6th DIVISIONAL
DEVELOPMENT REVIEW SESSION
District Ambala
Priority Items
1. Public Works (B&R)Agenda Items Departmental Comments DC RemarksConstruction of H.L. Bridge over Sadhaura nadi on Shahbad from Barara - Kala Amb to Village Sahila.
Earlier for this purpose an estimate amounting to Rs.450 lacs was prepared by the PWD B&R department but the amount was not sanctioned by the govt and in the meantime the temporary arrangement has been made by the Panchayat Department from NREGS with an expenditure of Rs.35 lacs.
Department submitted the report that DDRS approval for the project was not received but in the meantime arrangement has been made by the Panchayat department from NREGS.Work has been completed and CC Road work is under progress for which an amount of Rs.15. lacs are to be obtained from NREGS to complete the CC Road work.
2. Public Works (B&R).
Agenda Items Departmental Comments DC RemarksConstruction of H.L. Bridge over Markanda Nadi from village Haryouli to Tandwal.Brief: Construction of H.L. Bridge over Markanda Nadi from village Haryouli to TandwalDC reports that- Bridge over Markanda Nadi from Village Haryouli to Tandwal is required.The approximate cost of this bridge will be Rs.1000.00 lacs.
Construction of H.L. Bridge over Markanda Nadi from village Haryouli to Tandwal.Brief: Construction of H.L. Bridge over Markanda Nadi from village Haryouli to TandwalDC reports that- Bridge over Markanda Nadi from Village Haryouli to Tandwal is required.The approximate cost of this bridge will be Rs.1000.00 lacs.
Department submitted the report that DDRS approval for the project is required for further action in this matter.
3. Uttar Haryana Bijli Vitran Nigam
Agenda Items Departmental Comments DC RemarksSet up 66 KV Sub Station at Hissar Road for the upcoming industrial growth.
1. As per report received from Executive Engineer, Op.Div., Ambala City, new colonies are coming up. Presently this area is being fed from 66KV Sub station at Layalpur Basti , Sonda, and Chaurmastpur. -all far away from this area,therefore resulting in frequent tripping/breakdown. Due to this very reason Nigam is neither able to cater quality supply to the area nor able to meet out the future demand of the area.
2. In view of the above it is proposed that a 66KV sub station be created at Hissar Road/village Balana with a installed capacity of one No. 10/12.5 MVA, 66/11 KV transformer so as to meet out the future load growth as well as to cater better quality of supply to the area. The required 66KV sub line will be tapped from nearby Tepla-sonda Line which is at a distance of approximately 7.0Km from proposed site. The approximate cost of the project is Rs.400.00 lacs subject to the availability of land free of cost.
Deptt. Submitted the report that this project is not feasible due to non availability of required land. However, the existing 66 KV sub station at saddopur, sonda and Layalpur Basti are being augmented to meet out the demand of industrial as well as other load growth.
4. Public Works (B&R)
Agenda Items Departmental Comments
DC Remarks
Construction of Mini Sectt. (IIIrd Phase) at Ambala is urgently required.
. Construction of Mini Sectt. (IIIrd Phase) at Ambala is urgently required.
Department Submitted the report that DDRS approval for the project is yet to be received by the govt.
5. Public Works (B&R)
Agenda Items Departmental Comments DC RemarksAdditional bridge on Tangri River.
For the Construction of Additional bridge on Tangri River,an estimate for Rs.750 lacs was prepared and the work was started on 01.11.2007 and completed on 30.09.2008. Total expenditure incurred was Rs.750 lacs
Work completed.
6. Public Works (B&R).
Agenda Items Departmental Comments
DC Remarks
Beautification of Flyovers.
Commissioner PWD B&R has informed that Deputy Commissioner may submit a specific proposal in this regard which would be taken up with NHAI
SDO © submitted a proposal that shops/rehris along the boundary of Railway Station may be shifted in the open space beneath the fly over. It may help in free flow of public transport/general traffic. Efforts are being made to shift the rehries/shops along the boundary of railway station and re-located at an open space. For this purpose sites are being inspected. In regard to the beautification of Fly over near Central Jail in Ambala NHAI reported that the project of 6 laning of NH is under consideration. In regard to above it is proposed that plantation will definitely help in beautification of the flyover near central jail in Ambala city.
7. Revenue
Agenda Items Departmental Comments
DC Remarks
Conversion of Leasehold land tenure into freehold in Ambala Sadar
A five member committee under the Chairmanship of FC & PS to Govt. Haryana Revenue Department was constituted by the Govt. on 23.11.2006 .Report awaited.
Matter is under consideration with the Government
8. Irrigation Deptt.
Agenda Items Departmental Comments DC RemarksNaggal Lift Irrigation Scheme. (Kanwala Distributory )
KANWALA DISTRIBUTARY
To operationalize 1st stage i.e. kanwala distributory system of NLIS, its rehabilitation is required. The capacity of kanwala distibutory is also to be increased to supply 30 Cs. Canal Water to HUDA for drinking purposes. Earlier the rehabilitation could not be done due to the reason that 20 Cs. Supply to MES Ambala Cantt is being given regularly.Due to inadequate storage capacity of tanks of these departments, the closure could not be arranged earlier.
Deptt submitted the report that approval of NABARD authority is awaited. The rehabilitation of naggal lift irrigartion scheme will be taken up after the approval of project by NABARD.Share money is also awaited from HUDA.
9. H.S.A.M.B.
Agenda Items Departmental Comments DC RemarksProposal for shifting of Anaj/Chara Manadi from inner area to outside in A/Cantt.
CA HSAMB informed that Section 6 notification has been issued regarding shifting of Anaj Mandi Sabji Mandi/Chara Mandi from inner area to outside from A/Cantt. The matter is under litigation as the Hon’ble Punjab & Haryana High court has passed stay orders on this land.
shifting of Anaj/Chara Manadi from inner area to outside in A/Cantt. is under process
10. H.S.A.M.B.
Agenda Items Departmental Comments DC RemarksShifting of Sabji Mandi from inner Areas to outside in Ambala City.
CA HSAMB informs that 25A-3K-13M land has been acquired on G.T. Road for the establishment of New Sabji Mandi. Market committee has made the payment of 3.27 cr. through LAC Ambala towards cost of the land. The HSAMB has granted administrative approval amounting Rs. 5.89 cr. for the development of the Mandi. The Work is under progress and Likely to be Completed by 31-05-2010
Shifting of Sabji Mandi from inner Areas to outside in Ambala City is under process
Regular Agenda Items
(A) Implementation of Development Activities
• 12th Finance Commission Grants
• 2nd State Finance Commission Grants
• LADT
Year Works /projects
Estimated Cost
Amount Sanctioned/ Released
Expenditure/Financial progress
Physical progress Remarks
< 50% > 50 %
2008-2009(Rural)
2009-2010(Rural)
2009-2010(B & R)
951
860
1
370.00
176.57
815-88
370.00
176.57
815-88
370.00
68.40
-
-
40%
Yes
100%
-
-
Completed
210 comle.650 in prog.
Work in progress
(A) Implementation of Development Activities
i) 12th Finance Commission Grants
Year Works /projects
Estimated Cost
Amount Sanctioned/ Released
Expenditure/Financial progress
Physical progress
Remarks
< 50% > 50 %
2007-2008
2008-2009
603
-
228.00
-
228.00
-
228.00
-
-
-
100%
-
Completed
No funds received during 2008-2009 and 2009-2010
(A) Implementation of Development Activities
ii) 2nd Finance Commission Grants
Year Works /projects
Estimated Cost
Amount Sanctioned/ Released
Expenditure/Financial progress
Physical progress
Remarks
< 50% > 50 %
2005-2006(Rural)
2008-2009(CC streets)
2008-2009(Roads)
2009-2010(Roads)
46
72
26
30
532.00
720.00
430.00
631.00
532.00
720.00
430.00
631.00
519.11
715.78
430.00
542.84
-
-
-
-
100%
100%
100%
85%
No funds received during 2008-2009 and 2009-2010
No funds received during 2008-2009 and 2009-2010
Completed
24 Completed6 in Progress
(A) Implementation of Development Activities
iii) LADT
(B) Rural Development Programmes Programme Funds
AvailableExp. Upto 31-10-09
%age Physical Achievement
NREGA 1000.484 666.387 66.6% Total 537 works undertaken out of which 172 works completed. Employment provided to 6256 Household. Total 29620 Household registered in this scheme.
Swaran Jayanti Gram Swarojgar Yojna(SGSY)
93.38 57.30 61%Job provided to 165 Swarojgaaaaris
Indira Awas Yojna(IAY)
208.901 166.60 99.9% Total Houses :812 Complete: 0In Progress:812
MPLAD (2008-09)
196.30 143.35 73.3% Complete:73 In Total works:109 Prog.: 36Works not started: 0(The funds of 2009-10 has not been received yet)
Haryali 5.50 0 0 Funds released to PIA/ Watershed committee/ Panchayats. Case for 2nd installment sent to Govt..
Total Sanitation Campaign(TSC)
533.18 493.04 92.5% Total toilets for BPL constructed : 19010School toilets: 284Aanganwadi toilets: 570Women sanitation complex: 65
H.R.D.F05-0606-0707-0808-0909-10
414.42406.88387.96922.87 48.75
412.15395.72384.75515.16 12.15
99%97%99%55%24%
Total comp. In Prog not started214 212 0 2 (site dispute)150 150 0 0 99 99 0 0 325 43 282 0(funds recd.in02/09) 45 2 43
Women Chopal.-Phase I (08-09)Phase II (09-10)
222.00 108.00
213.00 38.60
96% 36%
74 66 8 36 7 29
(C) Beautification & Improvements in Urban Surroundings
H.S.A.M.B(Ambala) Construction of Link Roads
Total No. of roads Length in (K.M.) Esti.cost No. of roads compl.
In Progress Not started Physical in Prog.
Exp.as on 31.10.09
(in K.M.)
Phase-I 13.23 60 6 0 0 13.23 61.66
Phase-II 19.51 78.32 10 0 0 19.51 76.4
Phase III & IV 8.67 43.18 4 0 0 8.67 38.03
Phase-V 32.49 198.77 11 4 0 22.43 178.9
Phase-VI 19.44 181.37 9 1 0 15.37 108.59
Phase-VII 52.05 507.07 0 0 0 0 0
(D) Infrastructure Development project
IRRIGATION DEPARTMENT
State Plan/Flood Works
S.N Year Total No. of Works
Works compl.
In Prog
Works not started
Total funds available
Exp. Upoto 31.10.09
% of exp.
Remarks
1. 06-07 9 9 0 0 389.15 90.74 23% Less exp. Due to drop of scheme
2. 07-08 13 5 3 4 675.64 161.86
24% Work not started due to land acquisition under process.
3. 08-09 8 4 3 1 4433.54
2636.74
60% Work not started due to land acquisition under process.
(D) Infrastructure Development project
Under Head AIBP.
S.N Year Total No. of Works
Works compl
In Progress
Works not started
Total funds available
Exp. Upto 31.10.09
% of exp.
Remarks
1. 06-07 3 2 0 1 160.50 135.00
84 Work not
started due
to drop
of scheme from AIBP
(D) Infrastructure Development project
P.W.D.(Water Supply & Sanitation)Rural Water Supply
S.No. Name of Head Total Funds available
Exp. Upto 31.10.09
% age of exp.
Total Works
Works compl.
In Progress
1. Agumentation State Plan
618.18 648.78 105% 65 63 0
2 Addl.Central Assistance
350.28 431.89 124% 32 32 0
3 ARWSP 1591.45 1573.02 99% 158 151 7
4 NABARD 538.66 536.59 100% 17 17 0
5 Harijan Basti 95.38 95.38 100% 20 20 0
Rural IGDWS
6 Infrastucture Development
249.30 539.76 216% 36 31 5
7 Pvt.Sc Connection
1309.60 964.69 74% 35422 30200 5222
(D) Infrastructure Development project
Rural Water Supply
Urban IGDWS
8 Pvt.Sc Connection Ambala City
155.01 105.03 68% 8409 4156 4253
Urban Water Supply
9 Ambala City 913.40 871.43 96% 5 3 2
10 Ambala Sadar 326.15 23.59 7% 6 4 2
Urban ACA
11 Ambala Sadar 2224.93 2491.44 112% 1 0 1
S.No. Name of Head Total Funds available
Exp. Upto 31.10.09
% age of exp.
Total Works
Works compl.
In Progress
(D) Infrastructure Development project
Urban Sewerage
12 Ambala City 1988.77 1570.76 79% 4 0 4
13 Ambala Cantt 170.42 60.34 36% 3 0 3
Drainage
14 Ambala City 278.81 212.44 76% 6 4 2
Grand Total 10810.34 10125.14 94% 44184 34681 9501
Rural Water SupplyS.No. Name of Head Total
Funds available
Exp. Upto 31.10.09
% age of exp.
Total Works
Works compl.
In Progress
(D) Infrastructure Development project
(E) Gaps in existing infrastructure
Transformers(nos.)
11KV lins (in Kms.)
L/T lines (in Kms)
Connection Category-wise(Numbers)
Domst Comm L.T. Indust
T/Wel PWW
Existing8318
2334 3890 145981 31274 3009 13852 612
Total requirement
8561 2357 3929 146481 31674 3049 14252 637
Gap243 23 39 500 400 40 400 25
Funds Required(Rs. In lac)
195.00 46.00 68.00 10.00 15.00 80.00 500.00 38.00
(F) CM ANNOUNCEMENTSDepartment Dropped Commissioned In
ProgressNot
FeasiblePending Total
District Administration 0 6 0 0 1 7
Education 1 16 1 13 0 31
Animal Husbandry 0 13 0 5 0 18
Forest 0 1 0 0 0 1
Health 0 1 2 2 0 5
Public Health 0 0 1 0 0 1
HUDA 0 0 1 1 2 4
Industries 0 1 1 0 0 2
Irrigation 2 4 2 0 0 8
Urban Local Bodies 0 0 1 0 0 1
Development Deptt. 0 6 2 0 0 8
Marketing Board 0 18 1 3 1 23
PWD B&R 0 4 5 6 0 15
Sports 0 8 0 4 0 12
UHBVN 1 3 1 0 0 5
Social Welfare 0 1 0 0 0 1
Roadways 0 1 0 0 1 2
Total 4 83 18 34 5 144
C.M. Announcements Pending with H.Q.
Sr. No.
Department Officer at District Level
Name of Work Remarks
1 Treasury & Accounts
Treasury Officer Opening of Sub. Treasury at Shahzadpur
Proposal submitted to the Director, Treasury & Accounts, Haryana, Chandigarh.
2 HUDA Estate Officer HUDA Const. of Parsu Ram Park in Sector-8, Ambala City
Layout Plan of Sector-23 submitted to Admn. HUDA PKL.
3 HUDA Estate Officer HUDA Const. of Parsu Ram Bhawan in Ambala City
Submitted to C.A. HUDA
4 HSAMB Xen, HSAMB Const. of Kisan Rest House at Shahzadpur Anaj Mandi
Approval awaited from H.Q.
5 Transport G.M. Roadways Const. of Bus Stand in Vill. Mullana
No. Objection awaited from Executive Engineer NH-73, PKL.
C.M. Announcements Dropped
Sr. No
Department Officer at District Level
Name of Work Remarks
1 Tech. Edu. Dir. Tech. Edu. Opening of Technical Institution
Does not Fulfill the Norms
2 Irrigation SE Irrigation Const. of Canal from Tajewala to Mohra via Nahoni
Dropped in the meeting under Chairmanship of PSCM
3 Irrigation SE Irrigation Const. of Canal from Hathni Kund for Naraingarh Area
The Clearance of this project is being pursued in CWC.
4 UHBVN SE, UHBVN Const. of 66 KV Power Sub Station in Vill. Ugala & Dheen
In Vill. Ugala Work in Progress & Sub. Satation at Vill. Dheen is not technically justified
C.M. Announcements Works in Progress
Sr. No.
Department
Officer at District Level
Name of Work Estimated Cost (Rs. In Lakh)
Expenditure (Rs. In Lakh)
Status
1 Industrial Training
Principal ITI
Const. of ITI for Naraingarh
997.95 Approval received, funds awaited
2 Health CMO Const. of Primary Health Centre in Vill. Boh-Babyal
207.22 46.03 45% work completed
3 Health CMO Establishment of Primary Helath Centre in Vill. Kesri
207.27 101.33 40% work completed and likely to be completed by 17.12.2009
4 P.W.D. (Public Health)
Xen, PH Providing Sewerage System in Ambala City
4937.47 1153.52 100% sewer has been laid Const. of STP in progress.
5 HUDA Estate Officer
Const. of Rajeev Gandhi Sports Stadium in HUDA, Sector-10
102.50 47.20 30% work completed
6 Industries G.M. DIC Setup SEX in Ambala City 195000.00 Action is being taken by M/s. DLF Pvt. Ltd. for purchasing the land.
7 Irrigation SE, Irrigation
Const. of Mansoorpur lift Irrigation Scheme
860.64 211.97 40% work completed
8 Irrigation SE, Irrigation
Drainage of Water for village Barara
10.46 In Progress
9 H.R.D.F. Xen, PR Development works in Fifteen Villages
Likely to be comp. by 31-03-2010
C.M. Announcements Works in ProgressSr. No.
Department Officer at District Level
Name of Work Estimated Cost (Rs. In Lakh)
Expenditure (Rs. In Lakh)
Status
10 H.R.D.F. Xen, PR
Shahzadpur & Shahzadpur Majra to be declared as Model Village
10% Completed Likely to be completed by 31-03-2010
11 Urban Local Bodies
Secy. M.C., N/Garh
Repair of Main Road of Market
64.64 In Progress
12 H.S.A.M.B. Xen, HSAMB
Opening of Collection Centre in Karasan Anaj Mandi
25.97 2.26 50% work Completed progress slow due to standing trees
13 PWD B&R XEN, B&R
Link road from Binjalpur to Zafferpur
30.00 20.00 80% work completed likely to be completed by 31-12-2009
14 PWD B&R XEN, B&R
Const. of Bridge over Shahzadpur River & Khanpur Brahaman river
226.09 174.00 Bridge Completed. Approaches 90% completed.
15 PWD B&R XEN, B&R
Link Road from Paplotha to Mullana upto Markanda River
69.00 52.20 80% work completed likely to be completed by 31-12-2009
16 PWD B&R XEN, B&R
Const. of New Road from Rajouli to Sarakpur
45.00 36.00 80% work completed likely to be completed by 31-12-2009
17 PWD B&R XEN, B&R
Link Road from Zaffapur to Jagdholi Road
56.50 45.20 80% work completed likely to be completed by 31-12-2009
18 HVPN SE, HBVN
Const. of 66 KV sub station in village Ugala and Dheen
In Vill. Ugala Work in Progress & Sub. Satation at Vill. Dheen is not technically justified
C.M. Announcements (Not Feasible)Sr. No.
Department Officer at District Level
Name of Work Status
1 Education (School) DEO Up-gradation of School in Vill. Batrohan from Middle to High
Does not fulfill the norms
2 Education (School) DEO Up-gradation of School in Vill. Barola from Middle to High
Does not fulfill the norms
3 Education (School) DEO Up-gradation of School in Vill. Chaurmastpur from High to Senior Secondary
Does not fulfill the norms
4 Education (School) DEO Up-gradation of School in Vill. Tharwa from High to Senior Secondary
Does not fulfill the norms
5 Education (School) DEO Up-gradation of School in Vill. Baknour from High to Senior Secondary
Does not fulfill the norms
6 Education (Higher) DHE, Chd. Const. of Govt. College for Girls Does not fulfill the norms
7 Education (Higher) DHE, Chd. Opening Govt. Girls College in Shahzadpur Does not fulfill the norms
8 Education (Primary) DEPO Up-gradation of School in Vill. Jodhpur from Primary to Middle
Does not fulfill the norms
9 Education (Primary) DEPO Up-gradation of School in Vill. Khojkipur from Primary to Middle
Does not fulfill the norms
10 Education (Primary) DEPO Up-gradation of School in Vill. Neharsi from Primary to Middle
Does not fulfill the norms
11 Education (Primary) DEPO Up-gradation of School in Vill. Ghasitpur from Primary to Middle
Does not fulfill the norms
12 Education (Primary) DEPO Up-gradation of School in Vill. Malwa from Primary to Middle
Does not fulfill the norms
C.M. Announcements Not FeasibleSr. No.
Department
Officer at District Level
Name of Work Status
13 Education (Primary)
DEPO Up-gradation of School in Vill. Jandheri from Primary to Middle
Does not fulfill the norms
14 Animal Husbandry
DD , ICDP Repair of Vet. Hosptial in Vill. Khudda Khurd
No. Govt. Institution exists in the Village
15 Animal Husbandry
DD , ICDP Shifting of animal hospital to main bazaar to anaj mandi
Not Feasible as approved by Hon’ble CM
16 Animal Husbandry
DD , ICDP Opening of Vety. Dispensary in Vill. Binjalpur
Live stock and human population is not as per norm
17 Animal Husbandry
DD , ICDP Opening of Vety. Dispensary in Vill. Nagla Jattan
Live stock and human population is not as per norm
18 Animal Husbandry
DD , ICDP Opening of Vety. Dispensary in Vill. Rajokheri
Live stock and human population is not as per norm
19 Health CMO Up-gradation of PHC to CHC in Barara Village
Population less than the National Helath Policy Norms
20 Health CMO Establishment of Health Dispensary in Vill. Gokulgarh
Population less than the National Helath Policy Norms
21 Town & Country Planning
Estate Officer Const. of Stadium in New HUDA Sector, Naraingarh
Due to Non availability of land
22 H.S.A.M.B. Xen, HSAMB Const. of Road Ugala , Buhawa Road to Deep Singh Dera
Due to Less consolidation path (Path is only 3 Karam)
23 H.S.A.M.B. Xen, HSAMB Const. of Road Dheen Saran road to Ram Nagar
Due to Less consolidation path (Path is only 2 Karam)
24 H.S.A.M.B. Xen, HSAMB Const. of Road Dadupur to Tandwali Rajokheri Road
Due to Less consolidation path (Path is only 3 Karam)
25 P.W.D. (B&R)
XEN, B&R Link Road from Adhoya to Barara Basti Due to Less consolidation path
C.M. Announcements (Not Feasible)
Sr. No.
Department Officer at District Level
Name of Work Status
26 P.W.D. (B&R)
XEN, B&R
Const. of PWD Rest House at Dosarka
Due to stay on land acquisition by Punjab & Haryana High Court
27 P.W.D. (B&R)
XEN, B&R
Const. of Road from Chahl Majra to Tandwal, Rajokheri Road
Due to Less consolidation path
28 P.W.D. (B&R)
XEN, B&R
Const. of New Rod from Duliana to Tangali
Due to Less consolidation path
29 P.W.D. (B&R)
XEN, B&R
Const. of Link Road Gola to Dera Saini Majra
Due to Less consolidation path
30 P.W.D. (B&R)
XEN, B&R
Const. of Link Road from Tammanuli to Saha
Due to Less consolidation path
31 Sports DSO Const. of Mini Stadium at Vill. Sardahri
Due to Non availability of land with Gram Panchayat
32 Spots DSO Const. of Mini Stadium at Vill. Barara
Due to Non availability of land
33 Spots DSO Const. of Mini Stadium at Vill. Samlehri
Due to Non availability of land
34 Spots DSO Const. of Stadium for Naraingarh Due to Non availability of land
General Issues
General Issues
1. Irrigation Construction of Siphon on SYL (Irrigation) to prevent flooding in the Naggal areas) and Electrification of all gates from existing manual system to mechanical system on SYL cost. (Appx. Cost 4.25 crore).
2. B&R Construction of parallel flyover on NH 65 at the existing location i.e. from Aggarsen Chowk to Anaj Mandi. (Appx. Cost 4.0 Crore)
3. Urban Dev. Remodelling and reconstruction of Mahavir Park.( 2.0 Crore)
4. B&R Construction of Byepass road from Ghunghat Palace to connecting N.H.I connectingAmritsar and further NH 22 connecting Chandigarh.
5. Relocation of Mini Secretariat (project being discussed with defence authorities for exchange of land).
6. B&R Construction of 40 new houses in old officer colony, Ambala City. Estimated cost is 7.30 crores.
7. B&R Construction of Mini Secretariat at Barara. Proposal already sent to Government.
8. Transport Shifting of Bus Stand from existing location to new location outside the city.
9 B&R Relocation of Motor Market from the existing location opposite Manji Sahib Gurudwara.
10. B&R Construction of building for sub Tehsil/Sub Treasury at Shazadpur.
11. B&R Construction of houses for Tehsildar and Naib Tehsildar at Naraingarh. Estimated cost is 1.44 crores.
General Issues
Thank you…