ACPS New South Wales February Meeting · 2018. 3. 20. · ACPS New South Wales February Meeting...

Preview:

Citation preview

ACPS New South Wales February MeetingFebruary 15, 2012 – New South Wales, Australia

Peabody Energy Australia Wilpinjong CHPP Expansion Project

Challenges and Successes

Safety Contact

Meeting Agenda

Project Introduction

Project Introduction – Production Objectives

Project Introduction – FEED and Contract Strategy

Project Introduction – Process Objectives

Process Design – Coal Handling Plant

Coal Handling Plant – Objectives

Coal Handling Plant – Process Flow Diagram

Coal Handling Plant – Process Flow Diagram – Raw Coal Handling

New ROM

Bin

CV-104

Raw Coal

Conveyor

New Sizing

Station

New Raw

Coal

Stacking

Conveyor

Existing

Radial

Stacker

Coal Handling Plant – Process Flow Diagram – Product Handling

Clean Coal Stacker CV-606Clean Coal Stacker CV-606

CV-605 Drive TowerCV-605 Drive Tower

New Reclaim Conveyor CV-802 connects to existing TLO

New Reclaim Conveyor CV-802 connects to existing TLO

Coal Handling Plant – Interface Point Challenges

New Stationary Tripper installed on existing Product Conveyor diverts washed coal to new Product Stockpile

New Stationary Tripper installed on existing Product Conveyor diverts washed coal to new Product Stockpile

New Conveyor CV-605New Conveyor CV-605

Existing Product Stacker CV-602Existing Product Stacker CV-602

Existing Product Conveyor CV-601Existing Product Conveyor CV-601

New Tripper HeadNew Tripper Head

Process Design – Coal Preparation Plant

CPP Expansion under construction (September 2011)

Coal Preparation Plant – Process Objectives

New

Spirals

Circuit

Expansion

Coal Preparation Plant – Major Process Decisions

Coal Preparation Plant – Process Flow Diagram

Coal Preparation Plant – Other Process Considerations

Field modify existing thickener with external launder to increase capacity

Field modify existing thickener with external launder to increase capacity

New higher capacity and re-designed centerwellNew higher capacity and re-designed centerwell

Coal Preparation Plant – Other Process Considerations

New D&R screens with large fixed sieve panelsNew D&R screens with large fixed sieve panels

Commissioning Performance

First train loading operations from new product stockpile (November 2011)

Commissioning Performance – Key Results

Commissioning Performance – Key Results

99

95

90

80

70

60

50

40

30

20

15

108

6

4

2

1

0.01 0.1 1 10 100

% P

ass

ing

Size (mm)

Rosin Rammler

Nominal Plant Feed

Coarsest Plant Feed

Finest Plant Feed

Initial Sizing

After Wet Tumble

Plant performance test sample aligned with nominal design size distribution

Plant performance test sample aligned with nominal design size distribution

Wet tumble of plant feed was within finest design envelope limits

Wet tumble of plant feed was within finest design envelope limits

Commissioning Performance – Coarse DMC Performance

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30

Par

titi

on

Nu

mb

er

(To

Pro

du

ct)

Specific Gravity

Coarse Dense Medium Cyclone (Plus 14 mm)

Actual

Guaranteed (Whitten)

Actual (Whitten)

Commissioning Performance – Fine DMC Performance

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30

Pa

rtit

ion

Nu

mb

er

(To

Pro

du

ct)

Specific Gravity

Fine Dense Medium Cyclone (14 mm x 4 mm)

Actual

Guaranteed (Whitten)

Actual (Whitten)

Commissioning Performance – Fine DMC Performance

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30

Pa

rtit

ion

Nu

mb

er

(To

Pro

du

ct)

Specific Gravity

Fine Dense Medium Cyclone (4 mm x 1 mm)

Actual

Guaranteed (Whitten)

Actual (Whitten)

Commissioning Performance – Spirals Performance

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

90.0

100.0

1.20 1.30 1.40 1.50 1.60 1.70 1.80 1.90 2.00 2.10 2.20 2.30

Pa

rtit

ion

Nu

mb

er

(To

Pro

du

ct)

Specific Gravity

Spirals (1.0 mm x 0.10 mm)

Actual

Guaranteed (Whitten)

Actual (Whitten)

Project Implementation – Other Capital Cost Considerations

Reclaim CV-202 from new Raw Coal stockpile onto existing Plant Feed Conveyor CV-201

Project Implementation – Other Capital Cost Considerations

Capital Cost Considerations – Imported Fabrication

Pre-assembly of new ROM bin in Tianjin before blasting and painting

Pre-assembly of new ROM bin in Tianjin before blasting and painting

Capital Cost Considerations – Lower Cost Engineering

Relocated sample system as part of new fixed tripper assembly on CV-601

Relocated sample system as part of new fixed tripper assembly on CV-601

Lessons Learned

CPP addition after enclosure November 2011

New CPP addition in September 2011

Lessons Learned – Procurement and Fabrication

New CPP addition in September 2011

Lessons Learned – Process Design and Engineering

New CPP addition in September 2011

Lessons Learned – Change Management

Conclusion

The Wilpinjong expansion project proved to be a successful cooperation between Peabody and Ausenco Taggart having met the Owner’s objectives for Safety performance, Process guarantees, Completion Schedule, and Capital costs.

Completed CPP Expansion with new CV-605 in the foreground (December 2011)

ACPS New South Wales February MeetingFebruary 15, 2012 – New South Wales, Australia

Recommended