROVED
35Each circuit has been tested for short circuits before connection
to relay.DATE APPROVED
36Proper operation of each relay has been verified by using the
override buttonsDATE APPROVED
37 None.
REPORTS & DOCUMENTATION
POWER AND COMMUNICATION
SENSOR CALIBRATION
EQUIPMENT STARTUP AND QUALITY CONTROL TESTS
American University Cx Plan
Prefunctional Checklist Checklist Page 3 of 3 E2 PFC Lighting Controls.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
MV SWITCHGEAR ATO
PREFUNCTIONAL CHECKLIST
MV ATOAll
1 Wiring is completed (interconnection, control power etc.) DATE APPROVED
2 Control wiring has been verified. DATE APPROVED
3
Temporary control power is available so the operation of the
switches can be verified before the utility energizes the
feeders.
DATE APPROVED
4Switches have been opened and closed manually and using
the controls on the front panel.DATE APPROVED
5The sequence of operation has been successfully performed
(automatic transfer operation).DATE APPROVED
6 Temporary Power available for test equipment. DATE APPROVED
7 Installation is complete and ready for verification testing. DATE APPROVED
Switchgear Automatic Transfer Operation (ATO)
Service Area
Contractor Notes
ACCEPTANCE CRITERIA
American University Cx Plan
Prefunctional ChecklistPage 1 of 1
E3 PFC EXAMPLE MV Switchgear w ATO.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
GENERATOR
PREFUNCTIONAL CHECKLIST
Engine
GeneratorAll
1Ground bus(ses) have been installed and terminated to
ground grid systemDATE APPROVED
2Permanent labels for bus, section, breakers and devices
installedDATE APPROVED
3
Electrical equipment clean of construction debris, dust, and
moisture and egress routes from electrical room are
unobstructed.
DATE APPROVED
4All bolted connections securely fastened in accordance with
recommended torque valuesDATE APPROVED
5Generator neutral bus is solidly grounded by factory-installed
bonding jumper as specified for a four-pole systemDATE APPROVED
6 Generator frame and enclosure bonded to ground DATE APPROVED
7Generator anchored in place according to manufacturer’s
recommendationsDATE APPROVED
8
All bolted electrical connections have been tightened to their
proper torque values. (Note: some connections will be
disconnected as part of the functional testing. These
connections will be field torqued to proper settings at the
conclusion of the field-testing.)
DATE APPROVED
9Manufacturer’s field service personnel have completed
preliminary checkout and startupDATE APPROVED
10 Engine lube oil system is fully operational and free of leaks DATE APPROVED
11 Engine coolant system is fully operational and free of leaks DATE APPROVED
12 Fuel supply system tank is full and ready for operation DATE APPROVED
13 Engine exhaust is fully operational and free of leaks DATE APPROVED
14 Engine exhaust has rain cap installed at exterior outlet DATE APPROVED
15 Engine exhaust has condensate drain installed at silencer DATE APPROVED
16 Batteries are fully charged and in service DATE APPROVED
17
Generator remote annunciation panel is remotely installed,
electrically connected and fully operational to comply with
NFPA 110, Level 1 system.
DATE APPROVED
Engine Generator
Service Area
Contractor Notes
ACCEPTANCE CRITERIA
American University Cx Plan
Prefunctional Checklist Page 1 of 2 E4 PFC EXAMPLE Generator.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
GENERATOR
PREFUNCTIONAL CHECKLIST
Engine
GeneratorAllService Area
Contractor Notes
ACCEPTANCE CRITERIA
18
Generator remote E-stop is remotely installed, electrically
connected and fully operational to comply with NFPA 110,
Level 1 system
DATE APPROVED
19Generator control wiring to building management control
panel is installed, electrically connected and fully operationalDATE APPROVED
20
All Overcurrent protective devices have been installed at the
proper ampere rating and all settings have been adjusted to
match the final approved system Coordination Study.
DATE APPROVED
21 Utility Power is available and connected for system operation DATE APPROVED
22All status and alarm indicators are installed and functioning
properly. DATE APPROVED
23
All field and interconnecting wiring is completed and labeled
at each end with visible and readable tags, printed markings
on the conductors are NOT acceptable
DATE APPROVED
24
Testing agency or manufacturer's representative has been
scheduled to perform the test and the commissioning
authority has been notified of the testing date.
DATE APPROVED
25Test equipment requirements have been reviewed with the
testing agency or manufacturer's representative.DATE APPROVED
26 Power available for test equipment. DATE APPROVED
27 Installation is complete and ready for verification testing. DATE APPROVED
American University Cx Plan
Prefunctional Checklist Page 2 of 2 E4 PFC EXAMPLE Generator.xls
THIS FORM TO BE COMPLETED BY GENERAL CONTRACTOR
NAME: ________________________________________________
EXAMPLE
AUTOMATIC TRANSFER SWITCH
PREFUNCTIONAL CHECKLIST
Automatic
Transfer SwitchAll
1 Electrical room grounding system complete. DATE APPROVED
2Ground bus(ses) have been installed and terminated to
ground grid systemDATE APPROVED
3Doors to electrical room installed and locks or temporary
security measures installed.DATE APPROVED
4 Electrical room clear of storage, temporary equipment, etc. DATE APPROVED
5Permanent labels for bus, section, breakers and devices
installedDATE APPROVED
6
Electrical equipment clean of construction debris, dust, and
moisture and egress routes from electrical room are
unobstructed.
DATE APPROVED
7All bolted connections securely fastened in accordance with
recommended torque valuesDATE APPROVED
8Working clearances meet NEC and contract documents and
ATS has been installed on a level housekeeping padDATE APPROVED
9 ATS anchored per manufacturer’s instruction DATE APPROVED
10 All enclosure panels and doors in place, fitted, undamaged DATE APPROVED
11
All field and interconnecting wiring is completed and labeled
at each end with visible and readable tags, printed markings
on the conductors are NOT acceptable
DATE APPROVED
12NORMAL and EMERGENCY sources are available for
testing.DATE APPROVED
13All settings have been adjusted to Engineer's provided
settings.DATE APPROVED
14
Testing agency has been scheduled to perform the test and
the commissioning authority has been notified of the testing
date.
DATE APPROVED
15Test equipment requirements have been reviewed with the
testing agency.DATE APPROVED
16 Installation is complete and ready for verification testing. DATE APPROVED
Automatic Transfer Switch
Service Area
Contractor Notes
ACCEPTANCE CRITERIA
American University Cx Plan
Prefunctional Checklist Page 1 of 1 E5 PFC EXAMPLE Automatic Transfer Switch.xls
EXAMPLE
VAV WITH REHEAT AND PERIMETER HEAT
FUNCTIONAL PERFORMANCE TEST
0
0 Pass?
?
?
?
VAV 0-067 VAV 1-025 VAV 1-061
2,400 1,100 2,400
1,200 1,050 1,200
2,400 1,100 2,400
1,200 1,050 1,200
ACCEPTANCE CRITERIA
1 Observe VAV boxRemovable without removing
ductwork or piping.Pass? Pass? Pass?
2 Observe reheat coil location.Re-heat coil removable without
removing ductwork or piping.Pass? Pass? Pass?
3Observe reheat hot water valve
location
Accessible for maintenance or
replacementPass? Pass? Pass?
4Observe perimeter radiation hot
water valve location
Accessible for maintenance or
replacementPass? Pass? Pass?
5 Observe temperature sensor location Temporary location Pass? Pass? Pass?
Space temperature setpoint Insert Value Insert Value Insert Value
Space temperature Insert Value Insert Value Insert Value
VAV discharge temperature Insert Value Insert Value Insert Value
Supply airflow setpoint Insert Value Insert Value Insert Value
Supply airflow Insert Value Insert Value Insert Value
Damper position Insert Value Insert Value Insert Value
Reheat valve position Insert Value Insert Value Insert Value
Perimeter heating valve position Insert Value Insert Value Insert Value
Airflow increases to cooling
maximum CFM.Pass? Pass? Pass?
Reheat valve is closed. Pass? Pass? Pass?
Perimeter heating valve is closed. Pass? Pass? Pass?
Record airflow setpoint Insert Value Insert Value Insert Value
Record airflow Insert Value Insert Value Insert Value
Record damper position Insert Value Insert Value Insert Value
VAV discharge temperature is
about equal to the AHU discharge
air temperature.
Pass? Pass? Pass?
Record VAV discharge
temperatureInsert Value Insert Value Insert Value
VAV airflow. Insert Value Insert Value Insert Value
Reheat valve position. Insert Value Insert Value Insert Value
Perimeter heating valve position. Insert Value Insert Value Insert Value
VAV discharge temperature. Insert Value Insert Value Insert Value
Record damper position Insert Value Insert Value Insert Value
Occupied Space Temperature Cooling Setpoint
Passed
Tested
Initial Test Date
Retest 1
Retest 2
Room(s) Served
Max Cooling CFM
Min Cooling CFM
Max Heating CFM
Min Heating CFM
Occupied Space Temperature Heating Setpoint
Notes
ACTION
DEVICE LOCATIONS
TEST INITIATION
6Record Initial Performance
Parameters
OCCUPIED COOLING
7
Override the space temperature to:
cooling setpoint plus 4 F. (Or adjust
control setpoints to achieve the same
system reaction.)
8
Override the space temperature to:
cooling setpoint minus 1.5 F. (Or
adjust control setpoints to achieve the
same system reaction.) After 5 to 10
minutes, record the system
parameters.
American University Cx Plan
Functional Performance Test Page 1 of 2 F1 FPT Terminal Units EXAMPLE.xlsx
EXAMPLE
VAV WITH REHEAT AND PERIMETER HEAT
FUNCTIONAL PERFORMANCE TEST
0
0 Pass?
?
?
?
VAV 0-067 VAV 1-025 VAV 1-061
2,400 1,100 2,400
1,200 1,050 1,200
2,400 1,100 2,400
1,200 1,050 1,200
ACCEPTANCE CRITERIA
Occupied Space Temperature Cooling Setpoint
Passed
Tested
Initial Test Date
Retest 1
Retest 2
Room(s) Served
Max Cooling CFM
Min Cooling CFM
Max Heating CFM
Min Heating CFM
Occupied Space Temperature Heating Setpoint
Notes
ACTION
Airflow at heating CFM. Pass? Pass? Pass?
Reheat valve opens to100%
before the perimeter heating
valve opens? Sequence of
operation is not clear.
Pass? Pass? Pass?
Perimeter heating valve opens to
100%.Pass? Pass? Pass?
Discharge air temperature
increasesPass? Pass? Pass?
Record airflow Insert Value Insert Value Insert Value
Record damper position Insert Value Insert Value Insert Value
Record VAV discharge
temperatureInsert Value Insert Value Insert Value
10
Override the outside air temperature
to 41 F (or change the perimeter
heating lock-out setpoint).
Perimeter heating valve closes. Pass? Pass? Pass?
11
Override the outside air temperature
to 39 F (or change the perimeter
heating lock-out setpoint).
Perimeter heating valve opens. Pass? Pass? Pass?
Perimeter heating valve closes to
0% open prior to the reheat valve
closing? Sequence of operation
is not clear.
Pass? Pass? Pass?
VAV airflow Insert Value Insert Value Insert Value
Record damper position Insert Value Insert Value Insert Value
Reheat valve position. Insert Value Insert Value Insert Value
Perimeter heating valve position. Insert Value Insert Value Insert Value
VAV discharge temperature. Insert Value Insert Value Insert Value
13 Not applicable for this project.
14
Override the space temperature to 5
F below the space temperature
setpoint.
Alarm to the operator's console. Pass? Pass? Pass?
15
Override the space temperature to 5
F above the space temperature
setpoint.
Alarm to the operator's console. Pass? Pass? Pass?
16Deactivate any system over-rides
(setpoints, sensors, modes).
Terminal unit resumes normal
operationPass? Pass? Pass?
OCCUPIED HEATING
TEST CONCLUSION
9
Override the space temperature to:
heating setpoint minus 4 F. (Or
adjust control setpoints to achieve the
same system reaction.) Override the
outside air temperature to 39 F (or
change perimeter heating lock-out
setpoint).
12
Override the space temperature to:
heating setpoint plus 1.5 F. (Or
adjust control setpoints to achieve the
same system reaction.) After 5 to 10
minutes, record the system
parameters.
UNOCCUPIED MODE
ALARMS
American University Cx Plan
Functional Performance Test Page 2 of 2 F1 FPT Terminal Units EXAMPLE.xlsx
EXAMPLE
LIGHTING CONTROL SYSTEM
FUNCTIONAL PERFORMANCE TEST
TEST EQUIPMENT REQUIRED
Test Name
Light Level
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION
a
Ultrasonic ceiling mounted occupancy sensors are
mounted a minimum of six (6) feet from HVAC
supply/return vents
Pass?
bSensors mounted over doorways are placed one
(1) foot inside threshold.Pass?
c
All occupancy and daylight photo sensors are
easily accessible for adjustment, repair, and
replacement.
Pass?
Record results in applicable sensor
worksheets when checking function of
those sensors
dOutdoor photocell is mounted facing northern sky
and pointed away from nighttime light sources.Pass?
aLighting Controller located and mounted in a
location where audible noise is acceptablePass?
bLighting Controller voltage wiring is at least six (6)
feet from sound and electronic equipment wiring.Pass?
cClearance on left and right side of the relay
cabinets is 1 1/2 " or greaterPass?
dLighting Control cabinets are easily accessible for
adjustment, repair, and replacement.Pass?
eCabinets are cleaned of all dust, debris, metal
particles.Pass?
fRelay cabinet anchored and supported per
manufacturer's recommendationsPass?
1.3Check the lighting circuit breakers to ensure that
they are duty rated.a
Circuit breaker shall be rated for switching
functions “SWD”Pass?
OPEN OFFICE SPACE LIGHTING CONTROL
2.1
Verify that the occupancy sensing devices installed
match with drawings, shop drawings and
specifications.
aCorrect occupancy sensing devices have been
installed.Pass?
aLighting in open office spaces comes on at __ am
and turns off at __ pm.Pass?
Record results for each Open Office space
in Time Clock worksheet
bA blink warning occurs 5 minutes prior to lighting
shut off.Pass?
aLighting in each zone turns ON when initiating
overridePass?
Prior to functional testing, for best lamp life, verify installed fluorescent lamps have a logged 100 hours of operation prior to any dimming or testing of dimming.
Time controller function controls lighting in Open
Office Spaces as expected
2.3 Verify override control for each lighting zone.
Equipment Description
Light Level Meter
Verify Installation of lighting control devices.1.1
Verify installation of lighting controllers1.2
2.2
American University Cx Plan
Functional Performance Test Page 1 of 6Lighting Control
F2 FPT EXAMPLE Lighting Controls.xls
EXAMPLE
LIGHTING CONTROL SYSTEM
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
b
Lighting in other zones (not pressed) remains OFF -
until the zone override is initiated for each
particular zone.
Pass?
cLighting override times out after _____ minutes and
lighting turns OFF.Pass? Verify time in minutes of override control.
2.4 Verify daylighting control within open office spaces. a
Verify daylight photosensor controls - record test
data for each daylight photosensor in Daylight
Photosensor worksheet
Pass?
Light level setpoint for Open Office Spaces
to be verified prior to initiating this test -
confirm that light level meets or exceeds
IES recommended standards at the task
surface (50 fc assumed). Record results for
each photosensor in Daylight Photosensor
worksheet
a
Before __ am or after __ pm and after lighting in a
particular zone has automatically turned off, walk
by occupancy sensor and confirm that lighting
controlled by the occupancy sensor turns on.
Pass?
Record results for each sensor in
Occupancy Sensor worksheet. Note that
time ON may be user selected at time other
than __am to __pm. Record actual time
settings.
bAfter a time delay of __ minutes, lighting in area
controlled by occupancy sensor turns offPass?
Note that sensors can be set to shorter
timeout settings for these test, but must be
set back to original setting - see worksheet
a
Confirm that schedules can be re-assigned and
confirm that modified schedules respond as
expected.
Pass?
bConfirm that holiday schedule is programmed as
required.Pass?
2.7Return all changed control parameters and
conditions to their pre-set values.a
Time of day schedule, occupancy sensor timeout
delay and photosensor light level setpoints are
returned to initial settings.
Pass?
2.3 Verify override control for each lighting zone.
2.5
Review system programming options
Verify occupancy sensor control of lighting during
evening and weekend hours.
2.6
American University Cx Plan
Functional Performance Test Page 2 of 6Lighting Control
F2 FPT EXAMPLE Lighting Controls.xls
EXAMPLE
LIGHTING CONTROL SYSTEM
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
HALLWAYS AND LOBBY LIGHTING CONTROL
3.1
Verify that the occupancy sensing devices installed
match with drawings, shop drawings and
specifications.
aCorrect occupancy sensing devices have been
installed.Pass?
aLighting in Hallways and Lobbies comes on at __
am and turns off at __ pm.Pass?
Record results for each Hallway and Lobby
space in Time Clock worksheet
bA blink warning occurs 5 minutes prior to lighting
shut off.Pass?
a Lighting in Lobby turns on when initiating override Pass?
b Lighting in other zones (not Lobby) remain off. Pass?
cLighting override times out after _____ minutes and
Lobby lighting turns off.Pass? Verify time in minutes of override control.
a
Before __ am or after __ pm (same as Open Office
space time settings) and after lighting in Hallways
have automatically turned off, walk by occupancy
sensor and confirm that Hallway lighting controlled
by the occupancy sensor turns on.
Pass?
Record results for each sensor in
Occupancy Sensor worksheet. Note that
time on may be user selected at time other
than __am to __pm but should be same as
Open Office Space. Record actual time
settings.
bAfter a time delay of __ minutes, lighting in Hallway
controlled by occupancy sensor turns offPass?
Note that sensors can be set to shorter
timeout settings for these test, but must be
set back to original setting - see worksheet
3.5Return all changed control parameters and
conditions to their pre-set values.a
Time of day schedule, occupancy sensor timeout
delay and photosensor light level setpoints are
returned to initial settings.
Pass?
BATHROOM/RESTROOM, STORAGE CLOSETS AND ENCLOSED CORRIDORS - OCCUPANCY SENSOR VERIFICATION
4.1
Verify that the occupancy sensing devices installed
match with drawings, shop drawings and
specifications.
aCorrect occupancy sensing devices have been
installed.Pass?
Record each room in Occupancy Sensor
(OS) worksheet
4.2Verify all ceiling mounted occupancy sensing
devices.a
Ceiling mounted occupancy sensing devices have
been installed in the locations show on the design
drawings.
Pass?
4.3 Verify that lighting turns on when motion is sensed aUpon entering the room, the light fixtures will switch
ON.Pass?
4.4Remain motionless for occupancy sensor timeout
settinga
Light fixtures will remain on for __ minutes in
Restroom/Bathrooms, __ minutes in
storage/mechanical closets and __ minutes for
enclosed corridors
Pass?
Note that sensors can be set to shorter
timeout settings for these tests, but must be
set back to original setting - see Occupancy
Sensor Worksheet
4.5Return all changed control parameters and
conditions to their pre-set values.a
Occupancy sensor timeout delays are returned to
initial settings.Pass?
Time controller function controls lighting in Hallways
and Lobbies as expected
Verify override control for Lobby lighting zone.
Verify occupancy sensor control of Hallway Lighting
during evening and weekend hours.
3.2
3.3
3.4
American University Cx Plan
Functional Performance Test Page 3 of 6Lighting Control
F2 FPT EXAMPLE Lighting Controls.xls
EXAMPLE
LIGHTING CONTROL SYSTEM
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
PRIVATE OFFICES AND CONFERENCE ROOM - LIGHTING CONTROL VERIFICATION
5.1
Verify that the occupancy sensing devices installed
match with drawings, shop drawings and
specifications.
aCorrect occupancy sensing devices have been
installed.Pass?
Record each room in OS w override
worksheet
5.2 Verify all occupancy sensing devices. a
Occupancy sensing devices PIR/Ultrasonic and
have been installed in the locations show on the
design drawings.
Pass?
5.3 Verify that lighting turns on when motion is sensed aUpon entering the room, the light fixtures will switch
ON.Pass?
5.4Remain motionless for occupancy sensor timeout
settinga
Light fixtures will remain on for __ minutes in
Private Offices, and __ minutes in Conference
Rooms
Pass?
Note that sensors can be set to shorter
timeout settings for these tests, but must be
set back to original setting - see Occupancy
Sensor Worksheet
5.5After lighting has turned off, turn on again with
motion.a
Upon movement detected, the light fixtures will
switch ON.Pass?
5.6 Verify override control switch operation a
By pressing low voltage override switch, lighting is
turned off by tenant even though movement is
being detected by occupancy sensor.
Pass?
5.7Return all changed control parameters and
conditions to their pre-set values.a.
Occupancy sensor timeout delays are returned to
initial settings.Pass?
MECHANICAL/ELECTRICAL ROOMS AND COMPUTER ROOMS
6.1Verify that the ON/OFF switches installed match
with drawings, shop drawings and specifications. a Correct switches have been installed. Pass? Record rooms tested
6.2 Verify ON operation of ON/OFF digital switches a Pressing switch turns lighting ON. Pass?
6.3 Verify OFF operation of room lighting control a
Light fixtures will blink after __ minutes (5 minute
"blink warn") and then will turn OFF automatically
after 5 minutes.
Pass?
Note that sensors can be set to shorter
timeout settings for these tests (greater
than 5 minute blink warn), but must be set
back to original setting - see ON/OFF
Worksheet
6.4After lighting has turned OFF, turn on again with
ON/OFF digital switch.a Pressing switch turns lighting ON. Pass?
6.5After "blink warn" has occurred, but before 5
minutes are up, press digital switcha
Lighting remains ON for an additional ___ minutes
before turning OFF automatically. Confirm that 5
minute "blink warn" again initiates.
Pass?
6.6Return all changed control parameters and
conditions to their pre-set values.a OFF timeout delays are returned to initial settings. Pass?
American University Cx Plan
Functional Performance Test Page 4 of 6Lighting Control
F2 FPT EXAMPLE Lighting Controls.xls
EXAMPLE
LIGHTING CONTROL SYSTEM
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
BOARD ROOM LIGHTING CONTROL
aOnly appropriate electronic dimming ballasts in use
for fluorescent lamps.Pass?
b
Controller wired with copper or copper clad wire
only. If aluminum wire used, only use devices
marked CO/ALR or CU/AL.
Pass?
c Load types are not mixed on any single zone Pass?
dThe insulation of the Class I (line voltage) field
wiring must be rated no less than 75°C.Pass?
eNo more than two (2) 12 AWG wires installed on
each screw terminal.Pass?
fBoth fluorescent lighting fixtures and dimmer are
grounded per manufacturer's recommendations.Pass?
a
Test each named scene ("Presentation,”
"Chandelier", "Lunch", etc.) and confirm operation
and naming. Named scenes will appear in the
display (LCD) when the button is pressed.
Pass?
Note- this FPT developed around
Leviton D3206 Multizone
Controller/Dimmer. Modify based on
actual dimming system provided.
Required Scenes to be reviewed with
Owner's representative as required.
bTest MAX button and confirm that all Loads are set
to maximum BRIGHTPass?
cTest OFF button and confirm that all Loads are
turned OFF.Pass?
dTest OFF button and confirm that all Loads are
turned OFF.Pass?
eTest "Dim Scene" function. This button dims or
brightens the selected scene.Pass?
fTest "Dim/Bright" function and confirm that manual
control of light level for selected zone is enabled.Pass?
gConfirm that proper date and time have been
programmed.Pass?
h
If applicable, confirm timer trigger operation as
expected (i.e. specific timer triggers a SCENE,
MAX, OFF or Auto OFF).
Pass?
iConfirm that Holiday schedule has been set up if
applicable.Pass?
j
Verify Auto OFF as been programmed for energy
savings (if applicable). Confirm that lights
automatically turn OFF at the programmed time
after a warning blink to maximum.
Pass?
Verify operation of Multizone Dimmer/Controller.7.2
Verify that Multizone Dimmer/Controller and
accessories installed per manufacturer's
recommendations.
7.1
American University Cx Plan
Functional Performance Test Page 5 of 6Lighting Control
F2 FPT EXAMPLE Lighting Controls.xls
EXAMPLE
LIGHTING CONTROL SYSTEM
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
k
Verify Auto OFF override operational (if applicable).
When Auto OFF occurs, press a Scene, or Zone
Dim/Bright button and confirm override of Auto
OFF. Confirm that the unit then sweeps the loads
OFF after the user defined time interval (of up to 2
hours) has elapsed. Confirm time off interval per
Owner's requirements.
Pass?
lProgram saved or backed up per installation guide
when completed.Pass?
7.3 Verify operation of Infrared Remote Control aLighting control and programming operational from
up to 40 feet (and a 100⁰ angle) Pass?
EXTERIOR SITE LIGHTING CONTROL
aConfirm that when sight light level drops below
____ fc, Exterior Lighting turns ON Pass?
bConfirm that when sight light level rises above
____ fc, Exterior Lighting turns OFFPass?
General Notes
1
2
3
4
5
Verify operation of Multizone Dimmer/Controller.7.2
Verify the automated lighting controls of exterior
lighting fixtures connected to photocells.8.1
American University Cx Plan
Functional Performance Test Page 6 of 6Lighting Control
F2 FPT EXAMPLE Lighting Controls.xls
EXAMPLE
MEDIUM VOLTAGE SWITCH
FUNCTIONAL PERFORMANCE TEST
Medium Voltage Switch - Section 1 - Substation B
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Bolt Torque
Insulation Resistance
Over-Potential/Hi-Pot
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Switch has no visible damage. Pass?
b Switchgear has no visible damage. Pass?
d View glass installed. Pass?
1.3 Verify anchoring. Anchor bolts are installed. Pass?
a Volts: 13.8kV (15kV class) Pass?
b Amps: 600A Pass?
c Current Limiting Fuse - 150E, 17.5kV 65kAIC Pass?
d Frequency: 60hZ Pass?
e Switch - Momentary Current 40 kA Asym Pass?
f Switch - Short time Current rating 25 kA @ 2 sec Pass?
g Bus - 600A Silver plated copper Pass?
h Silver plated copper ground bus Pass?
g Main Bus Bracing: 40kA Asym, (25kA Sym) Pass?
h 95kV BIL Pass?
i Enclosure: NEMA 1 Pass?
a Adhesive backed. Pass?
b Black Letters on white background Pass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Frames and enclosures bolted to ground buss. Pass?
bConnection from station ground grid to equipment
ground bus.Pass?
c Cable shields Pass?
a Phase to Phase 7.5 inches. Pass?
b Phase to ground 5.0 inches. Pass?
c Phase barriers installed and not damaged. Pass?
a Door can not open with switch closed. Pass?
b Switch can not close with door open. Pass?
ELECTRICAL INTEGRITY
2.1 Disconnect PTs, CPTs, surge arrestors etc. N/A
2.2
With the switch in the CLOSED position, measure the contact
resistance of each phase. Measure A phase, B phase and C
phase. (Non-Fused)
a Readings are within 50% of the average value. Pass? See Data Table for test results.
2.3
With the switch in the CLOSED position, measure the contact
resistance of the fuse and Fuse
holder. Measure A phase, B phase and C phase.
resistance. (Fused)
a Readings are within 50% of the average value. Pass? See Data Table for test results.
2.4
Perform an insulation resistance test at 5000 VDC phase-to-
phase and phase-to-ground with the switch closed and across
open contacts of each phase with switch open. Test for 1
minute.
a Measured values are minimum 5000 Megohms. Pass? See Data Table for test results.
2.5
Perform a DC Over Potential test on each conductor, with
other phases and shield grounded. Maximum DC field test
voltage for 100% cables is 56kV and 64kV for 133% cables.
a Phase to ground withstand for one minute. Pass? See Data Table for test results.
2.6 Reconnect surge, arrestors, TVSS and PTs. N/A
FINAL INSPECTION
a Hardware replaced. Pass?
b Tools clear. Pass?
c Clean. Pass?
General Notes
1
2
3
4
5
3.1 Final Inspection.
Verify grounding
1.2
1.6
1.7
1.8
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Verify permanent labels and mimic bus are installed.
Battery or line-powered (Hand-crank not acceptable).
1.4
Verify door Interlocks.
Calibrated torque wrench
1.5
High voltage DC dielectric test set
Equipment Description
Verify clearances.
Verify ratings and configuration.
Inspect the exterior of the switchgear
DVM
American University Cx Plan
Functional Performance Test Page 1 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls
EXAMPLE
MEDIUM VOLTAGE SWITCH
FUNCTIONAL PERFORMANCE TEST
Medium Voltage Switch - Section 2 - Substation C
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Bolt Torque
Insulation Resistance
Over-Potential/Hi-Pot
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Switch has no visible damage. Pass?
b Switchgear has no visible damage. Pass?
d View glass installed. Pass?
1.3 Verify anchoring. Anchor bolts are installed. Pass?
a Volts: 13.8kV (15kV class) Pass?
b Amps: 600A Pass?
c Current Limiting Fuse - 150E, 17.5kV 65kAIC Pass?
d Frequency: 60hZ Pass?
e Switch - Momentary Current 40 kA Asym Pass?
f Switch - Short time Current rating 25 kA @ 2 sec Pass?
g Bus - 600A Silver plated copper Pass?
h Silver plated copper ground bus Pass?
g Main Bus Bracing: 40kA Asym, (25kA Sym) Pass?
h 95kV BIL Pass?
i Enclosure: NEMA 1 Pass?
a Adhesive backed. Pass?
b Black Letters on white background Pass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Frames and enclosures bolted to ground buss. Pass?
bConnection from station ground grid to equipment
ground bus.Pass?
c Cable shields Pass?
a Phase to Phase 7.5 inches. Pass?
b Phase to ground 5.0 inches. Pass?
c Phase barriers installed and not damaged. Pass?
a Door can not open with switch closed. Pass?
b Switch can not close with door open. Pass?
ELECTRICAL INTEGRITY
2.1 Disconnect PTs, CPTs, surge arrestors etc. N/A
2.2
With the switch in the CLOSED position, measure the contact
resistance of each phase. Measure A phase, B phase and C
phase. (Non-Fused)
a Readings are within 50% of the average value. Pass? See Data Table for test results.
2.3
With the switch in the CLOSED position, measure the contact
resistance of the fuse and Fuse
holder. Measure A phase, B phase and C phase.
resistance. (Fused)
a Readings are within 50% of the average value. Pass? See Data Table for test results.
2.4
Perform an insulation resistance test at 5000 VDC phase-to-
phase and phase-to-ground with the switch closed and across
open contacts of each phase with switch open. Test for 1
minute.
a Measured values are minimum 5000 Megohms. Pass? See Data Table for test results.
2.5
Perform a DC Over Potential test on each conductor, with
other phases and shield grounded. Maximum DC field test
voltage for 100% cables is 56kV and 64kV for 133% cables.
a Phase to ground withstand for one minute. Pass? See Data Table for test results.
2.6 Reconnect surge, arrestors, TVSS and PTs. N/A
FINAL INSPECTION
a Hardware replaced. Pass?
b Tools clear. Pass?
c Clean. Pass?
General Notes
1
2
3
4
5
Equipment Description
DVM
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Calibrated torque wrench
Battery or line-powered (Hand-crank not acceptable).
High voltage DC dielectric test set
1.2 Inspect the exterior of the switchgear
1.4 Verify ratings and configuration.
1.5 Verify permanent labels and mimic bus are installed.
3.1 Final Inspection.
1.6 Verify grounding.
1.7 Verify clearances.
1.8 Verify door Interlocks.
American University Cx Plan
Functional Performance Test Page 2 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls
EXAMPLE
MEDIUM VOLTAGE SWITCH
FUNCTIONAL PERFORMANCE TEST
Medium Voltage Switch - Section 10 - Main 2 Section (Main Tie Main swgr)
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Bolt Torque
Insulation Resistance
Over-Potential/Hi-Pot
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Switch has no visible damage. Pass?
b Switchgear has no visible damage. Pass?
d View glass installed. Pass?
1.3 Verify anchoring. Anchor bolts are installed. Pass?
a Type HVL, Series 2 Dual Trip Pass?
b 120VAC Motor Operated Pass?
c Volts: 13.8kV (15kV class) Pass?
d Amps: 600A Pass?
e Current Limiting Fuse - 150E, 17.5kV 65kAIC Pass?
f Frequency: 60hZ Pass?
g Switch - Momentary Current 40 kA Asym Pass?
h Switch - Short time Current rating 25 kA @ 2 sec Pass?
g Bus - 600A Silver plated copper Pass?
h Silver plated copper ground bus Pass?
i Main Bus Bracing: 40kA Asym, (25kA Sym) Pass?
j 95kV BIL Pass?
k PT: 13800:120 Pass?
l Surge arrestor: Type XEP, 18kV, 15.3kV MCOV Pass?
m Enclosure: NEMA 1 Pass?
a Lights operational using push to test button Pass?
bLights operational with change of state - if no push
to testPass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Adhesive backed. Pass?
b Black Letters on white background Pass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Frames and enclosures bolted to ground buss. Pass?
bConnection from station ground grid to equipment
ground bus.Pass?
c Cable shields Pass?
a Phase to Phase 7.5 inches. Pass?
b Phase to ground 5.0 inches. Pass?
c Phase barriers installed and not damaged. Pass?
a Door can not open with switch closed. Pass?
b Switch can not close with door open. Pass?
ELECTRICAL INTEGRITY
2.1 Disconnect PTs, CPTs, surge arrestors etc. N/A
2.2
With the switch in the CLOSED position, measure the contact
resistance of each phase. Measure A phase, B phase and C
phase. (Non-Fused)
a Readings are within 50% of the average value. Pass?
2.3
With the switch in the CLOSED position, measure the contact
resistance of the fuse and Fuse
holder. Measure A phase, B phase and C phase.
resistance. (Fused)
a Readings are within 50% of the average value. Pass?
2.4
Perform an insulation resistance test at 5000 VDC phase-to-
phase and phase-to-ground with the switch closed and across
open contacts of each phase with switch open. Test for 1
minute.
a Measured values are minimum 5000 Megohms. Pass?
2.5
Perform a DC Over Potential test on each conductor, with
other phases and shield grounded. Maximum DC field test
voltage for 100% cables is 56kV and 64kV for 133% cables.
a Phase to ground withstand for one minute. Pass?
2.6 Reconnect surge, arrestors, TVSS and PTs. N/A
SWITCH OPERATION
aSwitch opens with front mounted Trip position of
selector switchPass?
bSwitch closes with front mounted Closed position of
selector switchPass?
FINAL INSPECTION
a Hardware replaced. Pass?
b Tools clear. Pass?
c Clean. Pass?
General Notes
1
2
3
4
5
Equipment Description
DVM
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Calibrated torque wrench
Battery or line-powered (Hand-crank not acceptable).
High voltage DC dielectric test set
1.2 Inspect the exterior of the switchgear
1.4 Verify ratings and configuration.
1.5 Pilot lights installed and operational
1.6 Verify permanent labels and mimic bus are installed.
1.7 Verify grounding.
1.8 Verify clearances.
1.9 Verify door Interlocks.
3.1 Operate Main A Switch manually with manual trip-close swtich
4.1 Final Inspection.
American University Cx Plan
Functional Performance Test Page 3 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls
EXAMPLE
MEDIUM VOLTAGE SWITCH
FUNCTIONAL PERFORMANCE TEST
Medium Voltage Switch - Section 6 - Main 1 Section (Main Tie Main swgr)
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Bolt Torque
Insulation Resistance
Over-Potential/Hi-Pot
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Switch has no visible damage. Pass?
b Switchgear has no visible damage. Pass?
d View glass installed. Pass?
1.3 Verify anchoring. Anchor bolts are installed. Pass?
a Type HVL, Series 2 Dual Trip Pass?
b 120VAC Motor Operated Pass?
c Volts: 13.8kV (15kV class) Pass?
d Amps: 600A Pass?
e Current Limiting Fuse - 150E, 17.5kV 65kAIC Pass?
f Frequency: 60hZ Pass?
g Switch - Momentary Current 40 kA Asym Pass?
h Switch - Short time Current rating 25 kA @ 2 sec Pass?
g Bus - 600A Silver plated copper Pass?
h Silver plated copper ground bus Pass?
i Main Bus Bracing: 40kA Asym, (25kA Sym) Pass?
j 95kV BIL Pass?
k PT: 13800:120 Pass?
l Surge arrestor: Type XEP, 18kV, 15.3kV MCOV Pass?
m Enclosure: NEMA 1 Pass?
a Lights operational using push to test button Pass?
bLights operational with change of state - if no push
to testPass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Adhesive backed. Pass?
b Black Letters on white background Pass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Frames and enclosures bolted to ground buss. Pass?
bConnection from station ground grid to equipment
ground bus.Pass?
c Cable shields Pass?
a Phase to Phase 7.5 inches. Pass?
b Phase to ground 5.0 inches. Pass?
c Phase barriers installed and not damaged. Pass?
a Door can not open with switch closed. Pass?
b Switch can not close with door open. Pass?
ELECTRICAL INTEGRITY
2.1 Disconnect PTs, CPTs, surge arrestors etc. N/A
2.2
With the switch in the CLOSED position, measure the contact
resistance of each phase. Measure A phase, B phase and C
phase. (Non-Fused)
a Readings are within 50% of the average value. Pass?
2.3
With the switch in the CLOSED position, measure the contact
resistance of the fuse and Fuse
holder. Measure A phase, B phase and C phase.
resistance. (Fused)
a Readings are within 50% of the average value. Pass?
2.4
Perform an insulation resistance test at 5000 VDC phase-to-
phase and phase-to-ground with the switch closed and across
open contacts of each phase with switch open. Test for 1
minute.
a Measured values are minimum 5000 Megohms. Pass?
2.5
Perform a DC Over Potential test on each conductor, with
other phases and shield grounded. Maximum DC field test
voltage for 100% cables is 56kV and 64kV for 133% cables.
a Phase to ground withstand for one minute. Pass?
2.6 Reconnect surge, arrestors, TVSS and PTs. N/A
SWITCH OPERATION
aSwitch opens with front mounted Trip position of
selector switchPass?
bSwitch closes with front mounted Closed position of
selector switchPass?
FINAL INSPECTION
a Hardware replaced. Pass?
b Tools clear. Pass?
c Clean. Pass?
General Notes
1
2
3
4
5
Equipment Description
DVM
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Calibrated torque wrench
Battery or line-powered (Hand-crank not acceptable).
High voltage DC dielectric test set
1.2 Inspect the exterior of the switchgear
1.4 Verify ratings and configuration.
1.5 Pilot lights installed and operational
1.6 Verify permanent labels and mimic bus are installed.
1.7 Verify grounding.
1.8 Verify clearances.
1.9 Verify door Interlocks.
3.1 Operate Main B Switch manually with manual trip-close swtich
4.1 Final Inspection.
American University Cx Plan
Functional Performance Test Page 4 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls
EXAMPLE
MEDIUM VOLTAGE SWITCH
FUNCTIONAL PERFORMANCE TEST
Medium Voltage Switch - Section 8 - Tie (Main Tie Main swgr)
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Bolt Torque
Insulation Resistance
Over-Potential/Hi-Pot
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Switch has no visible damage. Pass?
b Switchgear has no visible damage. Pass?
d View glass installed. Pass?
1.3 Verify anchoring. Anchor bolts are installed. Pass?
a Type HVL, Series 2 Dual Trip Pass?
b 120VAC Motor Operated Pass?
c Volts: 13.8kV (15kV class) Pass?
d Amps: 600A Pass?
e Current Limiting Fuse - 150E, 17.5kV 65kAIC Pass?
f Frequency: 60hZ Pass?
g Switch - Momentary Current 40 kA Asym Pass?
h Switch - Short time Current rating 25 kA @ 2 sec Pass?
g Bus - 600A Silver plated copper Pass?
h Silver plated copper ground bus Pass?
i Main Bus Bracing: 40kA Asym, (25kA Sym) Pass?
j 95kV BIL Pass?
m Enclosure: NEMA 1 Pass?
a Lights operational using push to test button Pass?
bLights operational with change of state - if no push
to testPass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Adhesive backed. Pass?
b Black Letters on white background Pass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Frames and enclosures bolted to ground buss. Pass?
bConnection from station ground grid to equipment
ground bus.Pass?
c Cable shields Pass?
a Phase to Phase 7.5 inches. Pass?
b Phase to ground 5.0 inches. Pass?
c Phase barriers installed and not damaged. Pass?
a Door can not open with switch closed. Pass?
b Switch can not close with door open. Pass?
ELECTRICAL INTEGRITY
2.1 Disconnect PTs, CPTs, surge arrestors etc. N/A
2.2
With the switch in the CLOSED position, measure the contact
resistance of each phase. Measure A phase, B phase and C
phase. (Non-Fused)
a Readings are within 50% of the average value. Pass? See Data Table for test results.
2.3
With the switch in the CLOSED position, measure the contact
resistance of the fuse and Fuse
holder. Measure A phase, B phase and C phase.
resistance. (Fused)
a Readings are within 50% of the average value. Pass?
2.4
Perform an insulation resistance test at 2500 VDC phase-to-
phase and phase-to-ground with the switch closed and across
open contacts of each phase with switch open. Test for 1
minute.
a Measured values are minimum 5000 Megohms. Pass? See Data Table for test results.
2.5
Perform a DC Over Potential test on each conductor, with
other phases and shield grounded. Maximum DC field test
voltage for 100% cables is 56kV and 64kV for 133% cables.
a Phase to ground withstand for one minute. Pass? See Data Table for test results.
2.6 Reconnect surge, arrestors, TVSS and PTs. N/A
SWITCH OPERATION
aSwitch opens with front mounted Trip position of
selector switchPass?
bSwitch closes with front mounted Closed position of
selector switchPass?
FINAL INSPECTION
a Hardware replaced. Pass?
b Tools clear. Pass?
c Clean. Pass?
General Notes
1
2
3
4
5
Equipment Description
DVM
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Calibrated torque wrench
Battery or line-powered (Hand-crank not acceptable).
High voltage DC dielectric test set
1.2 Inspect the exterior of the switchgear
1.4 Verify ratings and configuration.
1.5 Pilot lights installed and operational
1.6 Verify permanent labels and mimic bus are installed.
1.7 Verify grounding.
1.8 Verify clearances.
Operate Tie Switch manually with manual trip-close swtich3.1
1.9 Verify door Interlocks.
4.1 Final Inspection.
American University Cx Plan
Functional Performance Test Page 5 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls
EXAMPLE
MEDIUM VOLTAGE SWITCH
FUNCTIONAL PERFORMANCE TEST
Medium Voltage Main-Tie-Main Switchgear.
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Bolt Torque
Insulation Resistance
Over-Potential/Hi-Pot
Protective Functions
Transformer Turns Ratio
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Switchgear has no visible damage. Pass?
b Interior is clean and dry. Pass?
1.3 Verify anchoring. Anchor bolts are installed. Pass?
a Volts: 13.8kV (15kV class) Pass?
b Main Bus Bracing: 40kA Asym, (25kA Sym) Pass?
c 95kV BIL Pass?
d Amps:600A, Silver Plated Copper Pass?
e Silver Plated Copper Ground Bus Pass?
f Frequency: 60hZ Pass?
gController: SEL 2411, Part #
241101A2X2X3A3A0100Pass?
hUndervoltage Relay and Phase Sequence: ASEA
Brown Boveri, Type 47Pass?
i Enclosure: NEMA 1 Pass?
jControl power is supplied by customer supplied
UPSPass?
a Adhesive backed. Pass?
b Black Letters on white background Pass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Lights operational using push to test button Pass?
bLights operational with change of state - if no push
to testPass?
c 3/16" minimum height. Pass?
d Mimic bus is installed. Pass?
a Frames and enclosures bolted to ground buss. Pass?
bConnection from station ground grid to equipment
ground bus.Pass?
c Cable shields Pass?
a Phase to Phase 7.5 inches. Pass?
b Phase to ground 5.0 inches. Pass?
c Phase barriers installed and not damaged. Pass?
1.9 Verify Accessories provided a Hot stick with fuse handling tool provided Pass?
a Door can not open with switch closed. Pass?
b Switch can not close with door open. Pass?
ELECTRICAL INTEGRITY
2.1
Perform an insulation resistance test of the switchgear bus at
5000 VDC phase-to-phase and phase-to-ground.Test for 1
minute.
a Measured values are minimum 5000 Megohms. Pass?
a Pickup voltage within tolerance. Pass?
b Drop-out voltage within tolerance. Pass?
c Time delay within tolerance. Pass?
d Undervoltage relay trips the lockout relay (86). Pass?
e Undervoltage for Main A annunciated Pass?
a Pickup voltage within tolerance. Pass?
b Drop-out voltage within tolerance. Pass?
c Time delay within tolerance. Pass?
d Undervoltage relay trips the lockout relay (86). Pass?
e Undervoltage for Main B annunciated Pass?
aOutput contact picks up when voltage, frequency
and phase angle match on both sides of relay.Pass?
b
Output contact drops out when voltage is raised
above high tolerance and lowered below low
tolerance.
Pass?
c
Output contact drops out when frequency is raised
above high tolerance and lowered below low
tolerance.
Pass?
d
Output contact drops out when phase angle
difference is adjusted above the leading tolerance
and above the lagging tolerance.
Pass?
e
Output contact changes state when voltage is
applied to Main A side of relay and no voltage is
applied to Main B side of relay
Pass?
POTENTIAL TRANFORMERS (PTs) AND CURRENT TRANSFORMERS (CTs)
3.1 Instrument Transformers installed per Xcel requirements a
Minimum clearances around instrument
transformers
7.5" Phase to Phase
5.0" Phase to Ground
Pass?
3.3 PTs installation verified a ABB VIZ-75 unfused voltage transformers installed Pass?
3.3Perform an insulation resistance test on each potential
transformer. Measure phase A, B and C.a Measured values are minimum 5000 Megohms. Pass?
a Ratio accuracies are within 0.5% of nameplate. Pass?
b Polarity results match transformer markings. Pass?
ALARMS AND CONTROL PANEL TEST
5.1Verify connections to the building automation or other
monitoring system.a
Values and equipment status and alarms
displayed locally match values displayed on the
BAS.
Pass?
FINAL INSPECTION
a Hardware replaced. Pass?
b Tools clear. Pass?
c Clean. Pass?
General Notes
1
2
3
4
5
3-Phase Test Set (voltage and current)
2.3Using a three-phase test set, verify the operation of the
under-voltage (27) function of Main B
2.2Using a three-phase test set, verify the operation of the
under-voltage (27) function of Main A
2.4Using a three-phase test set, verify the operation of the sync-
check (25c) relay.
Measures turns ration and polarity
1.2 Inspect the exterior of the switchgear
Equipment Description
DVM
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Calibrated torque wrench
Battery or line-powered (Hand-crank not acceptable).
High voltage DC dielectric test set
1.4 Verify ratings and configuration.
1.5 Verify permanent labels and mimic bus are installed.
1.7 Verify grounding.
1.6 Pilot lights installed and operational
6.1 Final Inspection.
1.8 Verify clearances.
1.10 Verify door Interlocks.
3.5Perform a turns ratio test on each potential transformer.
Measure phase A, B and C. Test at all tap positions.
American University Cx Plan
Functional Performance Test Page 6 of 6 F3 FPT EXAMPLE MV Switchgear with MV Switches.xls
EXAMPLE
GENERATOR
FUNCTIONAL PERFORMANCE TEST
Generator
TEST EQUIPMENT REQUIRED
Test Name
Voltage/Continuity
Bolted Connection or Contact Resistance
Insulation Resistance
Primary Current Injection
2 and 4 Hour Load Bank Test
Phase Rotation
Volt. & Freq. Regulation
Decibel
Back Pressure
Bolt Torque
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a kW:______kW Pass?
b Rating: ____HP @ 1800RPM Pass?
c Freq.: 60hZ Pass?
d Phase/Wire: 3ph, 4W Pass?
e Power Factor: 0.8 Pass?
f Voltage Output: 480/277V Pass?
g Sound attenuation enclosure Pass?
a _____A, 3P Main Bkr Pass?
bGround fault protection is disabled or ground fault
indication only providedPass?
c
Circuit breaker is set per the coordination study and
provided with selective coordination - solid state trip
unit.
Pass?
d No visible damage to circuit breaker enclosure. Pass?
a No visible damage to generator or enclosure. Pass?
b Engine generator exterior is clean and dry. Pass?
c Generator control panel interior is clean and dry. Pass?
dGenerator control panel mounted at an accessible
height.Pass?
eVibration isolation is installed at engine and at
radiatorPass?
fExternal connections are made with flexible
connections.Pass?
gVerify remote monitoring wiring is connected and
labeled.Pass?
h Verify control wiring is connected and labeled. Pass?
iFeeder cable/bus routing doesn’t obstruct access
for operation or maintenance.Pass?
jControl wiring harness(es) does not rub against
vibrating or moving parts.Pass?
1.5 Verify anchoring. aAnchor bolts are provided in locations shown on
manufacturer's drawings.Pass?
aVerify ground rod is installed with connection to
engine generator frame.Pass?
bGenerator neutral is bonded to ground with
conductor sized per NEC 250-20.Pass?
cMeasured diameter of bare copper conductor
corresponds to diameter of specified conductorsPass?
d Ground strap from engine to frame. Pass?
e Ground strap from generator enclosure to frame. Pass?
fGround bus provided in termination cabinet with
properly terminated ground conductors.Pass?
Verify proper phasing
Computer to record voltage and frequency from the output of the generator control panel.
Four-probe Digital Low Resistance Ohmmeter (DLRO)
Battery or line-powered (Hand-crank not acceptable).
Current Injection Test Device rated for 2X the ground fault pickup setting of the breaker
Resistive load bank with capacity equal to or greater than rated load. Rated at 2% accuracy for voltage, current and KW.
Equipment Description
Measure sound pressure
Manometer with a scale of greater than 40” water
Calibrated torque wrench
DVM
1.2
1.6
1.3
1.4
Verify circuit breaker settings.
Verify that the Engine, Generator, Battery, and Battery
Charger nameplate data .
Verify equipment grounding.
Inspect physical and mechanical condition.
American University Cx Plan
Functional Performance Test Page 1 of 4 F4 FPT EXAMPLE Generator.xls
EXAMPLE
GENERATOR
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
1.7Verify lube oil levels are within manufacturer’s recommended
limits.a Lube oil level is filled to proper level. Pass?
a Tank(s) full of fuel (90% for diesel). Pass?
b Fuel level in fuel tank(s) matches fuel gauge. Pass?
c Fuel system is free of leaks. Pass?
d Flexible fuel lines are installed at engine. Pass?
a Coolant level is filled to proper level. Pass?
b Verify coolant system freeze protection level. Pass?
c Cooling system is free from leaks. Pass?
dFlexible coolant lines are installed between engine
and radiator.Pass?
aExhaust system, silencer and flexible connector
installed and supported.Pass?
bExhaust system expansion is not transferred to
engine components such as turbocharger.Pass?
cSilencer is equipped with condensate drain plug and
turn valve.Pass?
d Exhaust system is equipped with rain cap. Pass?
eExhaust system has at least 9” clearance from
combustible materials.Pass?
ELECTRICAL INTEGRITY
2.1 Prior to step 4.1 verify correct phase rotation. aPhase rotation at generator matches NORMAL
power source.Pass?
aVerify that valves to the water jacket heater are
open.Pass?
bVerify thermostats switch at their setpoint
temperatures (110°F).Pass?
cVerify pump runs continuously independent of
heater operation.Pass?
a Loss of Power Alarm is operable Pass?
b Low Battery Volt Alarm operable. Pass?
c High Battery Volt Alarms operable. Pass?
d Power On led in on Pass?
2.4With the breaker (s) in the CLOSED position, measure the
contact resistance of each phase of the primary circuit.a Readings are within 50% of the average value. Pass?
2.5
Perform an insulation resistance test on the Generator Circuit
Breaker(s) at 1000VDC, phase-to-phase and phase to ground,
connected to the bus in the CLOSED position, in accordance
with NETA Table 100.1.
Note: Disconnect line and load side conductors.
aMinimum insulation resistance shall be 100
Megohms.Pass?
2.6
Test the Long Time Delay (seconds) and Long Time Pickup
current (amperes) setting of the breaker, by using primary
current injection.
aLong delay current pick up and time delay per
coordination study.Pass?
2.7
Test the Short Time Delay (seconds) and Short Time Pickup
current (amperes) setting of the breaker, by using primary
current injection.
aShort delay current pick up and time delay per
coordination study.Pass?
2.8
Test the Instantaneous Time Delay (seconds) and
Instantaneous Time Pickup current (amperes) setting of the
breaker, by using primary current injection.
a Instantaneous pick up per coordination study. Pass?
Verify fuel system installation and integrity.
Verify operation of battery and starting system.
Record cell voltages for all cells with terminals available, total
battery charging voltage and charging current.
2.2
1.8
1.9
1.10
Verify cooling system installation and integrity.
Verify operation of coolant line heater.
2.3
Verify exhaust system installation and integrity.
American University Cx Plan
Functional Performance Test Page 2 of 4 F4 FPT EXAMPLE Generator.xls
EXAMPLE
GENERATOR
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
ALARMS AND CONTROL PANEL TEST
3.1Verify control wiring between generator and ATS are correctly
terminated. a Terminations match shop drawings. Pass?
3.2
Record all setpoints at Engine Generator Control Panel.
Note: Manufacturer’s checklist can be attached to this form in
lieu of recording.
N/A
a Overcrank Pass?
b Low Water Temp Pass?
c High Water Temp Pass?
d Low Oil Pressure Pass?
e Overspeed Pass?
f Low Coolant Level Pass?
g EPS Supplying Load Pass?
h Control switch not in Auto Pass?
i High Battery Voltage Pass?
j Low Battery Voltage Pass?
k Battery Charger AC Failure Pass?
l Lamp Test Pass?
m Contacts for local and remote common alarm Pass?
a Overcrank Pass?
b High Water Temp Pass?
c Low Oil Pressure Pass?
d Overspeed Pass?
e Low Coolant Level Pass?
a Overcrank Pass?
b Low Water Temp Pass?
c High Water Temp Pass?
d Low Oil Pressure Pass?
e Overspeed Pass?
f Low Coolant Level Pass?
g Control switch not in Auto Pass?
h Contacts for local and remote common alarm Pass?
i Audible alarm silencing switch Pass?
3.6 Verify installation of remote E-Stop. a E-stop pushbutton is accessible. Pass?
LOADBANK TEST
4.1 Verify correct phase rotation prior to transfer of load aPhase rotation at generator matches NORMAL
power source.Pass?
a Engine starts and runs. Pass?
b Air intake louvers open fully. Pass?
c Exhaust damper opens fully. Pass?
d Fuel is not leaking. Pass?
e Coolant is not leaking. Pass?
f Lube oil is not leaking. Pass?
g Exhaust system expansion is not transferred to Pass?
h Exhaust system is not leaking. Pass?
4.3
Restore NORMAL sources to ATS’s (or turn off load bank)
and transfer ALL load off of generator and allow to cool down
for 5 minutes
a Generator runs in cool down mode for 5 min. Pass?
a Engine starts and runs. Pass?
b Air intake louvers open fully. Pass?
c Exhaust damper opens fully. Pass?
a Fuel is not leaking. Pass?
b Coolant is not leaking. Pass?
c Lube oil is not leaking. Pass?
dExhaust system expansion is not transferred to
engine system components.Pass?
Verify remote audible annunciation of all status, warning/pre-
alarm, and shutdown conditions per manufacturer’s
instructions.
Verify all warning/pre-alarms per manufacturer’s instructions
and verify operation and local annunciation at Engine
Generator Control Panel.
Verify all shutdown conditions per manufacturer’s instructions
and verify operation and local annunciation at Engine
Generator Control Panel.
4.2
With generator in a “cold start” condition, conduct a load
performance test, by initiating a NORMAL failure and transfer
of ATS’s.
Load generator for a maximum of 2 hrs using available
building load and/or a load bank
During test, verify exhaust, coolant, and fuel system is
functioning properly.
4.4
3.5
With a load bank connected to the load side terminals of the
generator, start generator at local control panel with engine
control switch.
Conduct a load performance test utilizing a load bank to
achieve 100% rated load of generator.
Load generator at 50% for 15 min.
Load generator at 75% for 15 min.
Load generator at 100% for 3.5 hrs
During test, verify exhaust, coolant, and fuel system is
functioning properly.
3.3
3.4
4.5
American University Cx Plan
Functional Performance Test Page 3 of 4 F4 FPT EXAMPLE Generator.xls
EXAMPLE
GENERATOR
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
e Exhaust system is not leaking. Pass?
4.6In conjunction with step 4.4, verify voltage regulation by
recording RMS voltage while increasing load on generator.a Voltage regulation is ±1%. Pass?
4.7In conjunction with step 4.4, verify frequency regulation by
recording frequency while increasing load on generator.a Frequency regulation is ±1%. Pass?
4.8In conjunction with step 4.4, measure harmonic content of
output voltage at 50 and 100 percent rated load.Pass?
4.9During step 4.4, verify engine operation is within normal
operating limits.Pass?
4.10
During step 4.4 while generator is running at 100% load,
measure sound level. Measure at four locations on the
property line.
a Pass?
4.11While generator is running at 100% load, conduct Exhaust-
System Back Pressure Test.a
Maximum backpressure at full-rated load is within
manufacturer’s written maximum allowable limits of
5.9 kPa or 1.7” Hg for the engine.
Pass?
a Generator cools down Pass?
b No leaks from any system are found Pass?
4.13
After the cool down, once the prime mover has reached rated
voltage and frequency, transfer full rated load onto the engine
generator in a single block.
a
Engine continues to run without shutdown or
overspeed trip and recovers to steady state voltage
and frequency ranges within 5 seconds.
Pass?
a Generator shuts down Pass?
b Remote annunciator alarms with E-Stop Pass?
aEngine cycle cranks a minimum of three 15-second
cranking cycles with 15 seconds between cycles.Pass?
b
At completion of third cycle engine stops cranking
and “OVERCRANK” shutdown alarm is annunciated
locally and remotely.
Pass?
SPACE HEATER OPERATION
5.1 Adjust thermostat to 5 degrees below space temperature. a Space heater turns on to maintain set point. Pass?
5.2 Adjust thermostat to 5 degrees above space temperature. a Space heater turns off to maintain set point. Pass?
LOUVER OPERATION
Perform the following tests immediately after the load bank test.
a Generator starts and runs. Pass?
b Louvers open. Pass?
6.2 Turn generator control to “STOP”. a Louvers remain open. Pass?
6.3 Record Louver set point. N/A
6.4Adjust the Louver set point to a setting above the enclosure
temperature.a
Louvers close.Pass?
6.5
Return the Louver temperature set point to the original value.
a
Louvers re-open if the enclosure temp is above set
point or remain closed if the enclosure temp is
below the set point.
Pass?
FINAL INSPECTION
7.1After testing is performed on the generator, verify tightness of
field landed feeder terminations.a
Feeder cable connections properly torqued and
marked.Pass?
7.2 Refill fuel tanks and verify 90% fuel levels. a Fuel level indicator verifies 90% fuel level in tank. Pass?
General Notes
1
2
3
Decrease load to 0% and shutdown generator with local E-
Stop.
Disconnect fuel solenoid and simulate START to engine.
4.14
Decrease load to 0% and allow the generator to cool down for
5 minutes
Conduct a load performance test utilizing a load bank to
achieve 100% rated load of generator.
Load generator at 50% for 15 min.
Load generator at 75% for 15 min.
Load generator at 100% for 3.5 hrs
During test, verify exhaust, coolant, and fuel system is
functioning properly.
6.1Turn generator control to “RUN” (if not already running)
4.15
4.12
4.5
American University Cx Plan
Functional Performance Test Page 4 of 4 F4 FPT EXAMPLE Generator.xls
EXAMPLE
CLOSED TRANSITION AUTOMATIC TRANSFER SWITCH
W ISOLATION BYPASS
FUNCTIONAL PERFORMANCE TEST
Automatic Transfer Switch (ATS), Closed Transition with Isolation Bypass
TEST EQUIPMENT REQUIRED (TO BE PROVIDED BY CONTRACTOR OR TEST AGENCY)
Test Name
Bolt Torque
Bolted Connection or Contact Resistance
Voltage/Continuity
Insulation Resistance
Action Expected Result Status Comments Notes/Reference Initial Date
INSTALLATION INTEGRITY
1.1Safe conditions (protective gear in-place, available &
procedures observed)Pass?
a Normal: Pass?
b Emergency: Pass?
a Volts: ______VAC Pass?
b Amps: _____A Pass?
c __4 pole, ___W Pass?
d Frequency: 60hZ Pass?
e Interrupting Rating: Pass?
f Enclosure: NEMA 1 Pass?
a Adhesive backed. Pass?
b White letters on dark gray background. Pass?
c 3/8 in minimum height. Pass?
a Door opens freely and swings fully open. Pass?
b 3’-6” minimum clearance in front of switch. Pass?
cCables do not block access to indicators or
adjustable components.Pass?
dCables do not block access to manual transfer
switch operator.Pass?
a No visible signs of damage. Pass?
b No visible dirt, metal chips or contamination. Pass?
c Appropriate source indicating lights are illuminated. Pass?
1.7 Verify anchoring. aAnchor bolts are provided in locations shown on
manufacturer's drawings.Pass?
a Enclosure bonded to ground bus. Pass?
b
Incoming (normal and emergency) and outgoing
(load) feeder grounding conductors bonded to
ground bus.
Pass?
c Neutral bus/pole isolated from ground. Pass?
1.9Confirm that components of control system including terminal
block, wiring, and Ni-Cad batteries are complete.a Pass?
aSwitch should transfer smoothly and with full
contact travel speed.Pass?
b
Mechanical interlocking should prevent
simultaneous closure of NORMAL and
EMERGENCY sources.
Pass?
1.11 Perform manual bypass transfer operation to each source. aSwitch should transfer smoothly and with full
contact travel speed.Pass?
Verify ATS is properly grounded.
1.10
Perform manual transfer operation with both NORMAL and
EMERGENCY sources de-energized. Use detachable
manual operator to transfer from NORMAL to EMERGENCY
and back.
Equipment Description
1.4 Verify permanent labels for transfer switch is installed.
1.5
Calibrated torque wrench
1.2Confirm that NORMAL and EMERGENCY sources match
final design drawings.
1.3Verify nameplate data matches one-line drawings,
specifications, and shop drawings.
Four-probe Digital Low Resistance Ohmmeter (DLRO)
DVM
Battery or line-powered (Hand-crank not acceptable).
Verify accessibility for maintenance.
1.6 Inspect physical and mechanical conditions.
1.8
American University Cx Plan
Functional Performance Test Page 1 of 3 F5 FPT ATS.xls
EXAMPLE
CLOSED TRANSITION AUTOMATIC TRANSFER SWITCH
W ISOLATION BYPASS
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
ELECTRICAL INTEGRITY
2.1
Measure contact resistance on all poles in all closed
positions (Normal, Emergency, Bypass to Normal, Bypass to
Emergency)
aReadings are within 50% of the average value,
including the neutral pole.Pass?
2.2
Perform an insulation resistance test at 500VDC (or at test
voltage per mfgr recommendations) on each bus section,
phase-to-phase and phase to ground.
aMinimum insulation resistance shall be 100
megohms.Pass?
2.3
Perform insulation resistance test at 500 VDC (or at test
voltage per mfgr recommendations) to verify Automatic
Transfer Switch is isolated from load when bypassed.
aInsulation resistance shall equal or exceed 100
Megohms.Pass?
a All data displays operate. Pass?
b All program parameters accessible. Pass?
2.5 Verify “In Phase Monitoring” setting. a In phase monitoring is enabled/disabled. Pass?
a Use ATS microprocessor control system. Pass?
b Device pick-up (PU) and drop-out (DO). Pass?
a NORMAL power available Pass?
b EMERGENCY power avail. Pass?
c ATS in NORMAL position. Pass?
d ATS in EMERGENCY position. Pass?
e LED indicating lights are operating Pass?
f Test light button operational Pass?
g Bypass Switch Bypassed to Normal Pass?
h Bypass Switch Bypassed to Emergency Pass?
i ATS Connected Pass?
j ATS in Test Position Pass?
k ATS Isolated Pass?
2.8 Verify proper phase rotation a Emergency source matches utility source. Pass?
TRANSFER OPERATION TESTS
a Time delay on engine start equals setpoint. Pass?
b Start signal sent to engine generator. Pass?
c Transfer time delay equals setpoint. Pass?
d ATS transfers to Emergency source position. Pass?
eTotal time to connect to Emergency source is no
more than ____ - secondsPass?
a Re-transfer time delay equals setpoint. Pass?
b ATS transfers to Normal source position. Pass?
cClosed transition switching (if applicable) occurs.
No loss to load detected as applicablePass?
d Engine cool down time delay equals setpoint. Pass?
e Engine shuts off after cool down delay times out. Pass?
a Time delay on engine start equals setpoint. Pass?
b Start signal sent to engine generator. Pass?
c Transfer time delay equals set point. Pass?
d ATS transfers to Emergency source position. Pass?
a Re-transfer time delay equals setpoint. Pass?
b ATS transfers to Normal source position. Pass?
cClosed transition (if applicable) switching occurs.
No loss to load detected as applicablePass?
d Engine cool down time delay equals setpoint. Pass?
e Engine shuts off after cool down delay times out. Pass?
3.5
Repeat steps 3.1 and 3.2 except manually disconnect
EMERGENCY source, to simulate failure of the engine, after
restoration of NORMAL power and before the re-transfer
delay has expired.
a
Switch should re-transfer (closed transition if
applicable) to Normal without delay on engine
shutdown.
Pass?
3.6 Verify operation of ATS TEST switch. a Simulates failure of normal source. Pass?
3.7 Confirm closed transition. a No interruption to the load during closed transition. Pass?
Verify all voltage, frequency, and time delay settings.
2.4Verify the operation of four-line LCD display and character
keyboard.
3.2Restore Normal power source to Automatic Transfer Switch to
verify setpoints.
Disconnect NORMAL power source to transfer switch.
2.6
Restore each phase (Normal) voltage to Automatic Transfer
Switch to verify setpoints.3.4
2.7Verify all applicable local and remote annunciation by the
monitoring system for various operating conditions.
3.1
3.3Simulate loss of phase to ground voltage for each phase of
the NORMAL source.
American University Cx Plan
Functional Performance Test Page 2 of 3 F5 FPT ATS.xls
EXAMPLE
CLOSED TRANSITION AUTOMATIC TRANSFER SWITCH
W ISOLATION BYPASS
FUNCTIONAL PERFORMANCE TEST
Action Expected Result Status Comments Notes/Reference Initial Date
EXTENDED PARALLEL/SHUNT TRIP
a Normal circuit breaker feeding the ATS shunt trips. Pass?
bGenerator continues to serve the load (no
interruption to load)Pass?
4.2Attempt to reset the ATS feeder circuit breaker without re-
setting the lock out relay.a ATS normal Circuit breaker will not reset, Pass?
4.3 Reset the lock out relay and reset the normal circuit breaker. a ATS normal Circuit breaker resets. Pass?
4.4Confirm that ATS transfers back to Normal source by closed
transitiona
No interruption to the load during closed transition
back to normal sourcePass?
BYPASS AND ISOLATION SWITCH OPERATION
5.1
Verify Automatic Transfer Switch manual bypass (to Normal
and Emergency sources) and isolation switch operation with
NORMAL source energized and load on ATS.
aATS mechanism is de-energized and power passes
through the bypass/isolation switch path.Pass?
5.2
Restore the Automatic Transfer Switch to its automatic mode
by manually reversing the bypass and isolation switch
operation.
aATS mechanism is energized and the
bypass/isolation switch path is de-energized.Pass?
ATS REMOTE ANNUNCIATOR
6.1 Verify installation of remote annunciator. aDisplay mounted at reasonable height. (easily
viewable from the floor)Pass?
6.2 Verify interface to each transfer switch. a Correct status of each transfer switch is displayed. Pass?
FINAL INSPECTION
7.1
After testing is performed on the ATS, verify tightness of field
landed feeder terminations (NORMAL, EMERGENCY, and
LOAD feeders).
aFeeder cable connections properly torque and
marked.Pass?
7.2Prior to energization, inspect interior hardware and electrical
terminations.a
Prior to energization, inspect interior hardware and
electrical terminations.Pass?
General Notes
1
2
3
4
5
4.1Simulate an extended parallel between the normal (utility)
and emergency source.
American University Cx Plan
Functional Performance Test Page 3 of 3 F5 FPT ATS.xls
Recommended