Operational Test & EvaluationAugustaWestland 101
Air Operations Inspectorate
Concept: Acquisition – Acceptance – OT&E – Education & Training – Operations
Brief for the Sola Pre-Conference by Col Alfheim CO OT&E AW101
2015-09-21Mission First, Safety Always
LuftforsvaretOT&E AW101
2
Luftforsvaret
Roadmap
• Introduction and Historical Back Ground– Why OT&E– NAWSARH
• OT&E AW101– The Concept– The OT&E-process– Education & Training– Basing and Operations– Risk and Safety– Simulation
• Summary• Q&A
Mission First, Safety Always 2015-09-21
Luftforsvaret
3
OT&E AW101
Why OT&E?
1951 – 1958 Phase Tests
1. Airworthiness (Contractor)
2. Contractor Compliance (AF)
3. Design Refinement (Contractor)
4. Performance and Stability (AF)
5. All Weather (AF)
6. Functional Development (AF)
7. Operational Suitability (User)
8. Unit Operational Employment Testing (User)
1958 – 1972 Category Tests
1. Subsystem Development & Initial Airworthiness ”Prototype or early production aircraft” (Contractor)
2. System Development & Integration of subsystems into complete aircraft ”Early production aircraft” (AFFTC and User)
3. Operational ”Production aircraft” (User with some contractor support)
Mission First, Safety Always 2015-09-21
• OT&E tended to be a QA evaluation after the procurement decision had been made
• Poor performance of weapon systems during Vietnam War
LuftforsvaretOT&E AW101
4
Luftforsvaret
Why OT&E ..
• US Congress mandated that an independent, operational test and evaluation be done prior to a production decision.
• Each US military service established an Operational Test Agency reporting directly to their Chief of Staff
• Independent of program office, DT&E, contractor…• Current Users—operators and maintainers• Evaluation done in Real world conditions
• Joint/Integrated Test Teams - Contractor, DT&E, and User Combined Test Forces
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
5
Luftforsvaret
Evolutionary Test Strategy
Mission First, Safety Always 2015-09-21
Concept Technology Development
System Development
Production & Deployment
Operations & Support
User Needs, Technology, Opportunities, and Politics…
IOC FOCDT&E
OT&E
EOA
Integrated DT&E and OT&E
TD&EIOA FOT&EIOT&
E
AT&EQT&E
LuftforsvaretOT&E AW101
6
Luftforsvaret
Kebnekaise…
Mission First, Safety Always 2015-09-21
Luftforsvaret
7
OT&E AW101
OT&E Purpose
Determine system operational effectiveness & suitability• Operationally realistic
conditions• Operated and maintained by
typical Users• Production representative
systems• Using delivered equipments,
training, data, mission planning, etc
• Use of certified models, simulations, and data bases
Answer Critical Operational Issues• Documenting deficiencies• Recommend system
enhancements• Provide information for
refining:– Logistics support requirements– Software support– Training– Doctrine– Tactics,Techniques, and
Procedures
Mission First, Safety Always 2015-09-21
All hardware/software modifications that change delivered system performance must be tested and evaluated
Luftforsvaret OT&E AW101LOI
8
Air Force Regulations
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
9
Luftforsvaret
OrganizationSquadron• “Small/simple OT&E”• P-3 MX-20 (EO/IR) og TCDL• Raven UAS
Multi National OT&E• “Same type config” • F-16 (M6.5)• F-35• C-130J (Block 7.0/8.1)
Dedicated OT&E unit• “Large/complex OT&E” • NH90 (2010)• AW101 (2015)
Mission First, Safety Always 2015-09-21
Luftforsvaret OT&E AW101LOI
10
Contract signed 19. Dec 2013
MoJ & AW
NAWSARH-PROJECT – TIMELINE
• “Pre-phase” (White paper, studies, studies new studies, NH 90 option etc, etc) 1997 – 2007• Pre-study (“QA1 study & QA2 study”) 2007 – 2010• Parliament decision Dec 2010• Competition Timeline:
• Pre Qualification (AW, EC, SK, NHI, RHI) Dec 2011
User Needs, Technology, Opportunities, and Politics
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
11
Luftforsvaret
BACKGROUND - CONTRACT
• AW101 – 612 to replace Sea King by end of 2020
– First delivery early 2017
– RNoAF to remain the operator
• SAR-service to be maintained on all 6 bases
• «Turn Key provider» solution
– Availability as main KPI
– All new Integrated Logistic Support solution (PBL)
– Train-the-trainer concept.
Mission First, Safety Always 2015-09-21
Luftforsvaret
Full Ice Protection 30minute Run Dry Transmission
Sliding door, Crew Door & Ramp
Ground Clearance Ca. 500mm
183 cm Cabin height
3 Observation Windows
AW101-612 – KEY FEATURES
Active Vibration Attenuation (ACSR)
30minute Dry Run capability XMSNs
BERP III MRB
3 Observation Windows
Crashworthy Structure, Seats,
Fuel System
AW101-611 “CSAR” as baseline for
certification
Luftforsvaret
No folding MRB
Engine Configuration (3x GE CT7-8E)
New Automatic Flight Control System*
Fully articulated Tail Rotor (NEW)
New AESA 3x Flat Panel Radar
Low maintenance workload program
* Including Hover Trim Controller (HTC)
AW101-612 – KEY FEATURES (NORWAY)
Luftforsvaret
DETECTION AESA Radar (Simultaneous Modes)
Independent Weather Radar HD Electro Optics/IR Sensor DF & Mobile Phone Detection
TERRAIN AWARENESS HTAWS (Fully Integrated)
3 x Digital Map (Elevation Data) Integrated Synthetic Vision
Low Height System (2 x Rad Alt) Configurable S.A. Overlays
OBSTACLE DETECTION Laser Obstacle Warning System
Obstacle Proximity LiDAR Integrated Synthetic Vision
AREA NAVIGATION 3 x Integrated Digital Maps
High Integrity Navigation Suite 2 x Civil GPS, Integrated RadNav
Automatic Nav. Accuracy Monitoring Jeppesen Database
VFR / IFR Navigation AFCS Modes
TRAFFIC AWARENESS Integrated TCAS II (Overlay on
Map) ADS-B Tx Transmissions
AIS Tx/Rx Capability IFF Transponder
Growth Option for Link 16
AW101-612 – KEY SA FEATURES
Luftforsvaret
SAR LAYOUT
Flexible Cabin Arrangement
Wireless Passenger & Crew Intercom
Crew Galley & Relief Facilities
Rear Ramp Stowage Area
Adjustable, Rotating & Traversing Crew
Seats
Flexible / Adaptable Medical Rail System
Wet Storage Adjacent to Rescue
Station
Stretcher Compatibility with
Ground Ambulance
Dedicated System Operator Console
Area
Dual Trauma Station (Gas & Air Provisions)
AW101-612 – KEY CABIN FEATURES
LuftforsvaretOT&E AW101
16
Luftforsvaret
ILS
P7661
HRS - communication
Training
SAR Bases
Hospital Helipads
GFE / GFA
Florø
Helicopters
The NAWSARH Project
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
17
Luftforsvaret
OT&E AW101
Sola (40)
COM IAO
OT&E
CoS RNoAF
Air Staff
Training/Sim
Tech/Maint
P7661Air Sys /Heli
LogisticsNAWSARH
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
18
Luftforsvaret
NAWSARH / OT&E AW101 - timeline
• 2014 PDR• 2015 CDR • 2016
Planning, preparation, and training for The Mission:
1. OT&E AW101
2. Train 330 SQN
Mission First, Safety Always 2015-09-21
• Initial OT&E AW101 org• Final OT&E AW101 org
LuftforsvaretOT&E AW101
19
Luftforsvaret
Mission First, Safety Always 2015-09-21
”The Big Picture”2015 2016 2017 2018 2019 2020 2021
1 Initial
FFS and Helicopters
OT&Ephases
TrainingSchedule (Base based)
3 Final
2 Follow On
Train 330 SQN
Luftforsvaret OT&E AW101LOI
20
Base 0 Sola#1 2017 OT&E and Training
Base 1 Sola#1 2018 Base 2 Ørland#2 2018
Base 3 Banak#1 2019
Base 4 Bodø#2 2019
Base 5 Rygge#1 2020
Base 6 Florø#2 2020
1 - 2018
2 - 2018
1 - 2019
2 - 2019
1 -2020
2 - 2020
Sea King RoA 20 rescuees~ 53 nm
Sea King RoA 2 rescues ~ 210+ nm
AW101 RoA 2 rescuees. >310nmRoA 20 rescuees >250 nm
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
21
Luftforsvaret
Mission First, Safety Always 2015-09-21
”A few details”2015 2016 2017 2018 2019 2020 2021
1 Initial
FFS and Helicopters
OT&Ephases
UKUK / ZVCN / ZVTrainingSchedule (Base based)
3 Final
2 Follow On
ZVOL
NA
BORY
FL
LuftforsvaretOT&E AW101
22
Luftforsvaret
OT&E Objectives
• Determine the AW101 helicopter actual capabilities, limitations, operational effectiveness and suitability
• Determine if the requirements in the Statement Of Intent (SOI) have been met
• Verify that the AW101 helicopter is properly manned and equipped
• Verify that the quality of training and logistics meet operational requirements for employment as a SAR system (operational suitability)
• Develop tactics, techniques and procedures (TTPs) • Establish the basis for further development of
organization, systems, TTPs by follow on OT&E activities at a later stage
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
23
Luftforsvaret
AW101 OT&E Phases
Phase 1• Initial – IOT&E (Basic SAR capability day & night).
Phase 2• Follow on – FOT&E (Full SAR capability day &
night/all weather. It will run in parallel with TR/TQP).
Phase 3• Final – FOT&E is planned to establish the full potential
of the AW101 for the remaining capabilities for military missions, support to special police missions, specialized firefighting, emergency relief, environmental protection, and other missions of public interest aimed at protecting assets or the environment.
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
24
Luftforsvaret
Critical Operational Issues (COI)
• COI-1: Is the AW101 system capable and available to meet national readiness requirements?
• COI-2: Can the AW101 system provide Search and Rescue capability in the Norwegian maritime environment?
• COI-3: Can the AW101 system provide Search and Rescue capability in the Norwegian land environment?
• COI-4: Can the AW101 system provide Helicopter Emergency Medical Service (HEMS) capability across NSRR?
• COI-5: Is the AW101 system capable of conducting and supporting national contingency operations?
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
25
Luftforsvaret
COI/MOE-MOS/MOP Structure
Mission First, Safety Always 2015-09-21
COI 1COI 1
COI 1COI 1
COI 5
MOS 1MOE 1COI 1
COI 1COI 1
COI 1MOS 5.6
MOE 1MOE 5.3
MOP 5.3.2 MOP 5.6.1 MOP 5.6.2MOP 5.3.1
Critical Operational Issue (COI)
Measure of Effectiveness (MOE) Measure of Suitability (MOS)
• Measure of Performance (MOP)
» Demonstrate – show operation» Determine/Measure - quantitative» Assess/Evaluate – qualitative
» Verify – quantitative versus ORCD» Determine – quantitative versus prediction
LuftforsvaretOT&E AW101
26
Luftforsvaret
RNoAF OT&E Tool
SharkScribe• Cooperation w/HOTEF, Canada
Aim• Tool to manage OT&E activity
• Automates OT&E process– Make test concept– Plan test activity (Sorties)– Log test data– Generate test card– Generate reports
• Standardize processes– COI – Critical Operational Issue– MOE – Measure of Effectiveness– MOS – Measure of Suitability– MOP – Measure of Performance / (Assessment)
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
27
Luftforsvaret
Conclusion Recommendation Terminology
ConclusionRecommendat
ionTerminology
RecommendationLevel
ACCEPTABLE No action No action
ACCEPTABLE / SATISFACTORY
SomethingCOULDbe done
DESIRABLE
ACCEPTABLE / UNSATISFACTOR
Y
SomethingSHOULDbe done
HIGHLYDESIRABLE
UNACCEPTABLE
SomethingMUST
be doneESSENTIAL
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
28
Luftforsvaret
AW101 OT&E Reporting
Mission First, Safety Always 2015-09-21
• CO OT&E AW101 is reporting to COM IAO after the completion of each campaign, COI and phase.
• COM IAO reports to CoS RNoAF the AW101 helicopter’s actual capabilities, operational effectiveness and operational suitability.
• Chief of Staff RNoAF will decide, based on the recommendations derived from the OT&E process if, how, and when the RNoAF can deploy the AW101 helicopter for live operations.
CO OT&E AW101 COM IAO CoS RNoAF
Luftforsvaret
29
OT&E AW101
Credible– Objective– Unbiased
Realistic– Typical operators– Realistic environment– Delivered equipments
Mission First, Safety Always 2015-09-21
Cost Effective– Efficient– Effective– Timely
LuftforsvaretOT&E AW101
30
Luftforsvaret
OT&E Tenents
• Objective, Dedicated and Independent– Representing the operational users– Separate from developing, procuring, and contractors– Minimize influence of acquisition managers
• Integral part of combined test teams– Involved as early as possible with DT&E
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
31
Luftforsvaret
AW101 OT&E
• Introduction of a new system tends to introduce new risks – OT&E Effectiveness and Suitability testing tends to be
hazardous– More people injured in other tests than in flight tests…
• Commence testing from a known and safe point• Incremental approach• Conduct a risk management analysis• Pre-determine actions for undesirable results• Have defined “knock-it-off” test criteria• Analyze results before proceeding to next test point
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
32
Luftforsvaret
RiskMission First, Safety Always
Mission First, Safety Always 2015-09-21
1 Identify Risk (Hazard)2 Analyze Risk (Hazard) – Cause & effect3 Eliminate/Control Risk (Hazard) – minimize probability & severity4 Establish emergency procedure
LuftforsvaretOT&E AW101
33
Luftforsvaret Risk MatrixMission First, Safety Always
RAC 1: Extremely High (R<=25)RAC 2: High (R<=20)RAC 3: Medium (R<=15)RAC 4: Low (R<=10)RAC 5: Acceptable (R<=5)
Mission First, Safety Always 2015-09-21
Experience/Expertise
Residual Risk =Assumed + Unidentified
LuftforsvaretOT&E AW101
34
Luftforsvaret
OT&E focus areas
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
35
Luftforsvaret
System Concepts – Hardware/Software
• Segregated
• Federated– Interfaces between subsystems– 1553 bus (typical)
• Integrated
• Complex• More difficult to relate cause and effect
– Automatic Diagnostic System (ADS)
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
36
Luftforsvaret
Simulation (FFS)
• Helps to understand the system• Predict performance• Increased efficiency / Reduce time and cost
Limited test articles / locations• Provide otherwise unattainable and immeasurable
data (Safety)• Be prepared – “What if?” Plan a “build-up” approach• Develop and train for test techniques• Development of test objectives, constrains, and criteria
Simulation models are designed to provide answers at a given abstraction level
Mission First, Safety Always 2015-09-21
LuftforsvaretOT&E AW101
37
Luftforsvaret
”In Short”
Concept for fielding of the NAWSARH AW101 in RNoAF
• OT&E AW101 will as a dedicated unit:– Conduct OT&E planned in three phases (IOT&E, FOT&E, and
“Final OT&E”)– Train 330 Sqn personnel (in phase two) to stand up one
SAR-base at the time (ZV-OL-NA-BO-RY-FL)
– Utilize FFS at ZV for:• Initial training TR/TQP• OT&E msn prep• Annual training ATP/CTP
– Support the safe and efficient introduction of AW101 into service
Mission First, Safety Always 2015-09-21
38
Operational Test & EvaluationAugustaWestland 101
Air Operations Inspectorate
OT&E AW101: “To Transform 40+ yrs of Sea King SAR-experience to AW101 in 4 yrs”
Brief for the Sola Pre-Conference by Col Alfheim CO OT&E AW101
2015-09-21Mission First, Safety Always
Q&A