50 MW METRO WIND POWER PROJECT
50 MW METRO WIND POWER PROJECT
Project Detail
Project Location = Jhimpir Sindh Pakistan
Client Name = Metro Power Company Limited.
EPC Contractor = Nordex Pakistan Pvt Ltd. Descon Engineering Ltd.
50 MW METRO WIND POWER PROJECT
Project Brief Introduction Award of Contract = Sep 8, 2011.
First Amendment to Contract = July 1, 2013.
Second Amendment to Contract = May 15, 2014. PNTC (Preliminary Notice to Commence) = July 8, 2013
PCD (Project Commencement date) establishment = October 9, 2013
PNTC-II (Preliminary Notice to Commence-II) = May 16, 2014
NTC (Notice to Commence) = October 22, 2014
CD (Commencement Date) establishment = Expected March 20, 2015 Project Completion Date (TOC) = Expected June 20, 2016(15 Month from CD)
50 MW METRO WIND POWER PROJECT
Preliminary Works-I (Off Shore & On Shore)
Micrositting Topography Survey for Access Road Design of Causeway for Naulla crossing Geological Survey for WTG Topography Survey for Metro Internal Road Design Initiation for E-BOP Project Management preparation
50 MW METRO WIND POWER PROJECT
Preliminary Works-I Micrositing
50 MW METRO WIND POWER PROJECT
Preliminary Works-I Geological Survey
50 MW METRO WIND POWER PROJECT
Preliminary Works-I Topographical Survey
50 MW METRO WIND POWER PROJECT
Preliminary Works-II (Off Shore) Order Confirmation and Advance payment of E-BOP Equipment
Order Confirmation and Advance payment of Tower Plates
Order Confirmation and Advance payment of Anchor cage (10 nos)Tower Plates
Beside Above, PO has been issued for following and ready for shipment upon CD
1. Tower Flanges 11. Earthing conductor and accessories for WTG. 111. Tower internals (Weld shocked and oil proof plate farms)
50 MW METRO WIND POWER PROJECT
Preliminary Works-II (On Shore)
Construction of Causeways and Access Road
Temporary Site Facility (office and residence)
Lay down Area and Work shop
Civil works for Batch plat (60 & 30 Cu meter)
Batch Plant Installation and Calibration
Apart from above, civil works for Metro Internal roads has almost been completed
50 MW METRO WIND POWER PROJECT
Project Progress
Overall Project Progress
Overall Project Progress = 31.93 %
50 MW METRO WIND POWER PROJECT
Project Progress
Project Management Progress
Overall Project Progress = 0.25 %
Main Highlights Submission of project procedures (HSE, QA/QC, Progress monitoring, Project
Security, Document management Plans etc)Geotech Survey Topography Survey
50 MW METRO WIND POWER PROJECT
Project Progress
Engineering works
Overall Engineering Works Progress = 62.40 (Discipline wise), 3.43 % (Overall)
Civil Engineering works = 53.87 %
E & I Engineering works = 8.808 %
50 MW METRO WIND POWER PROJECT
Project Progress
Procurement works
Overall Procurement Works Progress = 50.8 % (Discipline wise), 23.65 % (Overalll)
Main Procurement Works Highlights PO issuance of complete E-BOP Equipment
PO issuance of Tower Plates PO issuance of Tower FlangesPO issuance of 10 nos Anchor cagesPO issuance of WTG earthing conductor and accessoriesPO issuance of Tower internal (weld socket and oil proof plate farms)
50 MW METRO WIND POWER PROJECT
Project Progress
Construction works
Overall Construction Works Progress = 8.07 % (Discipline wise), 3.68 % (Overall)
Main Civil Works Highlights Completion of Access Road Completion of Causeways Internal Road in progress
50 MW METRO WIND POWER PROJECT
Project Progress
Fabrication works
Overall Fabrication Works Progress = 2.58 % (Discipline wise), 1.17 % (overall)
Main Fabrication Highlights
Marking, Cutting, beveling & Rolling = 10 Bottom , 10 Mid 1 , 3 Mid II Sections Marking, Cutting, beveling = 13 Mid II SectionsTacking & Welding completed = 4 Bottom, 6 Mid I Sections Tacking & Welding in progress = 6 Bottom, 4 Mid I, 3 Mid II Sections
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Construction of Cause Way-I
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Construction of Cause Way-II
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Construction of Cause Way-III
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Access Road
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Access Road
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Access Road
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Temporary Site Facilities
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Batch Plant Installation
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Tower Fabrication
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Tower Fabrication
50 MW METRO WIND POWER PROJECT
Preliminary Works-II Tower Fabrication
50 MW METRO WIND POWER PROJECT
THANK YOU