2012-2017Proposed Highway Improvement Program

Public Works and Transportation Committee

April 25, 2012

2

2012-2017 Five Year Highway Improvement Program

Management philosophy sets system priorities:

1. Preservation

2. Modernization

3. Expansion

3

Priority One: PreservationDeveloping a set of projects

ARGUS Pavement Management Software

Keeping tabs on the system

Asset Inventories

$1.6 billion to build

4

Developing the Project SetARGUS Pavement Management System……

……Today is an introduction to ARGUS

5

Pavement Management Goal

Make cost effective decisions

For given 5 year budget levels:

Where repairs are needed

What repair strategies to use

When the repairs should be done

6

Pavement ManagementSystem Components:

County highway database

Automated pavement testing

Repair strategies with costs

Pavement aging prediction

Optimization program

7

County Highway DatabaseContains information on…

Surface type

Surface width

Section area

Traffic volumes

Percentage of trucks

8

Automated Pavement Testing

About 855 lane miles in system

County is divided into quadrants

One quadrant is tested each year

Entire county is covered in four years

9

Automated Pavement Testing

First: Laser Road Surface Tester (RST) measures…

Cracking

Rutting

Ride quality

10

Automated Pavement Testing

Second: Dynaflect deflection tester measures strength and

condition of …

Pavement

Subgrade

11

Repair Strategies and CostsTwo Groups of Roadway Priorities:

(starting with 2010-2014 program analysis)

Four lane roads - 53 miles

Two lane roads - 244 miles

12

Repair Strategies and Costs

Four resurfacing strategies

Three “3R” strategies

Three reconstruction strategies

Associated per-square-yard costs

13

Pavement Aging Prediction Costs

14

ARGUS SummaryPavement Management System does…

Assess the present condition of the system

Estimate future road conditions

Identify and rank road projects

Maximize the condition of the system within the given budget

15

ARGUS Summary …Pavement Management System does not…

Replace professional judgment

Provide certain detailed project-specific

information

16

LCDOT ARGUS results

Started in 1986

System condition has improved from a rating of

68 to 79 (on 100 scale)

Area of backlog and failing pavement has been

reduced from 55% to 9%

17

2012 – 2017Proposed Highway Improvement Program

The following charts to appear in

Section 2 Preservation Projects

18

2012 Traffic Volumes

19

Definitions of Pavement ConditionGood (80 – 100)

Sections may require crack sealing or a thin overlay. These sections do not require immediate attention. Pavement in this category is generally less than 12 years old.

Satisfactory (70-79)Sections may require resurfacing or other rehabilitation in the near future. Pavement is generally 12-14 years old.

Failing (60-69)Will require some type of improvement in the near future to preserve the usability of the surface and avoid the need for reconstruction. This is pavement that is approaching the end of its useable life.

Backlog (10-59)May require surface and base course reconstruction to restore roadway serviceability. Some may require total reconstruction, including reconstruction of the subgrade. Pavement in this category is generally more than 15 years old.

20

Current Pavement Condition = 79Failing

6% Backlog3%

Satisfactory29%

Good62%

21

2012 Pavement Conditions

22

ARGUS optimizes improvements

23

Multiple treatments evaluated

24

System Recommendations2013 - 2017

25

System Preservation Projects 2013-2017

26

2013 ProjectsStreet Name From To Project Type

Darrell Road IL Route 176 Riverwalk Lane Resurfacing

Delany Road 21st Street Wadsworth Road Resurfacing

Dilleys Road Wadsworth Road Stearns School Road Resurfacing

Dilleys Road Stearns School Road IL Route 132 Resurfacing

Hart Road IL Route 14 Lake Cook Road Resurfacing

Kilbourne Road State Line Road Russell Road Resurfacing

Monaville Road Cedar Lake Road IL Route 83 Resurfacing

Wadsworth Road Dilleys Road CP Railroad Tracks Resurfacing

Sunset Avenue IL Route 131 Golf Road Resurfacing

Golf Road Sunset Avenue Greenwood Avenue Resurfacing

Greenwood Avenue Golf Road Sheridan Road Resurfacing

27

2014 ProjectsStreet Name From To Project Type

Fairfield Road Petite Lake Road IL Route 132 Reconstruction

Grass Lake Road 2025' E of Bridge IL Route 59 Resurfacing

Long Grove Road Ela Road Quentin Road Resurfacing

Midlothian Road Winchester Road IL Route 176 Resurfacing

Washington Street UP Railroad Bridge IL Route 131 Resurfacing

Lewis Avenue Glen Flora Avenue IL Route 132 Reconstruction

28

2015 Projects

Street Name From To Project Type

21st Street IL Route 131 Kenosha Road Resurfacing

9th Street Kenosha Road Lewis Avenue Resurfacing

9th Street Lewis Avenue IL Route 137 Resurfacing

Cedar Lake Road IL Route 134 IL Route 120 Reconstruction

Ela Road IL Route 22 IL Route 12 Resurfacing

Ela Road IL Route 12 Cuba Road Resurfacing

Petite Lake Road IL Route 59 Fairfield Road Reconstruction

Quentin Road Long Grove Road Lake Cook Road Resurfacing

Rollins Road Wilson Road Fairfield Road Resurfacing

29

2016 Projects

Street Name From To Project Type

Aptakisic Road Buffalo Grove Road Prairie Road Resurfacing

Aptakisic Road Prairie Road Weiland Road Resurfacing

Aptakisic Road Weiland Road IL Route 21 Resurfacing

Center Street IL Route 83 US Route 45 Resurfacing

Grass Lake Road IL Route 83 Deep Lake Road Resurfacing

Hunt Club Road IL Route 173 Wadsworth Road Resurfacing

Lewis Avenue Dugdale Road IL Route 137 Resurfacing

30

2017 ProjectsStreet Name From To Project Type

Deep Lake Road Grass Lake Road Gelden Road Resurfacing

Hunt Club Road IL Route 132 Dada Drive Resurfacing

Hunt Club Road Dada Drive Washington Street Resurfacing

Hunt Club Road Washington Street Gages Lake Road Resurfacing

Hunt Club Road Gages Lake Road IL Route 120 Resurfacing

Prairie Road IL Route 22 Aptakisic Road Resurfacing

Russell Road Kenosha Road Lewis Avenue Resurfacing

Wilson Road IL Route 120 IL Route 60 Reconstruction

31

Keeping Tabs on the System:Asset Inventories

Pavement and bike facilities, guardrail

Bridges and railroad crossings

Signals and signs

Drainage and stormwater facilities

More…

32

Program resurfaces about12 miles per year

33

Many roads initially built in the 1950s

Inventory: Lane Miles

34

Inventory: Culverts

35

36

Age of Highway Bridges

37

Age of Bridge Deck Surface

38

Age of Bike and Pedestrian Bridges

39

Bridges: Sufficiency Ratings

40

Stormwater Management Facilities

41

By the NumbersInventory: Non-Pavement Assets

14,468 Storm sewer structures

648 Culverts

197 Miles of storm sewer pipe

23,503 Feet of fencing

8,965 Feet of retaining wall

52 Miles of 4’ paved shoulder

18 Miles of guardrail

26 Landscape areas (48 acres)

April 2012

42

Inventory: Signs

43

Inventory: Railroad Crossings

44

Inventory: Signal Controllers

45

Priority One: Preservation

Developing a set of projects

ARGUS Pavement Management Software

Keeping tabs on the system

Asset Inventories

Next Program Presentation:

Priority Two – System Modernization

Priority Three – System Expansion

Recommended