Engineered  Heavy  Logistics:  Moving Deadlines Forward  

in 

LNG 

Modular  

Construction

SNAME ARCTIC NOVEMBER 20, 2013

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 2/41

2

PRESENTATION CONTENT

1. Modularization

2. Engineered Heavy Logistics

3. LNG: Australia to British Columbia

4. Lessons Learned

5. Questions

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 3/41

3

SAFETY MOMENT

The Mammoet Minute, only six steps

in 60 seconds:

 – Stop

 – Think

 – Look around

 –  Assess the Risk – Take Action

 – Start your task.

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 4/41

44

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 5/41

5

WHY MODULARIZATION?

• Limited / strained labor force

• Limited workforce accommodation

• Limited equipment availability

• Harsh environment

• Limited plot plan area or greenfield development• Restricted geographic location

• Environmentally sensitive

• Limited time window

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 6/41

6

ENGINEERED HEAVY LOGISTICS

6

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 7/41

7

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 8/41

8

HOW DOES MODULARIZATION SAVE TIME?

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 9/41

9

WHAT MUST BE CONSIDERED

BEFORE WE START TO DESIGN MODULES?

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 10/41

10

WHERE WILL THE MODULES BE FABRICATED?

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 11/41

11

 AVAILABILITY OF SUITABLE VESSELS

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 12/41

12

INCORPORATING TRANSPORTATION LOADS IN THEDESIGN OF STRUCTURAL STEEL

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 13/41

13

WHAT SIZE OF MODULES CAN BE REALISTICALLY MOVED?

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 14/41

14

INFRASTRUCTURE LIMITATIONS

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 15/41

15

INFRASTRUCTURE LIMITATIONS

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 16/41

16

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 17/41

17

• Limited / strained local labor force

• Access to offshore labor force

• Remote / “Harsh” environment

• Limited plot area / green field development

• Environmentally sensitive• Schedule / cost / safety driven projects

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 18/41

18

LNG MODULAR CONSTRUCTION EXPERIENCE

 Australia:

• Darwin LNG• Gorgon LNG

• Ichtys LNG Project

• Wheatstone

• Woodside LNG Train

• Woodside Pluto

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 19/41

19

GORGON PROJECT SCOPE OVERVIEW

• 56 Modules (MOD) (SPMT)

• Range between 450 – 6500 Tonnes

• 9 Column's (PDR) (CRANE)

• Range between 138 and 1112 Tonnes

• 233 Pipe racks (PAR) (SPMT / CRANE)

• Range between 12 and 1500 Tonnes

• 32 Substation Buildings (CRANE)

• 6 Compressor/Turbine lines (CRANE)

• 6 Waste Heat Recovery stacks (SPMT/CRANE)

• Additional scope : 140+ small pre-assembled structures (Load-out / Load-in AMC Yard Perth) <100Te

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 20/41

20

GORGON SITE OVERVIEW

MOF

JETTY / MOF

CAUSEWAY

LNG PLANT

FLARE

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 21/41

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 22/41

22

SITE PLAN (EXCL. FLARE + MOF)

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 23/41

23

ROLL ON / ROLL OFF

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 24/41

24

TRAIN 1 LNG MODULE (6000+ TE)

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 25/41

25

2ND LNG TRAIN MODULE (TAJB)

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 26/41

26

 AMINE ABSORBER (1112 TE)

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 27/41

27

 AMINE ABSORBER RIGGING

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 28/41

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 29/41

29

PIPE-RACK TRANSPORT IMPRESSION

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 30/41

30

PIPE-RACK TRANSPORT IMPRESSION

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 31/41

31

INSTALLATION CHALLENGES

Tight operations Constant changing site conditions Unexpected additional scope

Maintaining delivery schedule Large amount of auxiliary equipment Shortage of laydown area

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 32/41

32

LESSONS LEARNED

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 33/41

33

LESSONS LEARNED

1. 100% engineering completion before start of fabrication

• Failure to accomplish this will result in potential for significant increase in on site direct / indirect hours

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 34/41

34

LESSONS LEARNED

2. Early involvement of EHL (Engineered Heavy Logistics)

• Including an EHL as an overall advisor will optimise the logistics chain in time and money

• Optimization of sea fastening, grillage and lashing equipment thru smart engineering

• Determine logistics envelop

• Highlight bottleneck for logistics strategy

• Standardize lifting and transport supports as much as possible for all items

• An EHL approaches design from an optimized construction point of view. Historically, in the offshore

industry, modularisation has been a lump sum based execution strategy. Therefore, the EHL will view

onshore projects from the same mindset.

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 35/41

35

LESSONS LEARNED

3. Select construction strategy at early stage• Build high modules (only SPMT)

• Build lower modules (SPMT with cranes)

• Define maximum weights to optimize crane use (i.e. single crane for all lifts)

• Including legs on the modules allows for flexible placement and storage

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 36/41

36

LESSONS LEARNED

4. Interface management

• Strong technical and operational experience for integration of marine and land contractors

• Involved parties: MWS, marine contractor, customs, Client, site contractor, stevedores, longshoreman,

engineering design contractor, sea fastening fabricator, etc.

• Clearly understand responsibilities of all parties prior to operations

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 37/41

37

LESSONS LEARNED

5. Management of the unexpected

• We do not live in an ideal world. Always have a plan B (and perhaps even C)

• Prepare for receiving cargo day or night

• Sufficient support equipment (module stands, load spreader mats and miscellaneous equipment)

• Where possible, have 2 discharge locations to reduce potential for expensive demurrage for transport

vessel and equipment

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 38/41

38

LESSONS LEARNED

6. Module Alignment

• Module Alignment requires strong spotters to ensure proper positioning and no damage to piperacks

and equipment• There will be misalignment within the module blocks. Differences in temperatures will make every pipe

extend or retrack.

• Make sure you can compensate misalignment of this piping by using sleeves, or spacers and adequate

measuring and shimming equipment is available

• Understand boundaries of approval with all parties

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 39/41

39

LESSONS LEARNED

7. Shipping / Importation of Equipment

• In environmentally sensitive areas special preparations (cleaning of equipment, customs paperwork,

inspections) are required• Custom clearance for modules can be significant scheduling

8. Local Contractors

• Well versed in local labor regulations and requirements

• Experience with camp based work

9. Communication

7/25/2019 233187394-Mammoet-LNG-Modular-Construction.pdf

http://slidepdf.com/reader/full/233187394-mammoet-lng-modular-constructionpdf 40/41