06/14/2011 1
Mechanics of a Pre-Surveillance Analysis
in the World ofGovernment Property
Presented by:Fay Schulte, CPPM
06/14/2011
This presentation provides, a general checklist, as a guideline, to assist in the preparation of a Property Management System Analysis (PMSA) and to explain the pre-requisites and the components of the process based on my current knowledge and personal experiences.
This checklist describes the mechanisms that can be applied across all PMSAs in accordance with the FAR requirements, the compliance of Government contracts and company’s policies and procedures.
In most cases, the information provided in this presentation should be useful but you may need to customize and tailored it to your company’s specific needs.
2
Purpose
06/14/2011
Many of us, in Government Property Management, are all too familiar with the preparation of surveillances/analyses because we have prepared for them numerous times.
We also recognize that there are those who may not have the knowledge or understanding the mechanics of preparing themselves for these analyses, who in general, would attempt to do this on the fly.
3
Introduction
06/14/2011
Have you ever been through an analysis process, whether it’s internal or by the customer, and you are at a lost to determine what the processes are, when preparing yourself for the analysis?
For instance: How would you determine risks and prepare yourself for a positive
outcome in the analysis? How would you collaborate with other departments and help them
understand the risks, values and importance of the analysis to the company?
What are the challenges you would face to effectively communicate to these departments and engage them as part of the analysis process?
4
Introduction cont’d
06/14/2011 5
52.245-1 (June 2007) Government Property◦ includes Limited Risk of Loss
52.245-2 (June 2007) ◦ Installation Operations Services
52.245-9 (June 2007)◦ Use and Charges
DFARS Clause 252.211-7007, Reporting of Government Furnished Equipment (GFE) in the DoD Item Unique Identification (IUID) Registry (November 2008)◦ DCMA administered contracts◦ DoD administered contracts
Other Agencies’ Supplemental Property FAR Clauses
Government Property Clauses
06/14/2011 6
Analyses should be based on the contract and the 10 primary processes
1. Acquisition
2. Receipt of Receiving Government Property
3. Records of Government Property (establish, update)
4. Physical Inventories
5. Subcontractor Control
6. Reports (includes LDDT and annual property report as required by contract)
7. Utilization (includes Movement, Consumption and Storage)
8. Relief of Stewardship Responsibility (disposition of property)
9. Maintenance
10. Property Closeout – Property Disposal
Ten Primary Processes
06/14/2011 7
These additional outcomes/processes are embedded within the Government Property Clause
◦ Property Management-(52.245-1(b))◦ Identification-(under Receipt)◦ Consumption-(under Utilizing)◦ Movement-(under Utilizing)◦ Storage-(under Utilizing)◦ Disposition-(under Property Closeout)◦ LTDD-(under relief of Stewardship) This is really a policy and not a
process!
Additional Processes
06/14/2011 8
PMSA Generic Checklist Pre-Requisite Information
It is essential to maintain a good relationship with your custodians and technical staff. They are the backbone of your analysis because they know where the stuff is.
06/14/2011 9
PMSA Generic Checklist Pre-Requisite Information
06/14/2011 10
PMSA Generic Checklist – Process 1
06/14/2011 11
PMSA Generic Checklist – Process 2
06/14/2011 12
PMSA Generic Checklist – Process 3
06/14/2011 13
PMSA Generic Checklist – Process 4
06/14/2011 14
PMSA Generic Checklist – Process 5
06/14/2011 15
PMSA Generic Checklist – Process 6
06/14/2011 16
PMSA Generic Checklist – Process 7
06/14/2011 17
“It is in the best interest of the Property Manager to continue effective communication with the Program Managers and users of the property to ensure the property are properly utilized as stated in the contract’s SOW”.
PMSA Generic Checklist – Process 8
06/14/2011 18
PMSA Generic Checklist – Process 9
06/14/2011 19
PMSA Generic Checklist – Process 10
06/14/2011 20
Questions?
Mechanics of a Pre-Surveillance Analysis in the World of Government Property
Contact:
Fay K. Schulte, CPPM
(310) 539-6421(310) 722-3430 (M)