View
680
Download
0
Category
Preview:
Citation preview
© 2012 pmwares – All rights reserved
Earned Value Management in Action
Vivek Prakash – Aug, 16, 2012
© 2012 pmwares – All rights reserved
Earned Value Management
EVM Terms Explanation
Planned Value (PV) Estimated value of the work planned to be spent
as of today.
Earned Value (EV) Value of the work that is completed as of today
(PV of completed work)
Actual Cost (AC) Total cost actually incurred as of today
Budget at Completion (BAC) Total planned value of the project
Estimate at Completion (EAC) Forecasted total project cost as of today
Estimate to Complete (ETC) Estimated cost of the remaining work
Variance at Completion (VAC) The variance of total project cost project as of
today
Definitions
© 2012 pmwares – All rights reserved
Earned Value Management
EVM Terms EVM Formula Explanation
Schedule Variance SV = EV - PV Measure of schedule performance.
–ve value indicate delay
Cost Variance CV = EV - AC Measure of cost performance. –ve
value indicate cost overrun
Schedule Performance
Index
SPI = EV/PV Measure of progress achieved.
Value less than 1 indicate delay
Cost Performance
Index
CPI = EV/AC Measure of value of the work
completed. Value less than 1
indicate cost overun
To Complete
Performance Index
TCPI =
(BAC-EV)
(BAC-AC)
Measure of cost performance to be
achieved on remaining work to
meet project objectives
Estimate to Complete ETC = EAC - AC Estimated cost of remaining work
Formulas
© 2012 pmwares – All rights reserved
Earned Value Management
EVM Terms EVM Formula Explanation
Variance at
Completion
VAC = BAC - EAC Variance of total projected cost from
budget
Estimate at
Completion
(EAC)
AC + Bottom up ETC When original estimates are
fundamentally flawed
BAC
Cumulative CPI
Observing no variance, will continue
with same expenditure rate
AC + (BAC-EV) Variance observed as of now will not be
observed in future. Will complete the
project in remaining budget
AC + [(BAC-EV)/
(Cum.CPI x Cum.SPI)]
Current variance trends will continue.
Remaining budget is modified with cost
and schedule performance
Formulas
© 2012 pmwares – All rights reserved
Time
Cost baseline
Cost
Earned Value Management
© 2012 pmwares – All rights reserved
Actuals
Cost baseline
Earned Value Management
Time
Cost
© 2012 pmwares – All rights reserved
Actuals
Earned
Cost baseline
Earned Value Management
Time
Cost
© 2012 pmwares – All rights reserved
Actuals
Cost baseline PV
AC
EV
Earned Value Management
Time
Cost
Earned
© 2012 pmwares – All rights reserved
Actuals
Earned
Schedule variance in $
Cost baseline
Earned Value Management
PV
EV
AC
Time
Cost
© 2012 pmwares – All rights reserved
Cost baseline
Actuals
Cost variance
PV
AC
EV
Time
Cost
Earned
Earned Value Management
© 2012 pmwares – All rights reserved
Earned Value Management
Side 1
Side 2
Side 3
Side 4
Task Week 1 Week 2 Week 3 Week 4 Status Cost incurred
Side 1 AS------AF Complete $1000 Side 2 AS--------PF Half done $800
Side 3 PS-----------PF To start
Side 4 PS-----------PF To start
AS – Actual Start, AF – Actual Finish, PS – Planned Start, PF – Planned Finish
A wall is to be constructed around a square plot. Each side takes 1 week with
estimated budget of $1,000. You have only one crew (with 1 supervisor and 3
workers), therefore construction is planned in sequence. After 1st week, a worker
fell ill. We are not at end of 2nd week and status of the project is as below
Status at the end of 2nd Week
© 2012 pmwares – All rights reserved
# Terms Values Comments
1. PV
2. AC
3. EV
4. BAC
5. CV
5. SV
6. CPI
7. SPI
8. EAC
9. ETC
10. VAC
Earned Value Management
© 2012 pmwares – All rights reserved
# Terms Values Comments
1. PV = 1000+1000 2000 We planned to do work worth $2000
2. AC = 1000+800 1800 We actually spent $1800
3. EV = 1000+500 1500 We actually completed $1500 worth of work
4. BAC 4000 Originally budgeted to complete in $4000
5. CV (EV-AC) = 1500 – 1800 -300 We are over budget by $300
5. SV (EV-PV) = 1500 – 2000 -500 We are behind schedule
6. CPI (EV/AC) = 1500/1800 0.833 We are getting 83 cents out of every dollar
invested
7. SPI (EV/PV) = 1500/2000 0.75 We are progressing @ 75%
8. EAC (BAC/CPI) = 4000/0.833 4801 We currently estimate that the total project
will cost $4801
9. ETC (EAC–AC) = 4801 – 1800 3001 We currently estimate that we have to spend
$3001 to finish the project
10. VAC (BAC–EAC) = 4000 – 4801 -801 We currently estimate that we will spend
$801 more than budgeted.
Earned Value Management
What it needs to implement EVM
Discipline
Planning
Stable baseline
Periodic tracking
Gathering data of actual progress from team
Actual Efforts & Remaining Efforts
Updating plan
Reporting
Measuring variance
Action Plan
Reporting to stakeholders
© 2012 pmwares – All rights reserved
Recommended