PRESENTED BY :

ARC. A. A. OSEZAY (M.D) CEEZALI

•  Name: Arc. A. Aliyu Osezay (CEO Ceezali Ltd, Abuja-Nigeria)

•  Project: Masaka-Mpape, Abuja Road (and Adjoining Districts)

•  PROJECT NEEDS: Equipment: Dozers, Graders, Loaders, Batching Plant, Asphalt Plant and Pavers.

Financing: Ceezali Ltd, First Bank Plc, FCT, and Investors.

Partners: Ceezali Ltd, First Bank Plc and FCT.

Summary: •  The proposed Masaka-Mpape, Abuja Ring Road is to serve as a

connecting route from Masaka in Nasarawa State via Mpape to Abuja. The total length of the road is approximately 26 km; and the duration of the road project is 2 years.

a

bc  

d  

road    layout  

Objective: •  To decongest Abuja-Keffi Road which is causing a colossal loss of lives

as a result of incessant traffic accidents; loss of man-hour in productivity; and stress, arising from locked-up traffic. The traffic logjam on this road deteriorates during the morning and evening rush hours.

•  The high density of the population along Abuja-Keffi road axis contributes significantly to the chaotic traffic situation.

•  The construction of the proposed Masaka-Mpape Ring Road will achieve the following.

1. Provide an alternative route for commuters and travelers. 2. Minimize security threats posed by the over-flow of heavy traffic around the Three Arms Zone, where the seat of government is located 3. Open up vast area for the development of additional Districts.

district  layout  

Name of Project: •  MASAKA-MPAPE, ABUJA RING ROAD(and Adjoining Districts) Location: •  The Road starts from Masaka, Nasarawa State via Mpape to Abuja, FCT

a

d  

a  

satellite  map  

Project Implementation: •  The Federal Government of Nigeria is responsible for the Implementation

of the Project. Total Project Cost: •  N24Billion ($150Million) Project Structure: •  DBT(Design Build and Transfer) Economic Benefit: •  The project will generate 500 employment during the construction period •  Open up new Districts to attract investors •  Generate more revenue to the Federal Capital Territory of Nigeria

If you have questions, comments or suggestion, please don’t hesitate to contact:

Ceezali Limited,

No 24, Thabatsaka, By Britsh Village, Wuse II, Abuja FCT, Nigeria

Tel: +2348033325553, +2348078756968

www.ceezali.com ceo@ceezali.com