Presentation Outline

MTO Roadwork Scheduling and Coordination Unit (RWSCU)

� Responsibilities

� Process

� Workload

� Past Systems

Roadwork Scheduling System (RSS)

� Objectives

� Challenges

� Expected Benefits

� Architecture

� Agile Delivery Process

� Walkthrough

� Deployment Plan

Questions

MTO Roadwork Scheduling and Coordination Unit (RWSCU)

Roadwork Scheduling System (RSS)

MTO RWSCU:Responsibilities

� Responsible for managing work on Ontario roadways

� Roadwork may be for construction, engineering

investigation, maintenance, moving maintenance, special

events

� Priorities:� Priorities:

� Maintain knowledge of current and planned roadwork

� Maintain separation by time and space

� Prioritize emergency work

� Verify contract provisions are being met

� Monitor execution

� Disseminate information to the public

3

Responsible for managing work on Ontario roadways

Roadwork may be for construction, engineering

investigation, maintenance, moving maintenance, special

Maintain knowledge of current and planned roadwork

Maintain separation by time and space

Verify contract provisions are being met

Disseminate information to the public

MTO RWSCU:Process

4

MTO RWSCU:Workload

� In 2011

� ~100 contractors

� ~700 active roadwork contracts

� ~13,500 roadwork notifications

� Peaks during construction � Peaks during construction

season

5

~700 active roadwork contracts

~13,500 roadwork notifications

MTO RWSCU:Past Systems

� 2003 - In-House Oracle Forms Application

� 2008 - Next-Generation Compass Software

� Primary function of past systems was to maintain a

database of approved notifications for web publication

and performance monitoringand performance monitoring

� Placed a heavy burden on RWSCU staff to:

� ensure the correctness of the submitted notifications

� check for conformance with contract provisions

� identify and resolve conflicts with nearby closures

� perform data entry

6

House Oracle Forms Application

Generation Compass Software

Primary function of past systems was to maintain a

database of approved notifications for web publication

and performance monitoringand performance monitoring

Placed a heavy burden on RWSCU staff to:

ensure the correctness of the submitted notifications

check for conformance with contract provisions

identify and resolve conflicts with nearby closures

RSS:Objectives

� In 2011, MTO tendered a consultant assignment to

implement RSS

� Latest information technologies

� Operated by consultant as a service

� Runs in a “cloud” computing environment

� Accessible on the Internet

� Address process inefficiencies

� User-driven with online tracking

� Assignment was awarded to

� Completed as a joint effort between

7

In 2011, MTO tendered a consultant assignment to

Latest information technologies

Operated by consultant as a service

Runs in a “cloud” computing environment

Address process inefficiencies

driven with online tracking

Assignment was awarded to Delcan

Completed as a joint effort between Delcan and MTO

RSS:Challenges

� Short development timeframe

� Complex workflow and requirements

� Multiple stakeholders (MTO RWSCU, MTO Systems

Group, Contractors)

� Multiple cloud computing options� Multiple cloud computing options

� Securing the application on the internet

� Integration with existing MTO systems

8

Short development timeframe

Complex workflow and requirements

Multiple stakeholders (MTO RWSCU, MTO Systems

Multiple cloud computing optionsMultiple cloud computing options

Securing the application on the internet

Integration with existing MTO systems

RSS:Expected Benefits

Feature

Online entry, validation, and conflict

checking

User-driven approach

9

Online status tracking and automated e-

mails

Online storage and access to related

communications and materials

Benefit

Reduces rejection and resubmission

Reduces RWSCU data entry and results

in faster approval and earlier publication

of planned roadworkof planned roadwork

Enables contractors to stay informed

Simplifies administration

RSS:Architecture

� Secure publicly accessible website

� Runs in a “cloud” computing environment

� Offsite facility

� Virtual Server technology

� Very high CPU and network availability� Very high CPU and network availability

� Extensive security measures

� Administered by Delcan as a service

� MTO has full operational control of the system without

having to dedicate IT resources or equipment

� Web services integration with the existing NGCS ATMS

and TRIP

10

Secure publicly accessible website

Runs in a “cloud” computing environment

Very high CPU and network availabilityVery high CPU and network availability

as a service

MTO has full operational control of the system without

having to dedicate IT resources or equipment

Web services integration with the existing NGCS ATMS

RSS:Architecture

11

RSSArchitecture

� MTO Traveller’s Road Information Portal (TRIP)

12

Road Information Portal (TRIP)

RSS:Agile Delivery Process

� Prototype developed in close consultation with

stakeholders

� Software broken down into functional packages

� Packages incrementally delivered, reviewed,

adapted to ensure good fit stakeholder needsadapted to ensure good fit stakeholder needs

13

Prototype developed in close consultation with

Software broken down into functional packages

Packages incrementally delivered, reviewed, and

ensure good fit stakeholder needsensure good fit stakeholder needs

RSS:Walkthrough

Contractor self-registers

14

Contractor enters contract

information

RSS:Walkthrough

Contractor enters notification by completing the sentences

1.

15

Contractor enters notification by completing the sentences

1. Basic Information

2. Primary Closure

3. Additional

ImpactsImpacts

RSS:Walkthrough

Occurrences and staging

16

RSS:Walkthrough

Contractor performs conflict check

17

Contractor performs conflict check

RSS:Walkthrough

Contractor reviews

18

RSS:Walkthrough

Contractor submits

19

RSS:Walkthrough

Notification approval process

20

RSS:Walkthrough

� Email log

Online record of communications and related materials

� Attachments

21

Online record of communications and related materials

RSS:Deployment Plan

� Side-by-side with existing process until end of 2012

� Contractor training

� Help Desk and Issue tracking

� Outreach to other MTO regions

22

side with existing process until end of 2012

Help Desk and Issue tracking

Outreach to other MTO regions

Other Delcan Roadwork Information Systems

� QMost

� Web-enabled requirements management

highway construction and rehabilitation projects

� Construction requirements management, requirement

verification, performance monitoring and final acceptance

� iMove

23

� iMove

� Traveller information portal for disseminating information to the

public

� Provides multi-modal, multi-jurisdiction, real

traveller information via the World Wide Web

Roadwork Information Systems

requirements management application for

highway construction and rehabilitation projects

Construction requirements management, requirement

verification, performance monitoring and final acceptance

information portal for disseminating information to the

jurisdiction, real-time and static

traveller information via the World Wide Web

Questions?

Mark Conrad, Senior Systems Engineer

Delcan Corporation

Tel: 905-943-0524

E-mail: m.conrad@delcan.com

Hoi Wong, Senior Systems Engineer

Ontario Ministry of Transportation

Tel: 416-235-5614

E-mail: h.wong@ontario.ca

Mark Conrad, Senior Systems Engineer

m.conrad@delcan.com

Hoi Wong, Senior Systems Engineer

Ontario Ministry of Transportation

Recommended